TABLE 28 PART 2

====+====+=======+========+=======+=======+=============+========|

| | | |

| | | |

| | | |

| | | |

| | | |

| | | AVE. UNAVOIDABLE |

| | | DELAY PER |

| | AVERAGE TIME PER RING. | WORKING FACE. |

Cu. |Time|------------------------+-------+-------------+--------|

yd. |per |Shoving| | | | | Time |

per |cu. | and | | Lost | | Items |--------|

ring|yd. |mucking|Erecting| time | Total |not included |Ave unit|

----+----+-------+--------+-------+-------| in previous |--------|

Unit|Unit|Hrs Min|Hrs Min |Hrs Min|Hrs Min| figures |Hrs Min |

| | K | L | M | | | |

----+----+-------+--------+-------+-------+-------------+--------|

51 |0-27| 25 15| 3 41 | 0 02| 28 58|1st Bulkhead |136 00 |

45 |0-26| 19 31| 2 55 | 0 11| 22 37| 2d " |147 54 |

| | | | | | | |

39 |0-12| 7 31| 2 24 | 0 20| 10 15|Grouting |246 00 |

| | | | | | | |

43 |0-09| 6 46| 2 24 | 0 09| 9 19|Blow-outs | 91 11 |

| | | | | | | |

42 |0-06| 4 09| 2 51 | 0 10| 7 10|Miscellaneous|230 33 |

| | | | | | | |

43 |0-21| 14 47| 3 41 | 1 34| 20 02|Total |851 38 |

| | | | | | | |

----+----+-------+--------+-------+-------+-------------+--------|

| | | | | | | |

43 |0-18| 11 02| 2 54 | 0 16| 14 12| | |

----+----+-------+--------+-------+-------+-------------+--------|

12 |0-07| 1 20| 2 35 | 0 14| 4 12| | |

----+----+-------+--------+-------+-------+-------------+--------|

12 |0-05| 0 58| 1 44 | 0 10| 2 52| | |

----+----+-------+--------+-------+-------+-------------+--------|

| | | | | | | |

12 |0-06| 1 09| 2 05 | 0 12| 3 26| | |

----+----+-------+--------+-------+-------+-------------+--------|

20 |0-11| 3 33| 2 15 | 0 13| 6 01| | |

----+----+-------+--------+-------+-------+-------------+--------|

Average delay per ring--0 hrs. 44 min.

Average rings built by one shield = 1,146¼.

Average time per ring. 6 hr 01 min

Delays. 44 min

-----------

Total time per ring. 6 hr 45 min

NOTE.--The "unavoidable delays" included in this table do not embrace

the periods during which the work was at complete or partial standstill

due to experiments and observations, shortage of iron due to change of

design, and holidays.

K-Including time for jacks.

L-Including time spent by the whole gang on bolting; in

addition to this there was a small gang which spent its

whole time bolting.

M-Chiefly due to breakdowns of hydraulic lines and

erector.

_Air Pressure._--The air pressure varied from 17 to 37 lb. Behind the

river line it averaged 17 lb. and under the river 26 lb. Behind the

river lines the pressure was generally kept about equal to the water

head at the crown, except where at Weehawken, as previously described,

this was impossible.

In the silt the pressure was much lower than the hydrostatic head at the

crown, but if it became necessary to make an excavation ahead of the

shield, for example at the junction of the shields, the air pressure

required was about equal to the weight of the overlying material,

namely, the water and the silt, as the silt, which weighed from 97 to

106 lb. per cu. ft. and averaged 100 lb. per cu. ft., acted like a

fluid.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 49 / 55 题