CHAPTER IV.

SHIPPING.--IMPLEMENTS.--BUILDING MATERIALS,--AND PROGRESS OF THE BELL

ROCK WORKS IN THE YEAR 1808.

[Sidenote: 1808, January.]

After taking some notice of the preparations made during the

winter months, or early part of the year 1808, it is proposed, in

describing the progress of the works of this season, to adopt the

form of a journal or diary, as in the preceding chapter. The last

year’s operations being more of a preliminary nature, the implements

and apparatus employed were few in number, and simple in their

construction. But the facilities to be afforded by the erection of the

Beacon were such, that not only the site of the building was expected

to be prepared, but it was hoped that some of the courses of masonry

would also be laid during the ensuing summer. It therefore became

necessary to be provided with shipping, and every article, both of

implements and building materials, however small the actual progress of

the work might ultimately be.

_Shipping._

[Sidenote: The New Tender.]

It has already been noticed, in the course of last year’s operations,

that much inconveniency, and no small degree of hazard, were

experienced in making the numerous passages between the Bell Rock

and the Floating-light, especially when the boats were crowded with

artificers. Not having previously been so fully aware of these

circumstances, and with a view to save expence, the Floating-light

was likewise applied to the purpose of a tender. She was consequently

moored at a more considerable distance from the rock, as will be

understood from Plate V.; but as, from the nature of her tackling, she

could not be cast loose upon any emergency, she was found to be but ill

adapted to the uses of a tender.

[Sidenote: Is named The Sir Joseph Banks.]

The writer having represented this to the Light-house Board, was

immediately authorised to provide a vessel, to be exclusively employed

for the service of the rock. He accordingly purchased one upon the

stocks at Arbroath, in such forwardness, that she was launched upon

the 18th of January 1808. This vessel was built by a Mr Thomas Fernie,

and was considered so complete in the mould or figure of her hull,

that some of the best judges of shipping have described her as one

of the handsomest vessels which perhaps had hitherto been built in

Scotland. On account of the exertions of the late Sir Joseph Banks, in

his capacity of one of the Lords of Trade, in procuring the loan from

Government, for the use of the Bell Rock Light-house, already alluded

to in the Introduction to this work, the writer suggested, as a mark of

respect, that the new tender should be named “The Sir Joseph Banks,” to

which the Light-house Board most readily acceded.

[Sidenote: Is rigged as a schooner.]

She was no sooner launched, than her rigging and equipment, in the best

manner, were undertaken by professional people; but the inspection

of the interior fitting and accommodations was kindly undertaken by

the late Provost Balfour of Arbroath, a gentleman who took great

delight in architectural pursuits, and who, upon all occasions, felt

the most lively interest in the operations of the Bell Rock. In

order that this vessel might stow two large boats upon deck, and be

got as quickly as possible under sail, in the event of her breaking

adrift, she was rigged as a schooner; and that, by the application

of a tackle from each mast, the boats might be conveniently managed,

in getting them in and out of the vessel. The Sir Joseph Banks being

only 81 tons register, it was necessary to lay out the births, for the

several departments of the service, with all possible attention to

the economising of room. The forepeak was accordingly fitted up with

a coboose for cooking; immediately aft of this birth, a compartment

was set off for the ship’s company and the landing-master’s crew, with

births for fifteen sailors. But _Jack_ is by no means ill to satisfy

with his sleeping-place, and it was often found necessary to encroach

upon the allotted number for this birth, according to the exigencies

of the service. The waist or middle of the ship was set apart for the

artificers, and was capable of containing forty men. Still proceeding

aft, a small birth was set off for the mate and steward, which

communicated both with the artificers’ birth, and also with the cabin

for the engineer’s assistants, the landing-master, and the captain of

the tender. In the sternmost part of the ship, a cabin was fitted up

for the use of the writer; the whole being found extremely commodious

and suitable. From the great proportion of the ship required for the

birthage of seamen and artificers, the hold of this small vessel was

much curtailed, there being hardly more room left than was sufficient

for containing a stock of provisions, water and fuel, for any length of

time, besides stowing two or three tiers of casks of lime, cement, and

other necessaries for the use of the work.

[Sidenote: Praam-boats, or Stone-lighters.]

Continuing the description of the marine part of the establishment,

we next notice three new praam-boats, or stone-lighters, built for

conveying the building materials to the Bell Rock, from the vessels

employed in bringing them from the work-yard at Arbroath. The term

Praam-boat is applied to a certain description of Norwegian boats,

having their stem and stem rounded after a peculiar fashion. The

introduction of this phrase, in the Bell Rock service, was purely

accidental, having been applied, by Captain Grindlay, Master of the

Trinity-House of Leith, to the first or experimental stone-lighter,

from its resemblance to the praams of Norway. Those now alluded to,

however, were built of a more rounded form, after the Dutch manner.

They measured over all, on deck, about 28 feet by 8 feet 6 inches,

and their depth of hold may be stated at 2 feet, for, being built by

different carpenters, they were not exactly of the same dimensions.

They had a considerable spring or sheer, and were constructed for

carrying their cargoes entirely upon deck, which formed a kind of

_cockpit_ in the waist, having a high gunwale on each side, and a

break, both fore and aft, as will be seen in Plate XI., the first tier

of stones seldom reaching above the level of the gunwale. They had,

consequently, little or no hold, having only what was sufficient for

stowing some pig or cast iron ballast, a few empty casks, with the

necessary warps, kedge-anchors, and grappling-irons.

[Sidenote: Precautions taken for rendering them water-tight and

buoyant.]

These lighters were built of uncommonly strong materials, both in

their timbers, outward planks, and ceiling or lining, which last was

caulked and secured in a manner similar to that described for the

Floating-light, so that although the outward skin were damaged, by

striking or rubbing on the rock, there would still be an additional

defence against sinking. Such, however, was the presentiment of danger

attached to the landing-department, that besides the precaution of a

water-tight lining, each praam was provided with twelve strong empty

casks, which were stowed in the hold, and were sufficient to float and

render her buoyant, in case of accident. The praams, therefore, became

so many life-boats moored in the neighbourhood of the rock.

[Sidenote: Method of mooring the Praam-boats.]

These praams had but one hawse-hole, and that they might ride more

easily at their moorings in the open sea, it was placed amid-ships,

and as low or near the water-line as possible. The chain-hawsers with

which they were connected to their respective floating-buoys and

mushroom-anchors, were made of rod-iron, one-half inch in diameter,

turned into as short links as possible. This piece of chain was about

five fathoms in length, and was attached to the praam by a strong hook,

connected with her _bits_, the farther end being made permanently fast

to the mooring-chain of the mushroom-anchor. From the lowness of the

hawse-hole, and its central position in the praam, and from having

only a short piece of chain to carry, which connected the boat to the

mooring-buoy, may be attributed the astonishing ease and safety with

which these boats rode at anchor. So remarkable was this, that while

the tender, and the other vessels in the service, were tossed about,

and shipping a great deal of sea, and even at times obliged to slip

their moorings, the praams floated with an easy undulating motion, and

were generally as dry upon deck during a gale, though loaded with ten

tons of stone, as if, to use a sailor’s phrase, they had been riding in

a mill-pond. The facility, also, with which the praams were attached

and disengaged from their moorings, was another very great conveniency

to the work. In unmooring them, all that became necessary was to

unhook the hawser-chain from the bits, and throw it overboard, with a

small floating-buoy attached to it, for the purpose of suspending the

hawser-chain for the time. In the same manner, in making the praams

fast to their moorings, this chain was simply to be laid hold of, by

taking the small floating-buoy on board. The chain was then slipped

into the hawse-hole, by a corresponding slit in the stem of the

praam, and then attached to the bits, when the process was complete.

By inspecting the diagrams in Plate XI., this process will be better

understood.

[Sidenote: Attending Boats.]

The two cutters or boats employed last year for transporting the

artificers from the Floating-light to the Bell Rock, were found to be

rather too small in rough weather. They measured 16 feet in length of

keel, 5 feet 3 inches in breadth, on the mid-ship thwart or seat, and

2 feet 6 inches in depth. These boats were of as large dimensions as

the floating-light could stow, after making the necessary allowance

for _ranging_ her cables on deck. They had square sterns, were rowed

with four oars, and accommodated twelve sitters, including sailors.

But the Sir Joseph Banks being entirely fitted as a tender for the

works, the stowing of large landing-boats became a principal object.

Her boats were therefore made as large as possible, due regard being

had to their convenient management and fitness for the small creeks

or landing-places at the rock. After a careful consideration of these

circumstances, it was resolved that the two new attending-boats should

measure 20 feet in length of keel, 5 feet 8 inches in breadth, and

2 feet 10 inches in depth. They were rowed with eight oars, double

banked, or two upon each thwart, and could accommodate eighteen sitters

each. They were round in the stern, fitted with a backboard and a

convenient seat for the cockswain, who steered with a _yoke_ and lines,

instead of a _tiller_.

[Sidenote: Life-Boat.]

One of these boats was called The Mason, the other The Seaman. The

latter was fitted up as a Life-boat, somewhat after Greathead’s method,

being lined and girded with cork, to the depth of three streaks below

the gunwale. In case of accident, therefore, by the bilging of either

boat upon the rock, she was rendered more buoyant by the cork lining

and sheathing. They were built in Leith, and before being sent to the

rock, the buoyancy of the Life-boat was tried, when it was found that

she would float with thirty people on board.

_Implements._

[Sidenote: Railways.]

From the wasting effects of the sea, the Bell Rock is formed into

numerous benches and gullies, and its surface is consequently extremely

rough and irregular. The site of the Light-house being in a central

position on the rock, it became necessary to make some provision for

conveying the large blocks of stone speedily from the respective

landing-places to the site of the building; or at least within the

range of the cranes or machinery to be employed in laying them. In

ordinary situations, the most obvious method would have been to clear

away the inequalities of the rock; but here, from the lowness of its

position in the water, such an operation would have been extremely

tedious and difficult. Besides, every portion of the Bell Rock was held

sacred, excepting in so far as it was absolutely necessary to excavate

or remove part of it, in fixing the Beacon-house, and in preparing the

foundation of the Light-house. Instead, therefore, of quarrying the

rock, the writer found that the most advisable process would be, to lay

cast-iron railways round the site of the Light-house, projecting to the

several landing-places, on which waggons could easily be wheeled in all

directions, as will be seen by tracing the dotted lines on Plate VI.

