TABLE 32.--VOLUME OF CONCRETE PER BATCH, WITH VARIOUS KINDS OF STONE.

========+===========+================+===========+==================|

| | Resulting | |

| DESCRIPTION OF STONE. |volume per | |

Mixture.|-----------+----------------| barrel of | Remarks. |

| | |cement, in | |

| Passed | Retained on | cubic | |

| screen. | screen. | yards. | |

--------+-----------+----------------+-----------+------------------|

1:2½:5 | 1½-in. | 3/8-in. | 0.815 | Measured in air |

1:2½:5 | 2½-in. |Run of crusher. | 0.827 | " " " |

1:2½:5 | -- |General average.| 0.808[D]|Measured from plan|

1:2½:5 | 2-in. | 1½-in. | 0.768[E]| " " " |

========+===========+================+===========+==================|

[D] Average for whole of River Tunnel section.

[E] Average from 7,400 cu. yd. in Land Tunnel section.

The sand used was practically the same for the whole of the river tunnel

section, and was supposed to be equal to "Cow Bay" sand. The result of

the mechanical analysis of the sand is shown on Plate XLVI. The stone

was all trap rock. For the early part of the work it consisted of stone

which would pass a 2-in. ring and be retained on a 1½-in. ring, in

fact, the same as used for the land tunnels. This was found to be too

coarse, and for a time it was mixed with an equal quantity of fine

gravel or fine crushed stone. As soon as it could be arranged,

run-of-crusher stone was used, everything larger than 2½ in. being

excluded. About three-quarters of the river tunnel concrete was put in

with run-of-crusher stone. The force was:

_At Manhattan._

1 Foreman @ $3.00 per shift

4 Men on sand and stone cars " 1.75 " "

4 Men handling cement " 1.75 " "

2 Men dumping mixers " 1.75 " "

_At Weehawken._

1 Foreman @ $3.00 per shift

2 Men hauling cement " 1.75 " "

2 Men dumping mixers " 1.75 " "

The average quantity of concrete mixed per 10-hour shift was about 117

batches, or about 90 cu. yd. The maximum output of one of the mixers was

about 168 batches, or 129 cu. yd. per 10-hour shift.

Transportation.

_Surface Transportation._--At Manhattan the stone and sand were received

in scows at the wharf on the river front. For the first part of the

work, the wharf at 32d Street and North River was used, and while that

was in use the material was unloaded from the scows into scale-boxes by

a grab-bucket running on an overhead cable, and then teamed to the

shaft. For the latter part of the work, the wharf used was at 38th

Street and North River, where facilities for unloading were given to the

contractor by the Pennsylvania Railroad Company which was the permanent

lessee of the piers. The material was unloaded into scale-boxes by a

grab-bucket operated by a derrick, and teamed to the shaft. When the

scale-boxes arrived at the shaft they were lifted from the trucks by

derricks and dumped into the bins.

At Weehawken all the stone and sand, with the exception of the stone

crushed on the work, was received by water at the North slip. Here it

was unloaded by a 2-cu. yd. grab-bucket and dumped into 3-cu. yd.

side-tipping cars, which were hauled by a small steam locomotive over

the trestle to the shaft, where they were dumped directly into the bins.

Before beginning the concrete lining, the 2-ft. gauge railway, which had

been used for the surface transportation during the driving of the

iron-lined tunnels, was taken up and replaced by a 3-ft. gauge track

consisting largely of 30-lb. rails. The cars were 3-cu. yd.

side-dumping, with automatic swinging sides. Two steam locomotives which

were being stored at Weehawken (part of the plant from another

contract), were used for hauling the cars in place of the electric ones

used with the 2-ft. gauge railway.

_Tunnel Transport._--The track used in the tunnel was of 2-ft. gauge,

laid with the 20-lb. rails previously used in driving the iron-lined

tunnels. The mining cars (previously mentioned in describing the driving

of the iron-lined tunnels) were used for transporting the invert

concrete, although, for most of the work, dumping buckets carried on

flat cars were used. Several haulage systems were considered for this

work, but not one of them was thought to be flexible enough to be used

with the constantly changing conditions, and it was eventually decided

to move all the cars by hand, because, practically all the work being

down grade, the full cars could be run down by gravity and the empty

ones pushed back by hand. Two men were allotted to each car, and were

able to keep the traffic moving in a manner that would have been perhaps

impossible with any system of mechanical haulage. This system was

apparently justified by the results, for the whole cost of the tunnel

transport, over an average haul of about 2,000 ft., was only about 50

cents per cu. yd., which will be found to compare favorably with

mechanical haulage on similar work elsewhere, provided full allowance is

made for the use of the plant and power.

_Force Employed._--The average force employed on transport, both on the

surface and in the tunnel, is shown in Table 33.

Costs.

During the work, careful records of the actual cost to the contractor of

carrying out this work were kept by the Company's forces; these costs

include all direct charges, such as labor and materials, and all

indirect charges such as head office, plant depreciation, insurance,

etc., but do not include the cost of any financing, of which the Company

had no information.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 51 / 55 题