TABLE 8.--ANALYZED COST OF DRILLING.

+=============+===========================+===========================+

| | COST PER FOOT OF HOLE | COST PER DRILL SHIFT |

|Item of Cost.| DRILLED. | |

| +-------+-----+-----+-------+-----+------+------+-------+

| | 15 ft | 9 ft|24 ft|Average|15 ft|19 ft |24 ft |Average|

| | 4 in | 6 in| 6 in| | 4 in| 6 in | 6 in | |

|-------------+-------+-----+-----+-------+-----+------+------+-------+

|Drilling | $0.25 |$0.28|$0.31| $0.28 |$6.95| $7.75| $7.60| $7.45 |

|labor | | | | | | | | |

| | | | | | | | | |

|Sharpening | 0.02 | 0.02| 0.01| 0.016| 0.58| 0.42| 0.34| 0.43 |

| | | | | | | | | |

|Drill steel | 0.007|0.007|0.006| 0.007| 0.19| 0.20| 0.15| 0.19 |

|(5 in. per | | | | | | | | |

|drill shift) | | | | | | | | |

| | | | | | | | | |

|Drill repairs| 0.02 | 0.02| 0.02| 0.02 | 0.61| 0.59| 0.42| 0.54 |

| | | | | | | | | |

|High-pressure|[M]0.05| 0.04| 0.07| 0.07 | 1.39| 1.86| 1.67| 1.82 |

|air | | | | | | | | |

|-------------+-------+-----+-----+-------+-----+------+------+-------+

|Totals | $0.35 |$0.38|$0.41| $0.385|$9.67|$10.82|$10.18|$10.43 |

+=============+=======+=====+=====+=======+=====+======+======+=======+

[M] This is an estimated figure, ascertained by taking a proportion of

the whole charge for plant running.

_General Methods._--Whenever any considerable support was needed for the

ground, segmental timbering was used. In most cases, this was supported

by wall-plates at the springing line, and was set with an allowance for

settlement, so that it would be clear of the work when the masonry

lining was put in. As the twin-tunnel section involved the excavation of

the North and South Tunnels at the same time, the cross-section of the

upper part of the excavation consisted of two quadrants rising from the

springing line and connected at the top by a horizontal piece from 19 to

28 ft. in length. This made a rather flat arch to support by timbering.

The timber for the segmental work was 12 by 12-in. yellow pine. In light

ground the bents were spaced at 5-ft. centers, in heavy ground 2-ft.

6-in. centers.

When the soft ground in the roof was struck, posts had to be used in the

heading to support the caps. When the bench was removed, the posts were

replaced by others down to the bottom of the excavation. These long

posts were a great hindrance to all the work, and each replacement of

short posts by long ones meant a settlement of the caps; consequently,

it was decided to use in the section east of the cut-and-cover, where

all the ground was heavy, a temporary inner bent of segmental timber,

within and reinforcing the permanent bent, and resting on separate

wall-plates. This is shown by Fig. 6. These temporary bents were inside

the work, and were removed as the arch was built. However, the caps

settled considerably in some cases, so that it was not possible to do

away with posting entirely.

In heavy ground the caps were set about 1 ft. above the neat line of the

crown of the brick arch, in some cases they were set only 6 in. above,

but the settlement was often more than this, causing great trouble in

cutting out the encroaching timber when the arch had to be built.

[Illustration: DETAILS OF LONGITUDINAL SECTIONAL SHOWING METHOD OF

PLACING LAGGING IN CROWN WITH SOFT ROOF TYPICAL SECTION LOOKING EAST

FIG. 6.]

In the tunnels east of the cut-and-cover portion, wall-plate headings

were driven (shown by areas marked _A_ on Fig. 5), and, when a length of

wall-plate had been set, the full-width heading was advanced a foot or

two at a time, the timber segmental bents being set up as soon as

possible; lagging was then driven over the cap into the soft ground.

Fig. 6 shows the double set of segmental bents adopted in the 15-ft.

4-in. twin tunnels east of the cut-and-cover section.

When the soft ground came down so low as to interfere with the

excavation of the wall-plate headings, a small heading was driven into

the soft ground on the line of the ends of the caps, and lagging was

driven down from this to the wall-plate heading, as illustrated in Fig.

4.

In the 19-ft. 6-in. tunnels the wall-plate for the inner bent was

supported by a side-bench, termed the "Raker" bench. This was left in

position until the rest of the bench and the middle subgrade conduit

trench had been excavated; it was then possible to support the caps by

two rows of posts from subgrade level, take out the inner bents, and

excavate the raker bench.