For this purpose, patterns were prepared in the course of the winter,

from which castings of the several compartments of the railways were

made by Mr John Baird, of the Shotts Iron Works. These rails were

cast in lengths of four feet, and supported upon props and frames of

cast-iron, varying in height from six inches to five feet, according

to the inequalities of the rock, that the whole might be laid upon

one level. Besides the tracks for the wheels of the waggons, it was

necessary also to provide a tracking-path of the same metal, which was

formed of ribbed work, rested upon the supports of the rails, as will

be understood from the diagrams in Plate X. The waggon-tracks were of

the form technically termed Plate-rails, which were found convenient

for making the necessary fixtures. The edge-rail is less liable to

friction, and is certainly greatly preferable to the plate-rail, where

the track is liable to be impeded with dust, and other adventitious

matters; objections which do not apply at the Bell Rock, where the

rails were every tide considerably under water.

[Sidenote: Waggons.]

It was necessary that every thing intended to be left on the Bell Rock

during the working season, should have as little buoyancy as possible,

and as it would have been extremely inconvenient to have removed the

waggons from the rock, which were to be employed in conveying the

blocks of stone from the landing-places to the Light-house, they were

constructed entirely of iron, excepting two pieces of oak timber, which

were bolted upon the top, to form a seat for the stones. These waggons,

represented in Plate X., moved upon four trucks or wheels of cast-iron,

measuring one foot two inches in diameter, placed two feet six inches

asunder, being the length of the axle, and breadth of the railway. Each

waggon was provided with a handle, which shifted at pleasure to either

end, for the conveniency of reversing the motion, without the necessity

of turning the vehicle. But what was more peculiar to these waggons,

was a joint in the middle of the perch or double frame, connecting the

wheels, by means of which they were made applicable to the circular

tracks of the railway round the site of the building.

[Sidenote: Triangular Crane.]

Connected with the cast-iron railways, preparations were also made at

the eastern landing place, for lifting the stones by means of cranes or

other machinery from the Praam-boats, and laying them upon the waggons

to be conveyed to the building. After a good deal of consideration,

patterns were prepared for an apparatus consisting chiefly of six

pieces of cast-iron, four of which measured 12 feet in length, and of a

corresponding strength. As will be seen in Plate XI., these bars met

at the top in the form of two sets of sheers, but their lower ends were

placed about 9 feet asunder. Connected with these, a pair of sheers

were set up, which were moveable upon a bolt, and worked with a crab

or winch machine, the whole being strongly batted to the rock. When

the moveable pair of sheers, with their attached chain and hook, were

suspended outwards over the stone to be lifted from the praam, the

chain was hooked to the Lewis-bat, previously inserted into the block.

The sheers were then raised till they were brought to a perpendicular

position, when the motion of the winch was reversed, and the sheers

were lowered inwards upon the wharf, and the stone thus laid upon the

waggon. The chain was then unhooked, and the sheers were ready for

lifting another stone, as will be better understood by referring to

Plate XI., with its letter-press description.

[Sidenote: Crane with moveable Beam.]

Having, in the foregoing article, described the implement employed in

landing the stones on the Bell Rock during the year 1808, we are now

to notice the crane employed in laying or building them. It appears

from Mr Smeaton’s Narrative, that the implements chiefly used for

building at the Edystone, were a pair of moveable sheer-poles and a set

of triangles, most ingeniously applied to their respective purposes.

But such implements must have come far short of the expedition which

the writer had conceived to be necessary at the Bell Rock, both on

account of the much greater extent of the building, and also from its

foundation being so much lower in the water. After considering the

subject, and making minute inquiries into the practice at various

public works, he found no implement of the description, which he

considered applicable to his purpose. The common sheer-poles, still

chiefly in use, were recommended as having upon the whole been

successfully employed at the Edystone. In some instances, the common

crane, with the beam fixed at the top, at right angles to the shaft,

was applied for laying heavy materials. The writer, however, laid

it down as a proposition to himself, That a more effective mode of

building must be adopted at the Bell Rock than had hitherto been in

use, by which all the stones at any time likely to be landed in the

course of a tide, might be built and secured before the artificers left

the rock.

The chief difficulties attending the application of the common crane in

such a situation, consisted in the laying the stones perpendicularly

into their respective places, as they were all of a dove-tail or

angular form, as will be seen from Plate XIII. The fixed beam of the

common crane was further objectionable, from its being more liable to

interfere with the guy ropes. It would also have been difficult to have

lifted it either laterally or perpendicularly upon the building, from

one course to another. To these may also be added the great obstruction

which the beam would have presented to the waves of the sea at high

water. All these objections, however, were in a great measure got over,

by substituting a moveable beam to work upon a bolt at the foot or

lower end of the upright shaft, instead of a fixed beam at the top in

the usual manner. But as we shall have occasion again to notice this

machine in the operation of building, we shall here refer to Plate XIV.

with its letter-press description. Three of these cranes, with moveable

beams, were prepared for the work, in the course of the winter, one

with an upright shaft of 28 feet in length, for laying the prepared

stones upon the platform in the work-yard at Arbroath, and other two,

with shafts of 21 feet, for building at the rock.

[Sidenote: Sling Cart.]

Though none of the stones of the Bell Rock Light-house were likely

to exceed two tons in weight, in their finished state; yet, in their

undressed state, they were much more ponderous. From the waste

attending their dove-tailed form, and the working them square on all

their sides, the blocks from the quarry were greatly reduced; in

many instances, to one-half of the cubical contents of their quarry

dimensions, before they were brought to the size of the moulds. The

stones had not only to be conveyed from the harbour of Arbroath to the

work-yard, a distance of from two to three hundred yards, but also

required to be frequently lifted from place to place; as, for example,

when in a hewn or dressed state, they were removed to the circular

platform, in the middle of the work-yard, to be tried and marked;--they

were again shifted from this position, and ultimately carried to the

harbour to be shipped for the rock. From the various movements which

each stone had thus to undergo, it became an object of importance to

the facility and economy of the work, to consider how this could be

most conveniently accomplished. Had a cart or carriage, with four

wheels of the ordinary construction for great loads, been employed,

it would have been extremely troublesome, in all the operations of

loading, turning and moving from place to place. To have attempted to

avoid this by the use of waggons with low wheels, and the introduction

of railways along the quays and public streets of Arbroath, would

also have been objectionable, especially as the object could be much

more conveniently obtained by the use of what is called the Woolwich

Sling-cart, represented in Plate X. By this machine, the weight is

simply raised off the ground with a wheel and pinion apparatus fixed

upon the frame of the cart, and in this manner, the stone, instead of

being lifted upon the body of the carriage, had only to be suspended at

the necessary height for overcoming the inequalities of the road. This

vehicle had long been used with great advantage by military engineers,

in moving ordnance; but was probably first employed at Mylnefield

Quarry, and the Bell Rock works, in transporting blocks of stone.

[Sidenote: Carpenter’s Jack.]

Another implement prepared, in the course of the winter, for the Bell

Rock work-yard, was the Carpenter’s jack, used for raising ships upon

the blocks or props for the purposes of repair. This machine, which is

simple in its construction, and direct in its application, consists

of a rack and pinion, enclosed in a frame of oak timber, strongly

bound with iron, as represented in Plate X. By working the handle of

the jack, the stone-cutter is enabled, without the assistance of his

fellow workmen, to turn and lay the heaviest stone to his hand. This

apparatus the writer first saw used to much advantage, by the quarriers

at Portland Island, in the year 1801; and though it had not perhaps at

that time been put into the hands of the stone-cutter, it was obvious

that it might also be applied to his purpose with equal effect.

It may further be noticed, regarding this useful implement, as strongly

marking the prejudices of habit, that Mr Mylne, the proprietor of

Mylnefield Quarry, who, with enlightened views, furnished his works

with machinery of the very best description, among other articles,

provided a number of these jack-machines for his quarriers, but, for

a long time, they could not be induced to make use of them. One of

the men, however, happening, of his own accord, to apply the jack in

turning a heavy block, its utility soon became apparent; and Mr Allan

the manager, who had previously taken considerable pains to get the

jack introduced, was at length not a little pleased to find it, after

having been laid up in store as useless, in much request throughout

that extensive quarry.

[Sidenote: Lewis Bat.]

A Lewis Bat, of some form, for lifting large stones, is believed

to have been known to the ancients. But that now in common use is

generally understood to have been at least improved by the French

engineers, who, in honour of their Sovereign, gave it the name of

Lewis. This useful implement is so universally known in practice,

for its great utility in building with heavy materials, that it is

hardly necessary to do more than simply allude to it. It consists

of five pieces of iron, three of which, forming a dovetail, like

an inverted wedge or the keystone of an arch, are inserted into a

corresponding hole cut in the stone. The fourth is the bolt connecting

the shackle-piece, by which the weight is suspended, as will be better

understood by referring to the sketch or diagram illustrative of it in

Plate XI. Of this implement, it became necessary to furnish several

dozens, as well from the variety in the weight, as from the figure of

the stones, many of them requiring two Lewises to produce a proper

balance. But the number was more particularly encreased, from the

different sets required for the workyard, the stone-lighters, and for

the Bell Rock, where it was necessary to provide against loss, to which

this service was so peculiarly liable.

[Sidenote: Moulds.]

