CHAPTER X.

EXAMINATION, REPAIR, AND STRENGTHENING OF RIVETED BRIDGES.

In the preceding chapters defects of various kinds to which riveted

bridgework is liable have been more particularly dealt with; it is now

proposed to consider the examination of such structures, following this

by a reference to methods of repair and strengthening, leaving the

treatment of other classes of bridgework to be developed under their

proper headings, though some of the remarks immediately following will

apply to all.

The exhaustive survey of a bridge is only to be made after considerable

experience in the work, but it may be stated that in looking for defects

it is well to seek where they are least expected, till, with practice,

one knows better where to direct attention. When examining with a view

to pronouncing an opinion upon the fitness of the structure to remain in

place, if in any real doubt, it is wise to give a casting vote against

it; and finally it may be said that upon taking down a bridge condemned

for any one or more defects, it should be examined for worse. This may

seem to be somewhat pessimistic, but is based upon the teachings of

experience.

Preliminary examination of a bridge may reveal such faults or weaknesses

as at once to ensure its condemnation; but if this is not the case, and

there is a reasonable probability that the structure may be given a

fresh lease of life, it will, for the purpose of estimating the

strength, or for possible repairs, commonly be desirable to secure

precise particulars of the existing structure independently of any

drawings that may be in existence, and which will very probably be

incorrect, the finished work, if old, seldom agreeing with the contract

drawings. A final decision may in this case be deferred till after the

measuring up has been completed, the condition of the structure becoming

more familiar in the process.

It is desirable first to ascertain whether the bridge remains in good

form, whether the camber of girders appears to be what might be

expected, or agreeable with existing records, though much reliance must

not be placed upon figured cambers, it being quite common for girders to

leave the bridge yards with the camber something other than that

intended. The deflections under live load will also be observed, and

compared with the calculated result, or checked by judgment. The

calculations upon which strength and deflections are based will, of

course, refer to the actual sections, which are sometimes a little

difficult to ascertain if there has been irregular rusting. In

continuous girders also, levels having been taken, allowance should be

made for effects of settlement, if any; and with arches evidence of

movement of the piers or abutments sought for, with the like object. It

is seldom that the main flanges of girders show signs of weakness,

unless from flexure in the case of long and narrow top members,

insufficiently stiffened; but there may be want of truth from other

causes already dealt with. In plate girders the webs should be most

carefully scanned for possible cracks, particularly where cross-girders

are connected, and along the upper edges of bottom flange angles, if the

floor rest upon the flange. All riveted connections, of course, need

close attention, both for straining effects, where there is a liability

to wracking, and to detect loose rivets. Loose rivets and want of

tightness in other parts of the work may frequently be detected at

sight by a reddish bloom which appears on the neighbouring surfaces,

caused by rust working out and spreading under the effects of weather;

it may be seen round rivet-heads or along the edges of angle-bars, or

other parts where there is movement. Loose rivets, though generally to

be detected also by the hammer, may perhaps in the case of thin-webbed

cross-girders be working in the web-thickness only, possibly to a

considerable extent. This, if not otherwise evident, may sometimes be

detected by simultaneous deflection tests--with rods--at the top and

bottom flanges of a girder, at the same distance from the bearings. Any

difference in the readings may indicate loose web-rivets, or possibly a

tear in the web running parallel to the flange angles.

Bracings between girders are very apt to display a rich harvest of

working rivets. Cross-girders and longitudinals also may have loose

rivets at their connections, and be very badly wasted, with quite

possibly cracks in the webs, or other defects already enlarged upon.

The condition of the road upon the bridge will frequently be an

indication of the state of the floor which carries it; or the existence

of rail-joints which are working badly may very properly lead to a

critical examination of the girder-work immediately below, as this is a

fruitful source of damage in light constructions. Floor-plates, where

these exist, should be scanned for leakages, drainage nozzles, and

guttering, to see that they are free, the attachments of the latter

being often loose and unsatisfactory.

Trough floors may be expected to show loose rivets near the ends, with a

probability of excessive leakage where they abut against the webs of

supporting girders.

Floor plates resting upon abutments or piers, being very liable to

serious decay, require attention, and girder-work entering masonry

should receive close scrutiny, any obstruction to a sufficient

examination being removed so far as is judged sufficient for the

purpose. The structure should, of course, be closely watched during the

passage of live load for any signs of abnormal movement, excessive

vibration, or lurching.

In addition to seeking for these various defects, or others which have

been referred to in these pages at length, it will be well always to be

alive to the possibility of faults to be seen for the first time, or of

which the author has furnished no instance.

