TABLE 11.

==================+=========+========+=============+========+==========

Grade. |Total No.|Rate per|Drilling and |Mucking:|Timbering:

| | day. |blasting: No.| No. | No.

------------------+---------+--------+-------------+--------+----------

Superintendent | 1 | $7.70 | ½ | 1/8 | 3/8

Assistant engineer| 1 | 5.80 | ½ | 1/8 | 3/8

Electrician | 1 | 3.50 | ½ | 1/8 | 3/8

Engineer | 1 | 3.50 | | 1 |

Signalman | 1 | 2.00 | | 1 |

Foreman | 3 | 4.00 | 1 | 1 | 1

Driller | 5 | 3.00 | 5 | |

Driller's helper | 5 | 2.00 | 5 | |

Laborers | 14 | 2.00 | | 14 |

Timbermen | 3 | 3.00 | | | 3

" helpers | 4 | 2.00 | | | 4

Machinist | 1 | 4.00 | 1 | |

Blacksmith | 2 | 3.50 | 2 | |

" helper | 2 | 2.00 | 2 | |

Nipper | 2 | 2.00 | 2 | |

Waterboy | 1 | 2.00 | 1 | |

------------------+---------+--------+-------------+--------+---------

Total | 47 | | 20½ | 17-3/8 | 9-1/8

==================+=========+========+=============+========+=========

The general scheme of excavation is shown by Plate XXXIII. The bench was

kept 50 or 60 ft. behind the face of the heading. The powder used was

60% Forcite. The general system of drilling was as shown in Fig. 7. The

average length of hole drilled per cubic yard of excavation was 2.9 ft.,

as against 7.70 ft. at Manhattan; and the amount of powder used was 1.96

lb. per cu. yd., as against 1.24 lb. at Manhattan. There was little

timbering. A length of about 30 or 40 ft. adjoining the Weehawken shaft

was timbered, and also a shattered seam of about 17 ft. in width between

Stations 262 + 10 and 262 + 27.

[Illustration: LAND TUNNELS TYPICAL METHOD OF DRILLING USED IN THE

WEEHAWKEN TUNNELS FIG. 7]

The two entirely separate tunnels gave a cross-section which was much

more easily timbered than the wide flat span at Manhattan, and the

segmental timbering was amply strong without posts or other

reinforcement.

Table 12 is a summary of the cost of excavating the Land Tunnels, based

on actual records carefully kept throughout the work.

TABLE 12.--COST OF EXCAVATION OF LAND TUNNELS, IN DOLLARS PER CUBIC

YARD.

======================================+=========+=========+=============

| | |Total yardage

| | | and

|Manhattan|Weehawken|average cost.

--------------------------------------+---------+---------+-------------

Cubic yards excavated |43,289 | 8,311 | 51,600

_Labor._ | | |

Surface transport | $0.49| $0.87| $0.55

Drilling and blasting | 2.37| 1.55| 2.24

Mucking | 2.49| 2.08| 2.42

Timbering | 0.87| 0.18| 0.76

--------------------------------------+---------+---------+-------------

Total labor | $6.22| $4.68| $5.97

--------------------------------------+---------+---------+-------------

_Material._ | | |

Drilling | $0.15| $0.15| $0.15

Blasting | 0.21| 0.21| 0.21

Timber | 0.39| 0.20| 0.36

--------------------------------------+---------+---------+-------------

Total material | $0.75| $0.56| $0.72

--------------------------------------+---------+---------+-------------

Plant running | $0.76| $0.65| $0.74

Surface labor, repairs and maintenance| 0.15| 0.08| 0.14

Field office administration | 1.05| 1.18| 1.07

--------------------------------------+---------+---------+-------------

Total field charges | $8.96| $7.15| $8.64

--------------------------------------+---------+---------+-------------

Chief office administration | $0.34| $0.38| $0.34

Plant depreciation | 0.66| 1.01| 0.72

Street and building repairs | 0.27| | 0.23

--------------------------------------+---------+---------+-------------

Total average cost per cubic yard | $10.23| $8.54| $9.93

======================================+=========+=========+=============

Masonry Lining of Land Tunnels.