As the whole of the stones of each course or tier of this building were

connected or let into one another, by a system of dovetails, diverging

from the centre to the circumference, after the manner of the Edystone

Light-house, as will be seen from Plate XIII., each particular stone

required to be cut with accuracy, to fit its precise place in the

building; and as even the form into which the blocks of granite were

made, often depended upon the adventitious produce of the quarries, it

became a very considerable operation to prepare the necessary moulds

or patterns for the respective courses. When, therefore, the thickness

was ascertained that a lot of these stones would admit being dressed, a

plan of the particular course was first drawn upon paper by the Clerk

of Works; a certain compartment of the course was then protracted of

the full size, upon a platform of polished pavement, measuring 70 feet

in length, and 25 feet in breadth, and occupying part of the ground

floor of the workmen’s barrack. From this enlarged draught, Mr James

Slight, the principal mould-maker, took his dimensions in making the

moulds of the full size of the ground-plan of each stone, on which

were marked the necessary directions for the stone-cutter, both as

to the thickness of the course, and the position of the connecting

joggle-holes, trenails and wedges.

These moulds being made with great precision, were carefully marked

and numbered with oil paint, according to the positions which the

respective stones were to occupy. They were made of well seasoned

fir timber, and dressed clean in the form of open frame-work,

measuring from three to four inches in breadth, and from one-half to

three-fourths of an inch in thickness. At the angles and joints, thin

plates of iron were screwed upon these frames, to strengthen and

preserve them, while the workmen were making their draught-lines, and

in their numerous applications of them in the process of hewing the

stones. Each course of the solid part of the building required from

three to five moulds, of the form delineated in Plate X., which were

carefully laid aside in sets, till the particular course to which they

belonged should be landed upon the rock, and secured in the building.

In a work of this kind, such a precaution was indispensably necessary;

for, in case of loss or accident to any of the stones, in landing them

at the Rock, it would then only have been necessary to send to the

work-yard, referring to the particular number of the mould, from which

another stone could speedily have been prepared.

[Sidenote: Cofferdam.]

In the first designs for the Bell Rock Light-house, the writer had

modelled a cofferdam, five feet in height, intended to have been

erected of cast-iron, round the site of the building, that the work

in its early stages might be continued for a longer period, both

during the ebb and flood tides. The experience of last season’s work,

however, shewed that the erection of the proposed cofferdam would have

been attended with considerable difficulty; and, to have rendered

such an apparatus equally useful during ebb-tide as flood-tide, would

have required the pumping of water by machinery more complicated and

powerful than the situation of the Bell Rock would have admitted.

[Sidenote: Pumps.]

This idea was therefore laid aside, and two Pumps, of a simple

construction, were prepared, for clearing the foundation-pit of water.

They measured about twelve feet in length, and were of a square form,

both externally and internally, having each a void of ten inches. They

were made of fir timber, three inches in thickness, strongly jointed,

and put together with white-lead paint, having also a number of cross

bars and bolts of iron, to strengthen them for withstanding the

atmospheric pressure upon so considerable a surface. These pumps were

furnished with a wooden spear or rod, having a cross head or handle at

one end, and a leathern valve attached to the other. This valve was of

a very simple construction; it collapsed when plunged into the water,

and was inflated by the return draught delivering a quantity of water

equal to the cubical contents of the void or chamber of the pump.

[Sidenote: Winch-machines.]

There were four Crabs or Winch-machines prepared for working the

different purchases required in the various departments of the work,

as, for example, in lifting the stones from the praam-boats, as

represented in Plate XI. Another of these machines was fixed on

the temporary wooden bridge of communication, erected between the

Beacon-house and Light-house, as will be seen in Plate IX. Other two

of these machines are likewise represented for raising the stones

from stage to stage upon the building, as will be more particularly

described in the letter-press description of this Plate. These machines

were made wholly of iron, excepting the bushes for the gudgeons working

in, which were of bell-metal. They were calculated to work with what

is called _double and single purchases_, according to the weight of

the stones to be lifted. They were very powerful in their operation:

the winch or barrel being twelve inches in diameter, gave the single

purchase a power of about fifteen to one, and the double purchase about

sixty to one. These machines were calculated to work with five tons.

The weight of the largest size was altogether about 10 cwt., so that

they were not easily shifted by the impulse of the sea, when batted to

the rock, as represented in Plate XI.

_Building Materials._

[Sidenote: Stone.]

The Commissioners of the Northern Light-houses, as before noticed,

having finally resolved that the erection upon the Bell Rock should

be of stone, constructed upon principles similar to the Edystone

Light-house, it became a question of importance in the economy of

the work, to fix the quality and description of stone to be used.

Considering this subject in reference to the Edystone Light-house,

it appears that the hearting or interior of the solid part is of

sandstone from Portland Island, and that the exterior of that building

is of Cornish granite, both of which were highly suitable in quality,

and were fortunately procurable from quarries the most contiguous to

Plymouth, where these works were situate.

[Sidenote: Mineralogy of the southern and eastern shores of Britain.]

It may farther be noticed, that granite is perhaps the only stone upon

the coast of England, which possesses durability for withstanding

the effects of the weather in a situation so exposed, or strength

sufficient for undergoing the process of landing the stones when

in their prepared state. In Scotland, however, the case is widely

different, for here, the country abounds with excellent building

materials of almost every description; and excepting in those districts

which produce granite, that stone is rarely had recourse to for

buildings of any description. It is curious to observe, and it may here

not be out of place to remark, in looking into the mineralogy of the

British coast, on the great scale, that we find the shores of the whole

southern parts of the kingdom, or from Portland Island in Dorsetshire,

to Flamborough Head in Yorkshire, consist chiefly of chalk, limestone,

clay, and beds of gravel. But if we continue our course from thence

northward, to Stonehaven in Kincardineshire, including the Firth of

Forth, the strata, with little exception, are sandstone, greenstone,

limestone and coal. The Aberdeenshire coast is chiefly of granite,

syenite, and gneiss, while a part of Banffshire consists of serpentine

and porphyry: but here the sandstone again makes its appearance, and

stretches along the northern shores of the Moray Firth , Caithness and

Sutherland, nearly as far to the westward as Cape Wrath. To this great

extent of sandstone country, may also be added the islands of Orkney

and Shetland, with some considerable exceptions, however, in so far as

regards Shetland; but, in Orkney, these are confined to comparatively

small portions of gneiss with granite veins, which occur in Pomona or

the Mainland, and in the Island of Græmsay.

From this state of the mineral strata, it naturally follows, that those

who inhabit the sandstone districts employ that beautiful, easily

worked, and, in many instances, highly durable stone, in architecture;

and so of the other districts, according to the predominating species

of their stone. For a building, therefore, in a country situate like

that of the Bell Rock, abounding with sandstone of the first quality,

this description of stone obviously presented itself, both as the most

accessible and economical. But when the importance of this work came to

be fully considered in all its relations, a little additional expence

was not to be allowed to regulate a point so essential, without a due

regard to what might ultimately prove the most durable and permanent

fabric.

[Sidenote: The use of granite and sandstone is resolved upon.]

The attention of the Commissioners was consequently directed to the use

of granite, as combining the greatest number of properties for such a

building. Some doubts, however, having existed, as to the certainty

of procuring blocks of that stone of sufficient dimensions, it became

a matter of importance to determine this point, and also to ascertain

the quality of the sandstone, of which it had been proposed to form at

least the hearting of the solid part. The Commissioners, therefore, in

the month of November 1806, required a special opinion from Mr Rennie

and the writer upon this subject; who accordingly visited the sandstone

quarry of Mylnefield near Dundee, and the granite quarries in the

neighbourhood of Aberdeen, and made a report to the Board, which is

given in the Appendix, No. IV.

[Sidenote: Report of Mr Rennie and Mr Stevenson.]

This report sets forth, that many granite quarries were found in

activity at Aberdeen, some of which were capable of producing larger

blocks of stone than are usually met with, but that still it was

doubtful, whether any single quarry would be found to produce a

sufficient number of large blocks for this work in any reasonable time.

Upon the quality of the stones respectively; the report states, that

“the granite of Aberdeen is very strong and durable in its nature, and

having been used in works where the sea has acted upon it for time

immemorial, no doubt can possibly be entertained as to its adaptation

to a work of this kind. There is also every reason to believe that the

Mylnefield stone resists the sea and weather equally well, but we have

not been able to collect such positive proof of this as of the other;

for, although a great number of Mylnefield stones have been used in

the piers of the harbour of Dundee, yet, as these works consist of

stones from other quarries, having the same appearance, and nearly the

same composition, there is no possibility of our saying whether some

of the stones that appear in a wasting state, may not have been from

that quarry, although we have great reason to believe they have not.

However, where facts cannot be positively ascertained doubts exist,

and we think that a Light-house upon the Bell Rock is too important a

work to permit the leaving of the slightest doubt about the durability

of the materials. We have, therefore, no hesitation in recommending

that the outer part of the building, at least as high as the first

apartment, should be of granite; and as this is the great bulk of the

work, it may be as well to complete the outer course of granite.”

The Reporters then go on to state, from a review of the several quarry

prices, that, for the outer casing, the sum of about L. 2,500 would be

saved by the use of sandstone from Mylnefield, instead of granite from

Aberdeen; and that, for the hearting of the solid part, an additional

saving of about L. 1000 would further be made, if the sandstone of

the Redhead quarries, in the immediate neighbourhood of Arbroath,

instead of the Mylnefield stone, was used. On considering this subject,

however, in all its bearings, the Commissioners resolved that measures

should be taken for procuring granite for the whole outward casing of

the Light-house, and that the Mylnefield sandstone should be used for

the interior work. To the other properties of these stones, one of some

consideration for a work of this description was their ponderosity,

there being only about 13½ cubic feet of Rubislaw granite to the

ton, and 15 feet of Mylnefield stone, while the more common kinds of

sandstone contain about 15½ feet to the ton.

These, and other matters of minor importance alluded to in this report,

having been adjusted by the Light-house Board, the writer took the

necessary measures for entering into contracts and agreements for

the supply of stones from these quarries. The difficulties which

subsequently attended the procuring of a regular supply of stones for

the work have already been alluded to; and to this subject we shall

again have occasion to recur, as it was ultimately found necessary to

restrict the use of granite to the outward casing of the first thirty

feet or solid part of the building.