Having formed a reliable opinion as to the state of the bridge, this, if

satisfactory, may leave to be determined only the question of strength

relative to the loads carried. It is apparent that stress limits

suitable for a new structure, which has all its life before it, of

purpose moderate to cover possible deteriorations, the growth of loads,

and other adverse influences, may to avoid immediate reconstruction,

reasonably be permitted of a higher value for a further term of years in

the case of a structure which it is known has for a considerable period

behaved well, and remains in good condition. What this higher value may

be will be greatly influenced by the circumstances of each case, and,

being largely a matter of judgment, may be expected to vary with

different engineers. Experience shows, however, that the nominal unit

stress in an old bridge may be a very considerable amount in excess of

that allowed for new work, without, of necessity, showing any ill

effects; and the author is of opinion that for old bridges in good

condition it is quite prudent to allow an excess of 33 per cent. beyond

that permissible for a new design. If the structure is too weak to

satisfy this modified condition, it may be possible to bring it within

the stress limit by a reduction of ballast or other removable dead

weight. If this expedient does not promise to be satisfactory, or the

bridge shows actual signs of weakness, or palpable defects, it will be

necessary to deal with the question of repair, strengthening, or

reconstruction.

The repair of built up bridgework resolves itself largely into a matter

of replacing loose rivets by cutting these out, rhymering the holes, if

desirable, and again riveting. It will often be sufficient to do this

with no particular precautions as to bolting up temporarily; the rivets

having been loose, may very well be spared for a time. In re-riveting

cross-girder connections it may, however, be imperative to remove all

the rivets, bolting up securely as this is done, in order to make a

tight job, taking out each bolt in turn as required, and again filling

the holes; or it may be well in a bad case first to remove all loose

rivets, substituting good bolts, in order that work which has gone out

of shape owing to defective rivets may first be brought true.

Cross-girder webs, cracked vertically or nearly so, are commonly

repaired with splice-plates on either side; but in doing this it is

undesirable to add plates of excessive thickness relative to the

web--probably poor--as by an abrupt change of web section it appears not

unlikely a fresh break may be favoured.

[Illustration: FIG. 60.]

[Illustration: FIG. 61.]

[Illustration: FIG. 62.]

[Illustration: FIG. 63.]

Replacing wasted flange-plates, or adding new plates to those which

exist, is occasionally resorted to in the case of main girders, the

flanges of which are sufficiently accessible, but the operation is

difficult, takes some little time, and should only be attempted under

the constant supervision of a thoroughly capable man. When done, if the

girder has not been relieved of load by staging, the stress under full

load will be unequally distributed between the old and the new section,

the old always taking more by the amount of the dead-load stress

previously carried. The method which the author has seen applied to

lattice girders of about 80 feet span, having good angle-bars in the

flanges, with a shallow vertical web for attachment of diagonals,

consisted in first cutting out the old flange rivets, and substituting

bolts well screwed up, till all the rivets necessary had been removed.

The new plate length having been prepared, was, on a Sunday, during a

few hours’ cessation of traffic, marked off, the temporary bolts being

removed for the purpose, and then replaced. After the plate had been

drilled, on a later Sunday, it was finally put into position, bolted up,

and riveted at leisure; cover-plates make additional trouble, but are

dealt with on the same principle. The method as shown in Fig. 60 is,

however, barely practicable for so many plates. It is preferable, if it

is proposed to add section, to do this with as little interference as

possible with existing rivets of importance. This may be accomplished,

if the existing plates are not too wasted at their edges, by riveting on

new strips or angle-bars (see Figs. 61 to 63). Occasionally the strength

of a girder is increased by the addition to the top or bottom boom of

material in such a form as sensibly to increase the depth, and thus,

while adding increased section to one boom, to reduce the stress in

each, though to dissimilar amounts. By this device also the relief is

effective only as regards the live-load stress; under dead load only the

new material does no work, provided, of course, that no relief staging

was used during the alterations. For girders carrying any considerable

proportion of dead load the method is very inefficient, though for

others, in which the live load is relatively large, the result should be

more satisfactory.

As this question of adding new section to old is of much importance in

dealing with repairs and strengthening operations, a few general remarks

upon the subject will be pertinent. The difficulty in such work commonly

is to cause the new to render any considerable assistance to the old in

those cases which occur in practice. If a bar be imagined under

longitudinal stress varying between 0 and a maximum, then, if the area

of the piece be increased at the time when it takes no stress, its

capacity for resisting the maximum amount will be increased, and for

added material of similar elasticity the unit stress proportionately

reduced. If, however, the load on the bar does not vary, the mere

addition of metal will not relieve the original section in any degree.