Plates XXXII and XXXIV show in detail the tunnels as they were actually

built. It will be seen that in all work, except in the Gy-East contract,

there was a bench at each side of each tunnel in which the cable

conduits were embedded. In Gy-East the bank of ducts which came next to

the middle wall was carried below subgrade, and the inner benches were

omitted.

The side-walls and subgrade electric conduits were water-proofed with

felt and pitch. The water-proofing was placed on the outside of the

side-walls (that is, on the neat line), and the space between the rock

and the water-proofing was filled with concrete. This concrete was

called the "Sand-Wall."

The general sequence of building the masonry lining is shown in Fig. 8.

The operations were as follows:

1.--Laying concrete for the whole height of the

sand-walls, and for the floor and foundations for

walls and benches up to the level of the base of

the conduits;

2.--Water-proofing the side-walls, and, where there was

a middle trench containing subgrade conduits,

laying and water-proofing these conduits;

3.--Building concrete wall for conduits to be laid

against, and, where there was a middle trench,

filling up with concrete between the conduits;

4.--Laying conduits;

5.--Laying concrete for benches and middle-wall;

6.--Building haunches from top of bench to springing of

brick arch;

7.--Building brick arch and part of concrete

back-filling;

8.--Finishing back-filling.

The whole work will be generally described under the headings of

Concrete, Brickwork, Water-proofing, and Electric Conduits.

_Concrete._--The number of types and the obstructions caused by the

heavy posting of the timbering made it inadvisable to use built-up

traveling forms at the Manhattan side, though they were used in the

Weehawken Rock Tunnels.

The specifications required a facing mixture of mortar to be deposited

against the forms simultaneously with the placing of the concrete. This

facing mixture was dry, about 2 in. thick, and was kept separate from

the concrete during the placing by a steel diaphragm. The diaphragm was

removed when the concrete reached the top of each successive layer, and

the facing mixture and concrete were then tamped down together. This

method was at first followed and gave good results, which was indeed a

foregone conclusion, as the Weehawken shaft had been built in this way.

However, it was found that as good results, in the way of smooth finish,

were to be obtained without the facing mixture by spading the concrete

back from the forms, so that the stone was forced back and the finer

portion of the mixture came against the forms; this method was followed

for the rest of the work. All corners were rounded off on a 1-in. radius

by mouldings tacked to the forms. The side-bench forms were used about

four times, and were carefully scraped, planed, filled at open joints,

and oiled with soap grease each time they were set up. When too rough

for face work they were used for sand-wall and other rough work.

The mixing was done by a No. 4 Ransome mixer, driven by 30-h.p. electric

motors. The mixer at Manhattan was set on an elevated platform at the

north end of the intercepting arch; that at Weehawken was placed at the

entrance to the tunnels. The sand and stone were stored in bins above

the mixers, and were led to the hoppers of the mixers through chutes.

The hoppers were divided into two sections, which gave the correct

quantities of sand and stone, respectively, for one batch. The water was

measured in a small tank alongside. A "four-bag" batch was the amount

mixed at one time, that is, it consisted of 4 bags of cement, 8¾ cu.

ft. of sand, and 17½ cu. ft. of broken stone, and was called a 1 :

2½ : 5 mixture. It measured when mixed about ¾ cu. yd.

The cement was furnished to the contractor by the Railroad Company,

which undertook all the purchasing from the manufacturer, as well as the

sampling, testing, and storing until the contractor needed it. The

Railroad Company charged the contractor $2 a barrel for this material.

The sand was required by the specifications to be coarse, sharp, and

silicious, and to contain not more than 0.5% of mica, loam, dirt, or

clay. All sand was carefully tested before being used. The stone was to

be a sound trap or limestone, passing a 1½-in. mesh and being

retained on 3/8-in. mesh. The contractor was allowed to use a coarser

stone than this, namely, one that had passed a 2-in. and was retained on

a 1½-in. mesh.