[Sidenote: Mortar of the ancients.]

The best composition for building-mortar appears to have been a problem

from the earliest history of the arts. Vitruvius, who lived about 130

years before the Christian æra, seems to have been practically, as well

as scientifically, acquainted with the whole subject of architecture.

But, although he, and other eminent authors who followed him, have

minutely treated of the composition of mortar, stating, no doubt, all

that was known of the practice of the ancients; yet, it has always

been a favourite maxim to maintain, that the secret of compounding

mortar has at some period of its history been irrecoverably lost. It

is certainly true, that many of the works of ancient times exhibit

wonderful specimens of the excellency of their building materials.

It may, however, be drawn no less conclusively from the writings of

intelligent travellers, that many of their finest edifices have been

subject to premature decay, which affords a proof that at least no

systematic rule was universally observed in the preparation of their

calcareous cements; but that, like the artists of the present day,

the quality of their materials depended much upon those adventitious

circumstances which too often regulate the views of their successors,

by an over-anxious desire for economy, without keeping duly in view the

permanency of their works.

[Sidenote: Attention of the moderns to this subject.]

In Great Britain, the composition of mortar does not seem to have

occupied much of the attention of the learned, prior to the beginning

of the 18th century, or the time of Sir Christopher Wren. And, indeed,

the subject was not pursued with much intelligence and effect, till

after the great discoveries of Dr Black, about the year 1754, which

unfolded the principles of latent caloric, and the expulsion of

fixed air, by which limestone loses about one-half of its weight

in the process of calcination. These discoveries were succeeded by

the excellent treatise of Dr Higgins on Water Cements, published in

1780; and in 1793, Mr Smeaton’s Narrative of the Edystone Light-house

appeared, containing, not only an account of the preparation of the

mortar for that celebrated building, but also of his experience for

thirty-six years, as an engineer of the most extensive practice of

his day. The composition of mortar has also occupied the attention of

several French authors, as Belidor, Loriot, Viccat and others, but

without perhaps adding much to our stock of practical knowledge.

[Sidenote: Experience of the writer.]

Were the writer permitted to state the result of his professional

observations for the last twenty years, he might notice, that no

error is more commonly met with in water buildings, than that of

employing house or common mortar in the erection of sea-walls. It may

also be stated, generally, in compounding mortar, that the cheapest

article is too apt to be made use of in the greatest proportion. We

accordingly find, that lime is not unfrequently made too _rich_, as it

is technically termed when a small proportion of sand is applied to the

mixture; an error, which is attended even with worse consequences than

when the lime is made _poor_, or when too great a proportion of sand is

used. But, perhaps, the worst of all mortar is that wherein very fine

_pit-sand_, containing a portion of earthy matters, is used, and when

the whole is mixed up with impure water. So little attention is often

paid to the quality of mortar, in common buildings, that one would

imagine it were applied, as if intended more to prevent the sifting

winds from penetrating the walls, than as the medium by which they were

ultimately to be bound or formed into a compact fabric.

It is not possible to give any formula for the composition of mortar

which will apply generally; so much depends upon the quality of the

limestone, the mode of its treatment in burning, the use of clean sharp

sand and pure water. When these ingredients are judiciously selected,

duly apportioned, and well beaten together, they will immediately form

a paste of some tenacity, which will ultimately take bond and give a

consistency to the work. From all the experiments that have been made,

it seems to be essential to the composition of the best water-cements,

that the limestone should contain about one-seventh of alumine or

clayey matter. But as this description of limestone admits of a less

proportion of sand in the mortar compounded of it, than that which is

more purely calcareous, it is not so much in request for the common

operations of building, as being less economical. It may, however,

be stated, as a pretty general maxim, that where comparatively pure

calcareous matter is met with, at least three measures of clean sharp

sand, free of earthy particles, mixed with one of burned lime, in the

state of powder, and a due portion of pure water, well beaten together,

will form good mortar for common use.

[Sidenote: Mortar of the Edystone.]

From the similarity of the situations and the buildings upon the

Edystone and Bell Rocks, and from Mr Smeaton’s celebrity as an

engineer, his Narrative of the former work became a text-book to the

writer in the erection of the latter. In considering the importance of

this subject, with a view to the erection of the Bell Rock Light-house,

the judicious remarks, and numerous experiments, of Dr Higgins on water

cement, were carefully examined, and they will always be consulted with

interest by the professional reader. The composition of the Edystone

mortar consisted of equal portions, by measure, of Aberthaw lime and

Pozzolano earth, both in the state of powder, mixed up with sea-water.

When the writer first visited Plymouth in the year 1801, the Edystone

Light-house had been erected about 42 years; and he was informed by Mr

Tolsher, agent for the establishment, that the original pointing of the

joints of that building had never required repair.

[Sidenote: Bell Rock Mortar.]

Of the ingredients of the Bell Rock mortar, as the pozzolano was not

only the most expensive, but, from the distracted state of Europe,

during the progress of the works, could hardly be procured at any

price, it became an object to be as independent of that article as

possible. A train of experiments was therefore undertaken by the

writer, when it was ultimately found, that pozzolano and lime, in

the state of a dry impalpable powder, and clean sharp sand, in equal

proportions by measure, mixed with sea-water, formed a mortar equally

good in all respects as when no sand was added. Under favourable

circumstances, this mixture did not seem to be more tardy in fixing,

than when the sand was excluded, while nothing could exceed the compact

and indurated state of the composition. The writer accordingly built

some small rubble-walls with it within sea-mark, which were allowed

to stand for a few months, and when pulled down, they appeared like

so many pieces of conglomerated rock, the mortar being as hard and

compact as the sandstone of good quality with which these little walls

were built. From the excellency of the Bell Rock mortar, it may not

be amiss to go a little farther into detail, by noticing each of the

ingredients of which it was composed.

[Sidenote: Lime.]

In the course of investigating this subject, specimens of lime,

from the counties of Edinburgh, Haddington, Fife and Forfar, were

subjected to various trials with mixtures of pozzolano and sand. The

results were not a little curious, as the experimental balls, made

with different proportions of these limes, did not set or harden;

but, on the contrary, the particles seemed to repel each other as the

mixture became heated, and ultimately crumbled into its constituent

ingredients. From these experiments, it was found advisable to bring

a cargo of limestone from Aberthaw in Wales, being the same as that

used for the Edystone Light-house. This lime is found imbedded in a

clayey matrix, in the state of water-worn nodules, varying in size from

a cubic inch to that of a cubic foot. This limestone is of a bluish

or beautiful French grey colour, of the specific gravity of 2.70.

It is easily calcined, and in that state is reducible to the finest

powder. It is the mountain or first flœtz limestone of geologists; and,

when broken, it pretty generally displays the _Cornua ammonis_, and

many other curious animal remains. This limestone is found in great

abundance on the sea-shore at Aberthaw, where the softer matters being

washed away from the lower stratum of certain high cliffs, containing

these rounded masses, the upper parts fall in great quantities, from

which the succeeding tides wash away the earthy matters, leaving the

limestone upon the beach in the state of debris. When a vessel is to

load limestone here, she is grounded on the shore at about half-tide,

and loaded when the water recedes. The price paid to the proprietor for

a cargo is at the rate of one shilling _per_ ton, as a lordship.

[Sidenote: Pozzolano.]

Pozzolano, the second mentioned ingredient of the Bell Rock mortar, is

a kind of earthy lava, of a brownish red or greyish colour. It contains

in the hundred parts, silica 55, alumina 20, lime 5, and oxide of iron

20. It was not so easily procured as the limestone from Aberthaw. It

is very abundant on the coast of Italy and shores of Sicily, where it

is found in considerable masses, and is usually imported in a crude

earthy state, requiring to be pounded, or beat in a mill, to fit it for

the finer purposes of mortar. It is generally brought to this country

as ballast; and, in time of peace, when the ports are open, is sold

for about L. 5 _per_ ton. During the progress of the Bell Rock works,

however, from the long continued and almost universal restrictions upon

British trade with foreign ports, as much as L. 15 _per_ ton has been

paid for pozzolano for the use of these works. The writer having had

great difficulty in procuring a supply of it for commencing the works,

got a quantity of Tarras from Holland, the Dutch ports being, at this

time, open to British vessels. Tarras or Trass is found near Andernach,

and is brought down the Rhine to Holland. It is very similar in its

nature and properties to pozzolano, and, like it, is of a reddish or

greyish colour. It contains 37 parts silica, 28 alumina, 6.5 lime

and 8.5 iron. Its property of setting in water is very remarkable,

and, when good, it admits even a greater proportion of lime in the

composition of mortar than pozzolano. The Dutch are very attentive in

ascertaining the quality of the trass before using it in building their

dikes. The following simple experiment is always employed. A small

vessel, made of a mixture of lime and trass, is filled with water,

and if at the end of three days the water does not filter through the

vessel, the trass is considered good; if, on the contrary, water passes

through, the trass is rejected as bad.

[Sidenote: Sand.]

According to Dr Higgins, the sand used for mortar should be free of

earthy particles, and have as many sharp angular points as possible.

The writer having accordingly examined the shores in the neighbourhood

of Arbroath, for sand answerable to this description, he found it of

excellent quality about a mile and a half westward from that place.

Upon examining this sand with a magnifying-glass, its appearance was

like so many small shining crystals shooting into numerous points.--It

is often a difficult question with mineralogists, to account for the

production of sand in many situations upon the coast; but here the

question involves no perplexity, as St Andrew’s Bay, which is generally

understood to extend from Fifeness to the Redhead, a distance of about

25 miles, is not only bounded by sandstone, but forms the embouchure of

the river Tay, and of several other considerable streams, which fall

into the sea upon its shores.

[Sidenote: Water.]