To take a third case, of the maximum being twice the minimum load, it

will be necessary, in order to lower the maximum unit stress by 25 per

cent., to double the original section of the bar if, as supposed, the

extra metal has been added to the piece when under the smaller load, so

that the new section is only effective in assisting to carry the

remainder of the load at such times as it may be imposed. The

relationship stands thus:--

Live load New area

---------------- × -------------- = relief.

Live + dead load New + old area

These statements will be true under the conditions named, within the

elastic limit of the material; but some advantage would be derived in

the second case, and a more marked benefit in the third, if the load

assumed to be a maximum were exceeded, or if the composite bar were

tested to destruction; as, however, these effects would be outside the

limiting conditions imposed, it must be a matter of judgment as to how

far this reserve of strength may be considered of value.

If, instead of simply adding section to the bar, some part of the

constant load is put upon the new section by the manner of attachment,

the combination will, of course, be more effective.

To apply these considerations and illustrate the way in which the two

methods of adding flange section work out when reduced to figures, the

case will be supposed of a girder 6 feet deep, carrying a load of which

one-third is dead and two-thirds live. To the flanges of this girder are

added plates equal to 50 per cent. of the original areas, in order to

reduce the stress of 7 tons per square inch to which the girder before

strengthening is liable, the depth remaining substantially unaltered.

With dead load only the original section would be stressed to 2·3 tons

per square inch, the new section being then unstressed. Under full load

the new and old material take 3·1 tons per square inch additional,

making the modified stress on the original section 5·4 tons per square

inch, as against 7 tons; or a reduction of 22 per cent. This compares

with 33 per cent., the relief due to 50 per cent. increase of flange

area under ordinary conditions of stress distribution.

Let the second method of strengthening the girder now be considered,

using, for purposes of comparison, the same total amount of new material

to increase the girder depth by an addition to the top flange. This

section will be equal to the area of one flange, which, though it may

be applied in many different ways, giving a greater or a less increase

to the depth, would probably be used in some such manner as that shown

in Fig. 64, increasing the effective depth for live-load stress by

nearly 10 inches.

[Illustration: FIG. 64.]

The added material will, as in the previous case, leave the dead-load

stress unaltered, or 2·3 tons per square inch. The stress in the bottom

flange due to live load will, however, now be 4·1 tons per square inch,

making a total stress of 6·4 tons per square inch, against 7 tons--the

original stress. The reduction here is 8 per cent. only, as compared

with 12 per cent., the relief due, under ordinary conditions, to an

increase of effective depth from 6 feet to 6 feet 10 inches, and by the

use of additional material, equal, as before, to one-half of the total

flange areas before the alteration.

The effect on the top flange need not be here gone into in detail, but

it may be said that, owing to the increase of gross section and of

depth, the ultimate stresses of both the new and old material are

greatly less than as given for the bottom flange.

Girders strengthened by the first of these two methods would, it is

probable, if tested to destruction, give results more nearly in accord

with the actual percentage increase of flange section, plastic

deformation of the metal, before failure, tending to reduce the

differences of stress on the new and old material of the sections.

[Illustration: FIGS. 65 and 66.]

Web members of lattice girders may, if weak, sometimes be dealt with by

the introduction of supplementary bars, parallel to and between the old

members, or by the addition of strips or angles to the existing

diagonals. The treatment will be largely influenced by the nature of the

old detail, which may lend itself to some one arrangement much better

than to any other.

End riveting of web members may, if it has become loose, be dealt with

by simply rhymering the holes a size larger, and re-riveting in the best

manner, if the stresses are not excessive; or it may be necessary to

devise some additional attachments by which new rivets are brought into

use (see Figs. 65 and 66). The effective relief due to supplementary

rivets will be influenced by similar considerations to those governing

increase of section.

[Illustration: FIG. 67.]

[Illustration: FIG. 68.]