The concrete was to be machine-mixed, except in cases of local

necessity. The quantity of water used in the mixture was to be such that

the concrete would quake on being deposited, but the engineer was to use

his discretion on this point. Concrete was to be deposited in such a

manner that the aggregates would not separate. It was to be laid in

layers, not exceeding 9 in. in thickness, and thoroughly rammed. When

placing was suspended, a joint was to be formed in a manner satisfactory

to the engineer. Before depositing fresh concrete, the entire surface on

which it was to be laid was to be cleaned, washed and brushed, and

slushed over with neat cement grout. Concrete which had begun to set was

not to be used, and retempering was not to be allowed.

[Illustration: MANHATTAN TYPES FIG. 8.]

The forms were to be substantial and hold their shape until the concrete

had set. The face forms were to be of matched and dressed planking,

finished to true lines and surfaces; adequate measures were to be taken

to prevent concrete from adhering to the forms. Warped or distorted

forms were to be replaced. Plastering the face was not allowed. Rock

surfaces were to be thoroughly washed and cleaned before the concrete

was deposited.

These specifications were followed quite closely.

A typical working gang, as divided among the various operations, is

shown below:

_Superintendence._

½ Superintendent @ $250 per month

½ Assistant engineer " 150 " "

1 Assistant superintendent " 150 " "

_Surface Transport._

1 Foreman @ $2.50 per day

1 Engineer " 3.00 " "

1 Signalman " 2.00 " "

16 Laborers " 1.75 " "

3 Teams " 7.50 " "

_Laying._

1 Foreman @ $4.00 per day

8 Laborers " 2.00 " "

_Forms._

1 Foreman @ $4.50 per day

4 Carpenters " 3.25 " "

5 Helpers " 2.25 " "

_Tunnel Transport._

¼ Foreman @ $3.25 per day

¼ Engineer " 3.00 " "

¼ Signalman " 2.00 " "

4 Laborers " 1.75 " "

_Mixers._

¼ Foreman @ $3.25 per day

2 Laborers " 1.75 " "

The superintendent and assistant engineer looked after the brickwork and

other work as well as the concrete. The surface transport gang handled

all the materials on the surface, including the fetching of the cement

from the cement warehouses.

The tunnel transport gang handled all materials in the tunnel, but, when

the haul became too long, the gang was reinforced with laborers from the

laying gang. Of the laying gang, two generally did the spading, two the

spreading and tamping, and the remaining force dumped the concrete. The

general cost of this part of the work is shown in Table 13.

The figures in Table 13 include the various items built into the

concrete and some that are certificate extras in connection with the

concrete, such as drains, ironwork and iron materials, rods and bars,

expanded metal, doors, frames and fittings, etc.

_Water-proofing._--According to the specifications, the water-proofing

was to consist of seven layers of pitch and six layers of felt on the

side-walls and a ½-in. layer of mastic, composed of coal-tar and

Portland cement, to be plastered over the outside of the arches.

By the time the work was in hand, some distrust had arisen as to the

efficiency of this mastic coating, and a great deal of study was devoted

to the problem of how to apply a felt and pitch water-proofing to the

arches. The difficulty was that there was no room between the rock and

the arch or between the timber and the arch (as the case might be) in

which to work. Several ingenious schemes of putting the felt on in

layers, or in small pieces like shingles, were proposed and discussed,

and a full-sized model of the tunnel arch was even built on which to try

experiments, but it was finally decided to overcome the difficulty by

leaving out the arch water-proofing altogether, and simply building in

pipes for grouting through under pressure, in case it was found that the

arch was wet.

As to the arch built through the length excavated by cut-and-cover on

the New York side, it was resolved to water-proof that with felt and

pitch exactly as the side-walls were done, the spandrel filling between

the arches being raised in a slight ridge along the concrete line

between tunnels in order to throw the water over to the sides. The

portions of arch not water-proofed were rather wet, and grouting with a

1:1 mixture was done, but only with the effect of stopping large local

leaks and distributing a general dampness over the whole surface of the

arch.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 15 / 55 题