It usually forms a condition in the Specification of mortar for

house-building, that it shall be mixed with pure water, free of

earthy or saline particles. In situations where water is scarce, many

impurities are apt to be mixed with it, which injure and even destroy

the adhesive quality of the mortar. The use of sea or salt water is

guarded against in these cases, from its liability to produce an

efflorescence on the walls; when the saline particles deliquesce with

the changes of the weather, and produce the appearance of dampness.

To have attempted to avoid the use of salt-water in the preparation of

the mortar for the Bell Rock Light-house,--which was all prepared on

the spot,--independently of the risk of deteriorating the mortar, would

have been attended with much additional trouble and expence. Besides

the practice at the Edystone, the writer had previously ascertained,

that the use of sea-water produced no bad effect upon the tenacity or

adhesive quality of the mortar into which it was introduced, and the

object of avoiding the appearance of dampness in this building was

extremely trifling. The stones were to be very correctly jointed, and

the whole of the interior walls to consist of polished masonry, so that

the fine lines of the joints exposed to the action of the air were so

inconsiderable, as hardly to be taken into account. Salt-water was,

therefore, uniformly used in the preparation of the Bell Rock mortar.

[Sidenote: Cement.]

The recent discovery of a very excellent water-cement, for which Mr

Parker of London obtained a patent, under the title of “Roman Cement,”

became another matter of importance to the Bell Rock works. This

substance is produced from calcined nodules of argillaceous limestone,

found upon the southern shores of England. It is of a brownish colour,

and from its excellent property of setting in water, when good and

fresh, its application as a mortar, for the lower courses of the

Light-house, demanded attention. But, for general use as a mortar,

it would not only have been expensive, but often highly inconvenient

in building, from the speedy manner in which it hardens. It is also

of too brittle a nature to be suitable for the general purposes of

common mortar; though it forms a paste of great value for _lipping_ or

pointing the outward joints of water buildings, not only by preserving

the mortar till it gets into a fixed state, but also as forming a

durable joint. A considerable supply of this cement was accordingly

used throughout the building, for pointing the exterior joints. This

cement is sold at the rate of five shillings per Winchester bushel, in

the state of powder, packed into casks, lined with paper, to prevent

it, in some measure, from imbibing humidity from the atmosphere, by

which its adhesive properties are destroyed.

[Sidenote: Oaken Trenails and Wedges.]

Following out the principle of the Edystone Light-house in most of its

details, the oaken trenail and wedge were used for fixing the stones,

till the mortar took band, and a superincumbent weight was got upon

them to prevent the sea from sweeping them away. These being also

introduced into all the lower courses of the Bell Rock Light-house, a

sufficient quantity was procured for the probable number of courses

that might be built during the ensuing season. The precise lengths of

the trenails and wedges could not be fixed, from the uncertainty of

the granite quarries, which regulated the thickness of the courses of

the building; but, for the present, the trenails were provided of the

length of 2 feet, and 1¼th inch in diameter. The wedges were of the

length of 18 inches, measuring 3 inches in breadth, 1 inch in thickness

at the top, and tapering to ¼th of an inch in thickness at the point,

as will be seen in Plate X. Figs. 10. and 11. But when we come to speak

of the process of building, their respective uses will be described.

[Sidenote: 1808, March.]

[Sidenote: The writer visits the Bell Rock.]

On the writer’s visit to Arbroath, in the end of March, he was anxious

to land upon the Bell Rock, to ascertain the precise state of the

Beacon, after the storms of the winter, that he might be enabled to

judge of the propriety of converting it into a habitable place for

the artificers during the working season. He accordingly sailed from

Arbroath on the 30th current, at 1 A. M. in the Light-house Yacht. The

wind was from E.NE., but the weather, though cold, was upon the whole

favourable for the trip. At 7 the Floating-light was hailed, and all

on board found to be well. It was now unfortunately too late in the

tide for landing upon the rock this morning; and it became necessary to

cruise about till the following day, there being at this season only

one tide with daylight. In the mean time, in sailing round the rock,

just as it was beginning to be covered with the tide, the base of the

Beacon was distinctly seen between the rolling seas, which broke upon

it; while at the top, the flag-staff proudly continued to surmount the

whole.

[Sidenote: Floating-Light.]

In the course of the day the writer examined the Floating-light,

where every thing connected with the security of the vessel, and her

moorings, was in good order. What seemed chiefly to please Mr Wilson

the commander, was a late improvement in the application of a winch,

with wheel and pinion fixed at the break of the quarter-deck, which was

now employed to great advantage in working the cable with stoppers as

on board of war-ships, the hempen cable, forming part of her moorings,

being too thick and unwieldy for _holding-on_ by hand. The vessel’s

manner of riding during some late gales was described as having been

very difficult, and even alarming at times; but it was nevertheless,

added, that nothing had been felt so severely as the gale of the 6th

and 7th of September last, when the writer was on board.

[Sidenote: The crew spend their time happily.]

The crew were observed to have a very healthy-like appearance, and

looked better than at the close of the works upon the rock. They

seemed only to regret one thing, which was the secession of their

cook, Thomas Elliot,--not on account of his professional skill, but

for his facetious and curious manner. Elliot had something peculiar

in his history, and was reported by his comrades to have seen better

days. He was, however, happy with his situation on board of the

Floating-light, and, having a taste for music, dancing, and acting

plays, he contributed much to the amusement of the ship’s company, in

their dreary abode during the winter months. He had also recommended

himself to their notice as a good shipkeeper, for as it did not answer

Elliot to go often ashore, he had always given up his turn of leave to

his neighbours. At his own desire, he was at length paid off, when he

had a considerable balance of wages to receive, which he said would be

sufficient to carry him to the West Indies, and he accordingly took

leave of the light-house service.

[Sidenote: The Light is comparatively feeble.]

Mr John Reid, the principal light-keeper, stated, that every thing

specially connected with his department on board, answered its purpose

to his entire satisfaction. In stormy weather, however, when the ship

rolled much, great difficulty was experienced in trimming the lights,

which often required the assistance of all hands. In the course of this

night’s cruise, the writer had a good opportunity of observing the

lights at different distances from the vessel. Even at the distance

of two or three leagues, it appeared feeble, compared with a regular

reflecting-light. It was also upon the whole so unsteady, from the

rolling motion of the ship, that, in running for it, mariners could

never venture to make very free with their course.

[Sidenote: Landing at the rock found difficult.]

At day-break, on the following morning, the Light-house Yacht, attended

by a boat from the Floating-light, again stood towards the Bell Rock.

On coming within a proper distance of it, the usual tools carried by

the artificers on such occasions were put into this boat, and every

thing was got into a state of readiness for making an attempt to land.

The weather felt extremely cold this morning, the thermometer being at

34 degrees, with the wind at east, accompanied by occasional showers

of snow, and the marine barometer indicated 29.80. At half-past 7,

the sea ran with such force upon the rock, that it seemed doubtful if

a landing could be effected. At half-past 8, when it was fairly above

water, the writer took his place in the Floating-light’s boat with the

artificers, while the Yacht’s boat followed, according to the general

rule of having two boats afloat in landing expeditions of this kind,

that in case of accident to one boat, the other might assist. After

several unsuccessful attempts, the boats for a time were beat back by

the breach of the sea upon the rock. On the eastern side, it separated

into two distinct waves, which came with a sweep round to the western

side where they met; and at the instant of their confluence, the water

rose in spray to a considerable height. Watching what the sailors term

a _smooth_, we caught a favourable opportunity, and in a very dexterous

manner the boats were rowed between the two seas, and made a favourable

landing at the western creek.

[Sidenote: State of the Beacon.]

At the latter end of last season, as was formerly noticed, the Beacon

was painted white, and from the bleaching of the weather and the sprays

of the sea, the upper parts were kept clean; but within the range of

the tide, the principal beams were observed to be thickly coated with a

green stuff, the conferva of botanists. Notwithstanding the intrusion

of these works, which had formerly banished the numerous seals that

played about the rock, they were now seen in great numbers, having

been in an almost undisturbed state for six months. It had now also,

for the first time, got some inhabitants of the feathered tribe: in

particular the Scarth or Cormorant, and the large Herring-gull, had

made the Beacon a resting-place, from its vicinity to their fishing

grounds. About a dozen of these birds had rested upon the cross beams,

which, in some places, were coated with their dung; and their flight,

as the boats approached, was a very unlooked for indication of life

and habitation on the Bell Rock, conveying the momentary idea of the

conversion of this fatal rock, from being a terror to the mariner, into

a residence of man, and a safe-guard to shipping.

[Sidenote: Propriety of converting it into a Barrack.]

Upon narrowly examining all the parts of the Beacon, then in the state

represented in Plate VIII., and especially the great iron stanchions

with which the beams were fixed to the rock, the writer had the

satisfaction of finding that there was not the least appearance of

working or shifting at any of the joints or places of connection; and

excepting the loosening of the bracing-chains, every thing was found

in the same entire state in which it had been left in the month of

October. This, in the estimation of the writer, was a matter of no

small importance to the future success of the work. He, from that

moment, saw the practicability and propriety of fitting up the beacon,

not only as a place of refuge in case of accident to the boats in

landing, but as a residence for the artificers during the working

months. With a view to this, he determined on the entire removal of the

bracing-chains, which, in general, were either so relaxed or loosened

by the unlocking of the screws, the stretching of the links, or the

drawing of the chain-bats, from the tremulous motion of the beacon, as

to be comparatively of little use. Measures were therefore taken for

procuring great iron-bars to fix in a horizontal position between each

pair of the principal beams, at the height of about 8 feet from the

rock, as the best means of strengthening them.

[Sidenote: Bread and water chest.]

