TABLE 20.--WEIGHTS OF BORE SEGMENTS AND ACCESSORIES, IN POUNDS.

====================+=====+====================================

Part. | No. | Material. | Weight, in pounds.

--------------------+-----+---------------+--------------------

Bore Segment No. 1 | 1 | Cast Steel | 3,004.0

Bore Segment No. 2 | 1 | " " | 2,628.0

Distance piece | 1 | " " | 423.5

Key | 1 | " " | 34.3

Plug | 1 | " " | 1,192.5

Yoke | 1 | " " | 57.3

Dogs | 2 | " " | 106.0

Slot cover | 1 | Rolled steel | 6.4

Plug cover | 1 | Cast iron | 162.0

Dog holders | 2 | Rolled steel | 6.4

--------------------+-----+---------------+--------------------

Complete weight of one pair, without bolts| 7,620.4

==========================================+====================

_Sump Segments._--In order to provide sumps to collect the drainage and

leakage water in the subaqueous tunnels, special "sump segments" were

installed in each tunnel at the lowest point--about Station 241 + 00.

The details of the design are shown in Fig. 14. The segment was built

into the tunnel invert as though it were an ordinary "_A_" segment. In

building the sump, three lining castings were bolted, one on top of the

other, and attached to the flat upper surface of the sump segment;

meanwhile, the bolts attaching the sump segment to the adjacent tunnel

plates were taken out and the plate and lining segments were forced

through the soft mud by hydraulic jacks, the three 6-in. holes in the

bottom of the sump segment being opened in order to minimize the

resistance. The sump when built appeared as shown in Fig. 14, the top

connection being made with a special casting, as shown.

The capacity of each sump is 500 gal., which is about the quantity of

water entering the whole length of each subaqueous tunnel in 24 hours.

_Cross-Passages._--When the contract was let, provision was made for

cross-passages between the tubular tunnels, in the form of special

castings to be built into the tunnel lining at intervals. However, the

idea was given up, and these castings were not made. Later, however,

after tunnel building had started, the question was raised again, and it

was thought that such cross-connections would be very useful to the

maintenance forces, that it might be possible to build them safely, and

that their subsequent construction would be made much easier if some

provision were made for them while the shields were being driven. It was

therefore arranged to build, at intervals of about 300 ft., two

consecutive rings in each tunnel, at the same station in each tunnel,

with their longitudinal flanges together, instead of breaking joint, as

was usually done. The keys of these rings were displaced twelve bolt

holes from their normal positions toward the other tunnel. This brought

the keys about 6 ft. above the bench, so that if they were removed,

together with the _B_ plates below them, an opening of about 5 by 7 ft.

would be left in a convenient position with regard to the bench.

[Illustration: DETAILS OF SUMPS IN SUBAQUEOUS TUNNELS AT STATION 241

FIG. 14.]

Nothing more was done until after the tunnels were driven. It was then

decided to limit the cross-passages between the tubular tunnels to the

landward side of the bulkhead walls. They were arranged as follows:

three on the New York side, at Stations 203 + 22, 206 + 80, and 209 +

80, and two on the New Jersey side, at Stations 255 + 46 and 260 + 14.

The cross-passages are square in cross-section.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 24 / 55 题