NUMBER OF MEN.

The number of men required is determined by the amount of concrete to be

placed in a given time, the method of mixing, and the size of the batch;

that is, the number of bags of cement mixed at one time. The amount of

concrete one man can mix by hand in a day depends upon the experience of

the man, the layout of the work, and other duties required of him. One

man should average 1-1/2 to 1-3/4 cubic yards of concrete in eight hours,

including mixing and wheeling not more than 50 feet.

The gang for a one-bag batch may consist of 3 men, but a larger number

make a more efficient force, for when the concrete is mixed by hand the

men can take turns at the various tasks and will not tire so easily. The

assigning of tasks so that each man's time fits into that of the others

requires considerable study and is one of the chief factors making for

loss or profit.