Having made these remarks upon the lower parts of the beacon, and

its connection with the rock, the writer ascended to the higher

parts, where he had also the satisfaction to find that the fixtures

of the cross beams were in the same good condition. Upon looking

into the bread and water-chest fixed on the top, in case of accident

to the boats, or in the event of shipwreck upon the Bell Rock, the

sea-biscuits which had been carefully put into a tin cannister, were in

good order; but, in the compartment of the chest allotted for water,

the fragments of several of the quart bottles in which it was contained

were found, which had probably burst with the freezing of the water,

for it can hardly be supposed to have arisen from the shaking or

tremulous motion of the beacon; be this as it may, only twelve of the

eighteen bottles remained entire.

[Sidenote: Advantages of the Beacon in its present state.]

While upon the top of the beacon, the writer was reminded by the

Landing-master, that the sea was running high, and that it would be

necessary to set off while the rock afforded any thing like shelter to

the boats, which, by this time, had been made fast by a long line to

the Beacon, and rode with much agitation, each requiring two men with

boat-hooks to keep them from striking each other, or from ranging up

against the beacon. But even under these circumstances, the greatest

confidence was felt by every one, from the security afforded by this

temporary erection. For, supposing that the wind had suddenly encreased

to a gale, and that it had been found unadvisable to go into the boats;

or, supposing they had drifted or sprung a leak from striking upon the

rocks; in any of these possible and not at all improbable cases, those

who might thus have been left upon the rock had now something to lay

hold of, and, though occupying this dreary habitation of the sea-gull

and cormorant, affording only bread and water, yet _life_ would be

preserved, and, under all such circumstances, the mind would still be

supported, by the hope of being ultimately relieved. After, with some

difficulty, getting off the Beacon, a proper time was again watched,

and, by active rowing, the boats soon cleared the Rock in safety,

though not without shipping two or three pretty heavy seas. About 12

noon the Light-house Yacht bore away, and at 7 in the evening she

reached the Bay of Arbroath, where the writer landed about 8 P. M., and

on the following day returned to Edinburgh.

[Sidenote: Impress Service, how it affected the Bell Rock operations.]

The Impress Service--that much-to-be-regretted system--being in great

activity, not only at the larger ports, but, owing to the pressure of

the war with France and the Northern Powers, orders having likewise

been issued for the establishment of an Impress at Dundee, Arbroath

and Aberdeen, it became necessary to be doubly careful in obtaining

protections for all our seamen. There being now five vessels employed

in the service of the Commissioners of the Northern Light-houses,

including the Bell Rock craft, a requisition was accordingly made

to the Admiralty for a protection for 35 seamen, which was readily

granted. In so far as the liberty of the subject is infringed by the

impress service, its existence is much to be regretted; but, in regard

to the works in question, it had the effect of rendering them popular,

instead of their being shunned by seamen, which might otherwise have

been the case.

[Sidenote: Protection Medal.]

As the impress officers were extremely rigid in the execution of their

duty, it became necessary to have the seamen carefully identified;

and, therefore, besides being described in the usual manner in the

Protection-bills, which, agreeably to the Admiralty regulations, must

always remain on board of the respective ships for which they are

granted, it was found advisable to give each man a ticket, descriptive

of his person, to which was attached a silver medal emblematical of

the Light-house service, as represented in Plate XII. On the one side

of this medal was the figure of the Bell Rock Light-house, and on the

other, the word ‘Medal,’ referring to the Admiralty Protection, and a

description of the person by the Engineer. The following is a copy of

the ticket of one of our best seamen.

[Sidenote: 1808, April.]

[Sidenote: Protection Ticket.]

“_Bell Rock Work-yard, Arbroath, 31st March 1808._

“John Pratt, seaman in the service of the Honourable the

Commissioners of the Northern Light-houses, aged 35 years, 5 feet 8

inches high, black complexion, and slightly marked with the small-pox.

“ROBERT STEVENSON,

“_Engineer for Northern Light-houses_.”

OBVERSE.

“The bearer John Pratt, is serving on board of the Sir Joseph

Banks Tender and Craft, employed at the erection of the Bell Rock

Light-house.

The signature of the Master of the Tender, “DAVID TAYLOR.

The signature of the bearer, “JOHN PRATT.”

These tickets were found to be indispensably necessary in the

Light-house service, as it was impossible that every man, or even each

boat’s crew, could carry the ship’s protection about with them. But the

check afforded by the several signatures as noted above, was generally

respected by the Impress officers.

[Sidenote: Light-house Yacht again visits the Rock.]

Directions having been given in the month of March for tightening the

bracing-chains, and fixing certain ring-bolts, both at the eastern and

western landing places of the rock, for the conveniency of the boats,

the Light-house Yacht again sailed on the 12th of April, carrying off

artificers and all necessaries for the service. After accomplishing

this duty she returned to Arbroath on the 14th, and in this state

things remained till the commencement of the works in the month of May.

[Sidenote: Preparatory state of the Works.]

The several implements already alluded to and described, were in a

state of great forwardness about the close of the winter, having been

prepared in Edinburgh, under the immediate directions of the writer.

At Aberdeen, Mr Alexander Gildowie, stone-agent, used every exertion

to procure an additional supply of granite from Rubislaw and other

quarries. But the severity of the winter was such as to prevent much

progress from being made. At Mylnefield Quarry, owing to the liability

of that stone to board or split in frosty weather, from its lying in

regular strata, by which moisture is more readily absorbed and acted

upon in the laminæ, the operations had been entirely suspended for

several months.

[Sidenote: Use of Granite restricted to the lower courses.]

In the month of April, the writer visited the works at Arbroath,

which he found still in a much retarded state, for want of a regular

supply of granite. Owing to this, it had not as yet been possible to

complete even one entire course of the building, although the figure

and dimensions of the moulds had been repeatedly altered to accommodate

the quarries. It had already become apparent, that the works would

unavoidably be stopped, if the whole of the outward casing were to

consist of granite. In order, therefore, to avoid a circumstance which

might prove hazardous to the whole operations, the Light-house Board

resolved to restrict the use of this material to the lower courses of

the building.

[Sidenote: Use of Sandstone extended.]

It having thus been found necessary to lessen the quantity of granite

at the Bell Rock, and proportionally to encrease the quantity of

sandstone, a new engagement was entered into with the proprietor of

Mylnefield, for an additional supply, at the rate of one shilling and

sixpence _per_ cubic foot, put free on board. On visiting this quarry

in the month of April, the writer had assurance of being largely

supplied with stone, if a greater range or variety in the thickness

of the courses were allowed. This, however desirable, was altogether

impossible, in so far as regarded the lower courses; the thickness

of which could only be regulated piecemeal, as the dimensions of the

granite stones could be determined.

[Sidenote: Mr Skene’s contract to supply Granite.]

Every exertion had already been made on the part of Mr Skene of

Rubislaw, who had entered into a contract with the Light-house Board to

supply granite, at the rate of one shilling and threepence per cubic

foot, for the use of the Bell Rock,--having been chiefly induced to

enter into this contract, on account of the celebrity of the work;--but

after furnishing a few of the lower courses, he found that he could

not implement his agreement without incurring considerable loss, and

running the risk of retarding the building: he therefore applied to be

relieved of his contract. From the commencement of the work, Mr Skene

had, with much liberality, stated, that in case the quarries upon his

estate should be found defective in producing the necessary size and

quantity of materials, his contract should never be allowed to form any

bar or stoppage to the Commissioners in applying to others. This had

accordingly been acted upon by the Stone-agent; but after making every

exertion for the space of about 12 months, he had been able to procure

only a few additional blocks of the requisite dimensions, even with

the range of all the quarries of Aberdeen, besides those of Rubislaw.

The price of suitable blocks had, in the mean time, advanced to three

shillings and threepence, and even to five shillings per cubic foot. At

the commencement of the Bell Rock works, the quarries of Aberdeen were

chiefly worked for paving-stones, and for common house purposes, and

were consequently unprovided with implements or tools suitable either

for working or transporting stones of large dimensions, for which they

had hitherto had no regular demand.

[Sidenote: He is remunerated for loss.]

Mr Skene having sustained considerable pecuniary loss, in opening

additional quarries for the Light-house, he had certain claims upon the

Board, which were remitted to Mr Kennedy, advocate, of Aberdeen, upon

whose opinion and report remuneration was made to the extent of about

L. 370.

[Sidenote: The Sir Joseph Banks takes the station of the Light-house

Yacht.]

The Light-house Yacht being employed in the general service of the

Northern Light-houses, she left the Bell Rock on the 16th of April,

to load stores at Leith. But the Sir Joseph Banks Tender being now

completely equipped, she sailed to supply her station, for the first

time, on the 20th of May, having on board several sets of moorings for

the use of the vessels in attendance at the Rock. The mushroom-anchors

of these moorings weighed about one ton each, and had about thirty-two

fathoms of chain attached to them, which was made from iron, measuring

seven-eighths of an inch in thickness. These moorings were laid down in

fourteen fathoms water, at about 200 fathoms apart, on a rocky bottom,

and at the distance of about a quarter of a mile on the north-western

side of the Rock, as will be seen from Plate V. After completing this

operation, and supplying the Floating-light with necessaries, the

Tender returned to Arbroath previously to the commencement of the

operations at the Rock for the season.

[Sidenote: 1808, May.]

[Sidenote: Wednesday 25th.]

[Sidenote: The writer begins the operations of the season.]

In the month of May, the number of artificers in the work-yard,

consisting of masons, smiths, mill-wrights, joiners and labourers,

amounted to sixty. On the 25th, the writer embarked at Arbroath, on

board of the Sir Joseph Banks, for the Bell Rock, accompanied by Mr

Logan _senior_, foreman-builder, with twelve masons, and two smiths,

together with thirteen seamen, including the master, mate and steward.

The vessel sailed at 3 o’clock P. M., under a salute of three hearty

cheers from a great assemblage of people on the quays; but before

getting to the Rock, it was too late for making fast to the moorings

that night; and she kept cruising about, with the Floating-light in

view, which proved a great comfort to the seamen, in directing them to

tack the ship, before she got too near the Rock.