The 24-ft. 6-in. twin tunnels, which are at the extreme eastern end of

this section, adjoining the open-cut work of the Terminal Station, and

under Tenth Avenue, were driven from the Terminal Station-West, and the

timbering had to be made very secure on account of the pipes and sewers

in the street above. Detailed records were kept of the amount of timber

used and the cost of labor and material expended in timbering. These

records cover the same portion of tunnel as that for which the detailed

records of drilling costs, previously referred to, were kept. These

records are shown in Tables 9 and 10. It will be noted that the timber

used in blocking, that is, filling up voids outside the main timbering,

amounted to more than two-thirds of the total timber, and that the cost

of labor in erecting the timbering exceeds the prime cost of the timber

by about one-third. The following distinction is made between permanent

and temporary timbering: The permanent timbering is that which is

concreted in when the masonry is built; the temporary consists of the

lower bents and posts, which have to be removed when the masonry is

built.

_Force Employed in Excavation._--A typical day's working force for

drilling, blasting, mucking, and timbering is shown in Table 11.

Where there was any large quantity of soft ground in the roof, the

timber gang was much larger than shown in Table 11, and was helped by

the mucking gang. The drillers did most of the mucking out of the

heading before setting up the drills.

_Excavation of Weehawken Rock Tunnels._--This subject may be dismissed

in a few words, as very few features of interest were called into play.

The rock was of good quality, being the sandstone typical of this part

of the country. Little or no timbering was needed, there were no

buildings above the tunnel to be taken care of, and large charges of

powder could be used.

TABLE 9.--SUPPLEMENTARY ANALYSIS OF TIMBERING, ROCK TUNNEL EXCAVATION

UNDER 32D STREET, EAST OF CUT-AND-COVER SECTION. ANALYZED COST OF

TIMBERING, PER FOOT RUN AND PER BENT.

