DETAILS OF CONSTRUCTION.

Fig. 1 is the plan of the well and the steps, landing and starting, at

the half-space landing. The lines marked C S are the direction of the

cuts to be made through the circular or well string for the risers to

mitre to.

Fig. 2 shows a piece of thin stuff cut to a semicircle to fit the

inside of the string. This piece is laid on the plan, and the position

and direction of the cuts for risers is marked on it as seen by C C.

Fig. 3 shows a section of a staved well, the joints being ploughed out

and cross tongues put in as shown. Each joint must be well glued and

rubbed and screwed through the back. It will be noticed it is carried

past the springing into the straight on both sides; this makes a better

job, as a joint made in the springing always has a crippled appearance,

no matter how well the job may be done.

Fig. 4 shows a falling mould for marking the treads and risers, also

the bottom edge of the well in a continuous line with the bottom edge

of the two straight strings. Take a thin lath and bend it around

Fig. 2, and mark on it the springing and risers, as shown by S S and

R R. Lay this lath on the piece of stuff the falling mould is to be

cut out of, in a horizontal position, as shown, and mark the risers

and springing. Set up a step above and below the springings, and set

off S S to equal S S, Fig. 2, Plate VIII. Then draw the under side of

straight strings and continue it across the well, taking care to have

the best possible falling line. H H shows the length the pieces forming

the well will require to be. This falling mould may be made out of good

stiff brown paper, or any other suitable stuff. Now bend it around on

the inside of the well, and mark the treads and risers and the bottom

edge. Keep the springing lines on the mould to the springing marked

on the well. To mark the springing on the well take Fig. 2 and hold

in the well, and mark the springing top and bottom and finish it with

a straight edge. Also mark the direction of the cuts as shown by the

lines marked C.

Fig. 5 shows how the well is fixed to the straight strings. This must

be all fitted in the shop ready to slide up in its place when the

stairs are fixed, when it should be well glued, wedged and screwed. The

circular string for the starting and top landing of Fig. 1, Plate VII.,

may be got out and fixed in the same way. These kind of wells answer

the purpose for which they are used, but they are not so strong as a

veneered well, which is shown on Plate XI.

Fig. 6 shows the step starting from the half-space landing. This step

is slightly curved at the end to make it the same width on the end as

the rest. The risers, starting and landing are laid down to suit the

rail, as shown in Plate XVII.

Fig. 7 shows the return nosing for this step.

Fig. 8 shows the landing step. This is got out long enough to reach

from wall to wall. This step is glued up in the shop with the rest; the

nosing is worked on the solid and returned as far as E, about 2 or 3

inches on. The scotia is fixed around the circular part after all is

fixed.

Fig. 9 shows the top landing step. This too goes from wall to wall, and

is treated in the same way as Fig. 8, only the nosing is worked from

end to end.

[Illustration: PLATE 10.]

Practical Stair Building and Handrailing By the square section and falling line system. · 第 39 / 78 题