On this occasion, the prospects of the writer were very different

from the state of things upon his sailing to commence the last year’s

operations, when much doubt and uncertainty attended every step. The

experience of last season, together with the facility and confidence

afforded by the erection of the Beacon, which had withstood the storms

of a winter, together with the use of a new Tender, which could now be

moored so near to the Rock as to be perfectly convenient for the boats,

and was at the same time capable of being cast loose from her moorings,

to take the people on board on any emergency;--these circumstances gave

a degree of security and promptitude to the work, which relieved all

concerned of much anxiety.

[Sidenote: Thursday 26th.]

The wind to-day was at south-east, and though the weather was not

very pleasant, yet it was moderate. Mr James Wilson, now Commander

of the Pharos Floating-light, and Landing-master, in the room of Mr

Sinclair, who had left the service, came into the writer’s cabin this

morning at 6 o’clock, and intimated that there was a good appearance

of landing on the rock. The bell being accordingly rung, the boats

were hoisted out, and at half-past 7 the artificers were seated and

arranged by the landing-master in their respective boats, who, with

the foreman-builder, went into the boat on the _off-side_, while the

writer steered the one on the side of the ship next to the Rock. Every

thing being arranged, both boats proceeded in company, and at 8 A. M.

they reached the Rock. The light-house colours were immediately hoisted

upon the flag-staff of the Beacon, a compliment which was duly returned

by the tender and floating-light, when three hearty cheers were given,

and a glass of rum was served out to all hands, to drink success to the

operations of 1808.

[Sidenote: State of the Bell Rock after the storms of winter.]

When the writer made a landing here, in the month of March, he was

so entirely occupied in examining all the parts of the Beacon, that

little attention was paid to the general appearance of the Rock.

Its surface was now found to be covered with a new crop of _Fuci_,

where it had been destroyed and rubbed off in the course of the last

season. Even the iron work, and lower parts of the Beacon, and the

site of the foundation of the Light-house, where it had been dressed

and worked with the pick, was now also thickly coated with a species

of _Conferva_, of a deep green colour, resembling very fine grass

where the water had left it, while in the pools it had the most

beautiful arborescent appearance. The limpets and white bucky were,

as formerly, in considerable numbers, and the barnacle had coated all

the higher parts of the rock, giving it a whitish appearance. On the

extreme points, a few detached clusters of mussels were seen, of a very

diminutive size, varying from a quarter to half an inch in length.

The six blocks of granite, which had been landed as an experiment

on the 1st of September 1807, were now scattered about in different

directions, covered with the delicate looking plant above described.

The general aspect of the rock remained otherwise unaltered.

[Sidenote: State of the Foundation-pit.]

The north-western half of the site of the building being higher than

the other, it had, in the course of last season, been wrought down to

a regular surface; but the other half contained depressions or holes,

varying in depth from six inches to no less than three feet. By 8

o’clock the tide had left the higher parts of the foundation dry, when

it appeared from observation, that the water ebbed at the rate of one

inch in two minutes and thirty seconds, and that the difference of

the perpendicular height, between the lowest and highest parts of the

foundation-pit, at the commencement of the works this season, was still

about four feet. After having been an hour and three quarters at work,

the water began to overflow the site of the building, when the boats

left the rock, the landing-master taking the lead; but after getting

clear, he waited, agreeably to usual practice, till the other boat got

out of the creek, when both proceeded for the Tender.

[Sidenote: Landing attended with considerable difficulty.]

In the evening tide the artificers landed at a quarter past 7, though

the sea ran pretty high, and the boats shipped a good deal of water.

Being rather early in the tide for working at the site of the building,

the time was occupied in getting the smith’s forge put in order upon

the cross-beams of the Beacon, a step of great importance to the future

progress and advancement of the work. At half-past 7, the higher parts

of the foundation being left dry, a few of the artificers set to work,

the others beginning as the water went off. At half-past 9 the tide

again overflowed the rock, when the boats left it, after the artificers

had been two hours at work. In coming out at the eastern creek this

evening, the landing-master’s boat was struck by a heavy sea, and

thrown to one side of the creek; but, by his dextrous management, the

boat’s head was fortunately kept seaward, and she got out in safety,

though not without having shipped a good deal of water.

[Sidenote: Friday, 27th.]

This morning the wind was at east, blowing a fresh gale, the weather

being hazy, with a considerable breach of sea setting in upon the

rock. The morning-bell was therefore rung, in some doubt as to the

practicability of making a landing. After allowing the Rock to get

fully up, or to be sufficiently left by the tide, that the boats might

have some shelter from the range of the sea, they proceeded at 8 A. M.,

and upon the whole made a pretty good landing; and after two hours and

three quarters’ work returned to the ship in safety.

[Sidenote: Found necessary still to excavate to the depth of fourteen

inches.]

In the afternoon the wind considerably increased, and as a pretty heavy

sea was still running, the Tender rode very hard, when Mr Taylor, the

commander, found it necessary to take in the bowsprit, and strike

the fore and main top-masts, that she might ride more easily. After

consulting about the state of the weather, it was resolved to leave

the artificers on board this evening, and carry only the smiths to

the Rock, as the sharpening of the irons was rather behind, from

their being so much broken and blunted, by the hard and tough nature

of the rock, which became much more compact and hard as the depth of

excavation was increased. Besides avoiding the risk of encumbering the

boats with a number of men, who had not yet got the full command of

the oar in a breach of sea, the writer had another motive for leaving

them behind. He wanted to examine the site of the building without

interruption, and to take the comparative levels of the different

inequalities of its area; and as it would have been painful to have

seen men standing idle upon the Bell Rock, where all moved with

activity, it was judged better to leave them on board. The boats landed

at half-past 7 P. M., and the landing-master, with the seamen, was

employed during this tide, in cutting the sea-weeds from the several

paths leading to the landing-places, to render walking more safe,

for, from the slippery state of the surface of the rock, many severe

tumbles had taken place. In the mean time the writer took the necessary

levels; and having carefully examined the site of the building, and

considered all its parts, it still appeared to be necessary to excavate

to the average depth of fourteen inches, over the whole area of the

foundation. Having made these remarks, we again left the rock, at

half-past 9, after having been two hours upon it. At the entrance of

the eastern creek, the sea ran high, and all on board got a thorough

wetting; but so long as the boats were kept from striking upon the

rock, the sprays which came on board were but little regarded.

[Sidenote: Saturday 28th.]

[Sidenote: Artificers much afflicted with sea-sickness.]

The wind still continued from the eastward, with a heavy swell; and

to-day it was accompanied with foggy weather, and occasional showers of

rain. Notwithstanding this, such was the confidence which the erection

of the Beacon had inspired, that the boats landed the artificers on the

Rock, under very unpromising circumstances, at half-past 8, and they

continued at work till half-past 11, being a period of three hours,

which was considered a great tide’s work, in the present low state of

the foundation. Three of the masons on board were so afflicted with

sea-sickness, that they had not been able to take any food for almost

three days, and they were literally assisted into the boats this

morning by their companions. It was, however, not a little surprising,

to see how speedily these men revived upon landing on the Rock and

eating a little dulse. Two of them afterwards assisted the sailors in

collecting the chips of stone, and carrying them out of the way of

the pickmen; but the third complained of a pain in his head, and was

still unable to do any thing. Instead of returning to the tender with

the boats, these three men remained on the Beacon all day, and had

their victuals sent to them along with the smiths. From Mr Dove, the

foreman-smith, they had much sympathy, for he preferred remaining on

the Beacon at all hazards, to be himself relieved from the malady of

sea-sickness. The wind continuing high, with a heavy sea, and the tide

falling late, it was not judged proper to land the artificers this

evening, but in the twilight the boats were sent to fetch the people on

board who had been left on the Rock.

[Sidenote: Sunday 29th.]

[Sidenote: Misunderstanding among the Artificers about their wages.]

The wind was from the S. W. to-day, and the signal-bell rung, as usual,

about an hour before the period for landing on the Rock. The writer was

rather surprised, however, to hear the landing-master repeatedly call,

“All hands for the Rock;” and, coming on deck, he was disappointed to

find the seamen only in the boats. Upon inquiry, it appeared, that some

misunderstanding had taken place about the wages of the artificers

for Sundays. They had preferred wages for seven days statedly, to

the former mode of allowing a day for each tide’s work on Sunday; as

they did not like the appearance of working for double or even treble

wages on Sunday, and would rather have it understood that their work

on that day arose more from the urgency of the case, than with a view

to emolument. This having been judged creditable to their religious

feelings, and readily adjusted to their wish, the boats proceeded

to the Rock, and the work commenced at 9 A. M. The artificers were

chiefly employed in removing the iron-stanchions, or frame-work of the

forge, which had last year been fixed on the rock, and which was now

set on a temporary scaffold erected for it on the Beacon. Having now

got two smiths’ hearths above the reach of the tide, the work of this

department made great progress, both in the sharping of the numerous

picks and irons, and in making bats for fixing the different railway

tracks upon the Rock. After getting three and a half hours’ work, the

boats returned to the ship at 12 noon, when the excellent prayer,

composed by the Rev. Dr Brunton, given in a former part of this work,

was read upon the ship’s quarter-deck, in the same manner as had been

done last year.

The sloop Smeaton arrived this afternoon with a quantity of cast-iron

rails, to be laid upon the Rock, for transporting the blocks of stone

from the different landing-places to the site of the building. She had

also on board some Norway logs, intended to be batted on the Rock, for

supporting the railways across the gullies, or inequalities of the

surface. The boats of the Sir Joseph Banks and Floating-light, being

employed during the evening tide in delivering the Smeaton, by landing

the cast-iron on the Rock, and bringing the timber on board of the

Tender, the artificers could not be landed this evening.

[Sidenote: Monday 30th.]

[Sidenote: Fish very abundant at the rock.]

The weather to-day was moderate, and there was much less breach in the

sea than there had been since the commencement of the work this season.