Old structures are very frequently deficient in bracing, which may, in

such cases, be advantageously introduced; or girders individually weak

may be rendered collectively efficient by suitable bracing. In

considering the advisability of this, however, the case should be viewed

with regard to the possible effects of such members, as already dealt

with in the chapter relating to these questions. There it has been

pointed out that bracing between a system of parallel girders may have

the effect, under live load, of increasing the stress on the outer

girders due to twisting of the structure as a whole, though the inner

girders will, except for full loading of the whole bridge, be advantaged

as to stress values, and in any event bettered by being held up to their

work. The effect upon the outer girders may be met by increasing their

strength, if this appears to be necessary. In all such alterations the

detail should be schemed with special care to ensure simplicity in

execution, smith’s work being rigorously avoided. A good arrangement for

supplementary bracing between plate-girders, which gives little trouble

in carrying out, is shown in Fig. 67; or where the stiffeners of such

girders are in line across the bridge, the detail given in Fig. 68 may

involve less expenditure. Difficulties may be experienced in riveting,

unless great care is taken in the positioning of rivets. Fitting-bolts

are only to be relied upon as such, if they really justify the name;

they are, though easy to specify, by no means easy to secure under the

conditions of practical work. Weak cross-girders may make

alterations--in some cases considerable--necessary, to rectify the

defect of strength. The removal of old girders to make room for new is

seldom resorted to, unless the existing detail renders this a simple

operation; but it is not unusual to introduce new girders between the

old in cases where there is no plated floor to make the work difficult.

By this method there is, of course, an increase of appreciable amount in

the dead load carried by the main girders, which would in many instances

be objectionable. With deep and heavy main girders, having plate webs,

cross-girders may be strengthened by improving the end connections by

suitable gussets, and attachment to good vertical stiffeners, the fixity

of the ends thus aimed at being assured by overhead struts or girders,

from one main girder to its fellow, at intervals apart well considered

with reference to the horizontal strength of the top flanges, the whole

thus making a closed frame, as shown in Fig. 69. The method appears

feasible, but it should be stated that the author has not known it to be

applied in its entirety as a means of strengthening an old floor.

[Illustration: FIG. 69.]

A simple and very common device consists in substituting for the

ordinary cross-sleeper road, where this exists, stout timber

longitudinals under the rails, which have, where the cross-girders do

not exceed 5 feet centres, a marked distributive effect, tending to

reduce the maximum load upon any individual girder. With a similar

object, trough girders containing longitudinal timbers are sometimes

adopted where the depth available is not enough to enable sufficiently

stiff timbers to be used alone. In either case the object sought is the

same--to modify the effect of the heavier wheel loads upon isolated

cross-girders. When the spacing is so close as 4 feet, the beneficial

result of this treatment is considerable, but at 8 feet centres it can

have but a moderate effect where timbers alone are used.

Occasionally, for long cross-girders, a distributing girder is placed,

with the same intent, in the 6 feet way, its function being limited to

this use only if the depth and strength are sufficiently small to serve

this object alone, as distinct from the case in which it becomes a

carrying girder transferring load to the abutments. As a distributor

simply, the girder has to equalise the bending moments amongst the

cross-girders, to effect which it will be evident that these moments

having been ascertained for the several cross-girders previous to

alteration, for a position of the wheel loads such that the heaviest

comes upon a centre cross-girder, the mean of these moments will, when

compared with that for each girder, show the difference to be induced as

a result of introducing the distributor. These differences of moment

render necessary at the centre of the cross-girders reactions upwards or

downwards, as the case may be, of amounts competent to induce moments

below the inner rails equal to these differences.

It is these reactions which must be provided by the distributing girder

at a moderate stress, and without flexure of such an amount as sensibly

to modify the reactions. The greatest section necessary at any one point

may then be adopted for the girder throughout. The result will commonly

work out to a moderate section, but there will be no harm in a little

excess in a case of this kind, the total cost being but little affected

by some small addition to the weight, where labour upon the site is so

considerable an item as in work of this description. The ends of the

distributing girder should be carried on to the abutments or piers to

ensure adequate relief of the end cross-girders. It will be found

desirable in arranging for distributing girders to ascertain at an early

stage, by boning or by levelling, the condition of the cross-girders as

to uniformity of heights, as this may affect the length most suitable

for separate sections. Between the underside of the distributor and the

cross-girder tops there will commonly be spaces of varying amounts,

which should be filled by packings to fit, rather than by pulling the

work together by force, introducing undesirable stresses of uncertain

amount.

In the earlier remarks upon the strengthening of bridgework by the use

of new material, it has been assumed that the modulus of elasticity of

the new metal is similar to that of the old; it may, however, as in

cases where wrought-iron work is reinforced by additions in steel, be

necessary to take the difference of elastic properties into account,

with which object the new section should be multiplied by a quantity

(greater or less than unity) inversely proportional to the higher or

lower modulus of the new material, that is to say, by

E of old material

-----------------

E of new material