The wind kept steadily in the south-west, and the barometer had changed

its range from 29.40 to 29.90, and the thermometer from about 40° to

45°. The abundance of fish caught near the Rock was another proof of

the more favourable state of the weather; for the fish never failed

to come upon the anchorage-ground during good weather, while they as

regularly disappeared on a change for the worse.

The Tender’s bell rung this morning, as the signal for going to the

Rock, at 9 o’clock; and at half-past 9, the water having partially

left the foundation-pit, the work commenced, and continued two and

three-fourth hours, or till a quarter from 1 o’clock P. M., when the

tide again overflowed the whole site of the building. The masons

and seamen returned with the boats on board the Tender, but the

mill-wrights and joiners, who had come off with the Smeaton to fit up

the railways, and such of the masons as were apt to be sick, remained

with the smiths on the Beacon throughout the day.

[Sidenote: General usefulness of Sailors as men of all works.]

The number of workmen at the Rock was now increased to twenty-eight,

including six sailors from the landing-master’s crew, who were

constantly employed in baling water, and keeping the foundation clear

of the chips, struck off by the pick. They also conveyed the irons to

the forge, by hoisting them up to the Beacon by a _whip-tackle_. The

seamen were of the greatest service in many of the operations, for

_Jack_ is a man of all trades; but as they had their boats to attend,

and were always at the landing-master’s call, they were not taken into

account in the enumeration of artificers.

[Sidenote: Mortar Gallery fitted up.]

Mr Francis Watt commenced, at this tide, with five joiners, to fit up

a temporary platform upon the Beacon, about twenty-five feet above

the highest part of the Rock. This platform was to be used as the

site of the smith’s forge, after the Beacon should be fitted up as a

barrack; and here also the mortar was to be mixed and prepared for

the building, and it was accordingly termed the Mortar Gallery. This

platform was supported with joisting, well framed, and properly fixed

to the principal beams; but the flooring or boarding, though two inches

in thickness, was only slightly nailed to the joisting, so that when

the sea rose, and struck it in bad weather, it might lift, without

endangering the general frame of the fabric. At the end of the working

season this floor was lifted, and the joisting only left during the

winter months.

[Sidenote: Smeaton is ballasted at the Bell Rock.]

The landing-master’s crew completed the discharging from the Smeaton

of the remainder of her cargo of the cast-iron rails and timber. It

must not here be omitted to notice, that the Smeaton took in ballast

from the Bell Rock, consisting of the shivers or chips of stone,

produced by the workmen in preparing the site of the building, which

were now accumulated in great quantities on the Rock. These the boats

loaded, after discharging the iron. The object in carrying off these

chips, besides ballasting the vessel, was to get them permanently

out of the way, as they were apt to shift about from place to place,

with every gale of wind; and it often required a considerable time to

clear the foundation a second time of this rubbish. The circumstance

of ballasting a ship at the Bell Rock afforded great entertainment,

especially to the sailors; and it was perhaps with truth remarked, that

the Smeaton was the first vessel that had ever taken on board ballast

at the Bell Rock.

[Sidenote: Tuesday, 31st.]

The winds were variable to-day, but chiefly from the north, accompanied

with fine weather. On landing at a quarter from 11 A. M., the higher

parts of the site of the building were dry, and the work continued two

and a quarter hours, when it was again stopped by the return of the

flood-tide. The joiners and smiths, together with those who were apt

to be sick on board of the Tender, remained on the Beacon throughout

the day, and at a quarter past 1 P. M. the boats left the Rock with the

masons.

There were eighteen seamen from the Smeaton, Sir Joseph Banks, and

Floating-light, employed to-day under the direction of Mr Wilson, the

landing-master, in laying the cast-iron work of the railways in a

compact manner, into the various crevices and holes in the Rock, to

prevent its being tossed about by the sea, until it should be wanted in

the course of fixing the tracks to the Rock.

[Sidenote: Chips of the rock in great request at Leith.]

The Smeaton being finally discharged, and partly loaded with stone

shivers from the Bell Rock, she sailed for Leith, in order to fetch

the remainder of the cast-iron, and some additional logs of timber. Mr

Pool, the commander of this vessel, afterwards acquainted the writer,

that when the ballast was landed upon the quay at Leith, many persons

carried away specimens of it, as part of a cargo from the Bell Rock;

when he added, that such was the interest excited, from the number of

specimens carried away, that some of his friends suggested, that he

should have sent the whole to the Cross of Edinburgh, where each piece

might have sold for a penny.

[Sidenote: Fish caught at the Bell Rock.]

In the evening the boats went to the Rock, and brought the joiners

and smiths, and their sickly companions, on board of the Tender.

They also brought with them two baskets full of fish, which they had

caught at high water, from the Beacon, reporting, at the same time, to

their comrades, that the fish were swimming in such numbers over the

rock at high water, that it was completely hid from their sight, and

nothing seen but the movement of thousands of fish. They were almost

exclusively of the species called the Podlie, or young Coal-fish.

This discovery, made for the first time to-day by the workmen, was

considered fortunate, as an additional circumstance likely to produce

an inclination among the artificers to take up their residence in the

Beacon, when it came to be fitted up as a barrack.

[Sidenote: 1808, June.]

[Sidenote: Wednesday, 1st.]

The boats landed to-day at 11 A. M., but the tides being neap, the

water went off very slowly, and it was 12 noon before it left the

site of the building. After continuing at work one hour and three

quarters, the artificers left the rock with all hands, when the tender

immediately got under weigh, or rather _cast off_ from her moorings,

by simply letting go one end of the mooring hawser, and sailed for

Arbroath. But the wind being N.N.W., it was 8 o’clock P. M. before she

got into the harbour.

[Sidenote: Saturday, 4th.]

[Sidenote: First course finished to-day. Its cubical contents, &c.]

This being the birth-day of King George III., who now entered into the

70th year of his age, and 50th of his reign, a considerable effort

was made to get the first entire course of the building laid upon the

platform at Arbroath, where it was to be marked and numbered, and

made ready for shipping for the Rock. It may seem strange, that after

continuing the operations of the work-yard for about twelve months,

there should only have been but one course ready to ship for the Rock.

Such also was the difficulty of procuring granite of a large size,

that this course was obliged to be hewn of the thickness of only one

foot. The chief advantage of thick courses in water buildings, besides

a saving of hewing, is that of getting sooner out of the reach of the

tide, there being nearly as much time necessary for laying a thin

course as a thick one. The stones for the first entire course were not

quarried particularly for it, but were taken from the whole materials

in the yard. The enumeration of the various kinds and quantity of work

in this single course of the Light-house, may perhaps surprise the

reader. Though only one foot in thickness, it contained 508 feet cubic

of granite in outward casing; 876 feet cubic of Mylnefield stone in the

hearting; 104 tons of solid contents; 132 feet superficial of hewing

in the face work; 4519 feet superficial of hewing in the beds, joints

and joggles; 420 feet lineal boring of trenail holes; 378 feet lineal

cutting for wedges; 246 oaken trenails; 378 oaken wedges in pairs.

[Sidenote: Certainty of commencing building this season.]

In the work-yard, about sixty stone cutters were employed in hewing and

preparing the various courses of the solid part of the building. Stones

were now got pretty readily from Mylnefield quarry; and besides the

quarries at Aberdeen, others had been opened near Peterhead, belonging

to Mr John Hutchison, which produced a great many fine blocks. As much

of the Aberthaw limestone had been broken and prepared for burning

as would charge the kiln. A number of casks of the capacity of about

32 gallons, had also been provided and were ready to be filled, in

equal numbers, of clean sharp sand, lime and pozzolano earth, in the

state of fine powder. After much trouble and correspondence with

timber-merchants in Leith, London, and other parts, a considerable

quantity of trenails and wedges of British oak were procured, which

were to be used in connecting the courses of the solid part of the

building, while the works were low, and in danger of being washed away

or injured by the sea. These oaken trenails and wedges were made up in

bundles, containing about 20. In short, every thing was in a state of

readiness in the work-yard, for building the first three courses of

the Light-house. The preparations for its foundation at the Rock were

now also in considerable forwardness, and the works, upon the whole,

put on an appearance which left no doubt as to the commencement of the

building this season.

[Sidenote: Artificers sail for the Rock.]

The writer sailed from Arbroath in the evening of the 6th of June in

the Tender, with a fine breeze of northerly wind, having on board 34

artificers, consisting of masons, smiths, mill-wrights and joiners,

besides the landing master’s crew, consisting of twelve seamen, who

worked the ship. There were also on board Mr Peter Logan, foreman

builder; Mr Francis Watt, foreman mill-wright; Mr James Dove, foreman

smith; Mr James Wilson, landing master; Mr David Taylor, master; Mr

William Reid, mate, and Mr John Peters, steward, counting in all

fifty-four persons. The weather was clear, and the vessel had no sooner

got out of the harbour, than the lights of the float were distinctly

seen; and before day-break, the Tender was made fast to her moorings

off the Bell Rock.

[Sidenote: Tuesday, 7th.]

[Sidenote: Arrangements at landing at an early hour on the Rock.]

At 3 o’clock in the morning, the ship’s bell was rung as the signal

for landing at the Rock. These artificers, to which this had been the

first trip, found their quarters rather confined in the ship, and some

of them being sickly, were glad of an opportunity of landing, and came

almost immediately upon deck, notwithstanding the earliness of the hour

at which the tide happened. But those who were more accustomed to the

business, calculated their time, knowing that sufficient warning was

always given, especially at hours so early. When the landing was to be

made before breakfast, it was customary to give each of the artificers

and seamen a dram and a biscuit, and coffee was prepared by the steward

for the cabins. Exactly at 4 o’clock, the whole party landed from

three boats, including one of those belonging to the Floating-light,

with a part of that ship’s crew, which always attended the works in

moderate weather. The landing-master’s boat called the Seaman, but more

commonly the Life-boat, took the lead. The next boat called the Mason,

was generally, steered by the writer; while the Floating-light’s boat

Pharos, was under the management of the boatswain of that ship.

[Sidenote: How the Artificers are employed.]