+=============================+================================

| | _Ke_

| |--------+------------+----------

| |Per foot|Per bent, |Per cubic

| |run of |3 ft, 6 in.,|yard

| |tunnel |center to |excavation

| | |center |

|-----------------------------+--------+------------+----------

|PERMANENT TIMBERING. | | |

|Lumber in feet, B. M. | | |

| Upper Bent. | 274 | 685 | 7.8

| Blocking. | 294 | 735 | 8.3

| Total. | 568 | 1,420 | 16.1

|Cost, in dollars. | | |

| Lumber. | 23.75| 59.38 | 0.67

| Labor. | 37.50| 93.75 | 1.06

| Total. | 61.25| 153.13 | 1.73

| | | |

|TEMPORARY TIMBERING. | | |

|Lumber in feet, B. M. | | |

| Lower Bent. | 479 | 11.97 | 13.6

| Blocking. | 193 | 483 | 5.5

| Total. | 672 | 16.80 | 19.1

|Cost, in dollars. | | |

| Lumber. | 29.13| 72.81 | 0.82

| Erection labor. | 28.85| 72.13 | 0.82

| Removal labor. | 8.29| 20.73 | 0.23

| Total labor. | 37.14| 92.86 | 1.05

| Total. | 66.27| 165.67 | 1.87

| | | |

|GRAND TOTAL. | | |

|Lumber in feet, B. M. |1,240 | 3,100 | 35.2

|Cost, in dollars. | | |

| Lumber. | 52.88| 132.19 | 1.49

| Labor. | 74.64| 186.61 | 3.60

| Total. | 127.52| 318.80 |

|-----------------------------+--------+------------+----------

| | _Ki_

| |--------+------------+----------

| |Per foot|Per bent, |Per cubic

| |run of |3 ft, 6 in.,|yard

| |tunnel |center to |excavation

| | |center |

|-----------------------------+--------+------------+----------

|PERMANENT TIMBERING. | | |

|Lumber in feet, B. M. | | |

| Upper Bent. | 227 | 830 | 5.3

| Blocking. | 164 | 601 | 3.8

| Total. | 391 | 1,431 | 9.1

|Cost, in dollars. | | |

| Lumber. | 16.84| 61.56 | 0.39

| Labor. | 12.82| 46.88 | 0.30

| Total. | 29.66| 108.44 | 0.69

| | | |

|TEMPORARY TIMBERING. | | |

|Lumber in feet, B. M. | | |

| Lower Bent. | 186.33| 681.25 | 4.33

| Blocking. | 42.80 156.50 | 0.99

| Total. | 229.13| 837.75 | 5.32

|Cost, in dollars. | | |

| Lumber. | 9.65| 35.31 | 0.22

| Erection labor. | 10.38| 37.97 | 0.24

| Removal labor. | 9.74| 34.09 | 0.23

| Total labor. | 20.12| 72.06 | 0.47

| Total. | 29.77| 107.37 | 0.69

| | | |

|GRAND TOTAL. | | |

|Lumber in feet, B. M. | 6.20| 22.69 | 14.4

|Cost, in dollars. | | |

| Lumber. | 26.49| 96.87 | 0.61

| Labor. | 32.94| 118.94 | 0.77

| Total. | 59.43| 215.81 | 1.38

|-----------------------------+--------+-----------------------

| | _Ko_

| |--------+------------+----------

| |Per foot|Per bent, |Per cubic

| |run of |3 ft, 6 in.,|yard

| |tunnel |center to |excavation

| | |center |

|-----------------------------+--------+------------+----------

|PERMANENT TIMBERING. | | |

|Lumber in feet, B. M. | | |

| Upper Bent. | 261 | 962 | 4.1

| Blocking. | 408 | 1,508 | 6.5

| Total. | 669 | 24.70 | 10.5

|Cost, in dollars. | | |

| Lumber. | 28.00| 103.38 | 0.44

| Labor. | 29.79| 110.00 | 0.47

| Total. | 57.79| 213.38 | 0.91

| | | |

|TEMPORARY TIMBERING. | | |

|Lumber in feet, B. M. | | |

| Lower Bent. | 350 | 1,291 | 5.5

| Blocking. | 61 | 227 | 1.0

| Total. | 411 | 1,518 | 6.5

|Cost, in dollars. | | |

| Lumber. | 18.45| 68.16 | 0.29

| Erection labor. | 20.83| 76.92 | 0.33

| Removal labor. | 12.16| 44.59 | 0.19

| Total labor. | 32.99| 121.51 | 0.52

| Total. | 51.44| 189.67 | 0.81

| | | |

|GRAND TOTAL. | | |

|Lumber in feet, B. M. |1,080 | 3,988 | 17.1

|Cost, in dollars. | | |

| Lumber. | 46.45| 171.54 | 0.73

| Labor. | 62.78| 231.50 | 0.99

| Total. | 109.23| 403.04 | 1.72

+=============================+========+============+=========

TABLE 10.--TIMBERING:--DETAILED COST OF TIMBER, LABOR, AND

SUPERINTENDENCE. ROCK TUNNEL EXCAVATION UNDER 32D STREET, EAST OF

CUT-AND-COVER SECTION.

+====+=======+======================================+====================+

| | | | EXCAVATION | |

| | | TIMBER USED, IN | IN CUBIC | COST OF |

| | | FEET, B. M. | YARDS | TIMBER |

| | |------------------------+-------------+--------------------+

| | | Main |Blocking| Total | | Paid | | | |

| |Date |timber.|timber. |timber.|Actual| for. | Main |Block.|Total.|

| |-------+-------+--------+-------+------+------+------+------+------+

| |1907 | _a_ | _b_ | _c_ | _d_ | _e_ | _f_ | _g_ | _h_ |

| |-------+-------+--------+-------+------+------+------+------+------+

|_Ke_|May | 18,016| 15,234 | 33,250| 1,736| 1,664| $810| $565|$1,375|

| |June | 14,048| 11,528 | 25,576| 809| 698| 680| 457| 1,087|

| |July | 20,092| 7,339 | 27,431| 1,022| 960| 900| 300| 1,200|

| |August | 6,485| 2,632 | 9,117| 743| 716| 290| 110| 400|

| |Sept. | 1,632| 2,224 | 3,856| 238| 238| 73| 94| 167|

| |Removal| | | | | | | | |

| |-------+-------+--------+-------+------+------+------+------+------+

| |Total | 60,273| 38,957 | 99,230| 4,548| 4,276|$2,703|$1,526|$4,229|

|----+-------+-------+--------+-------+------+------+------+------+------+

|_Ki_|May | | 3,537 | 3,537| 614| 527| | $150| $150|

| |June | 300| | 300| 357| 259| $14| | 14|

| |July | 7,776| 5,811 | 13,587| 530| 404| 350| 233| 583|

| |August | 19,712| 5,702 | 25,414| 925| 890| 887| 220| 1,107|

| |Sept. | 20,556| 9,218 | 29,774| 1,585| 1,501| 925| 325| 1,250|

| |Removal| | | | 1,669| 1,407| | | |

| |-------+-------+--------+-------+------+------+------+------+------+

| |Total | 48,344| 24,268 | 72,612| 5,680| 4,988|$2,176| $928|$3,104|

|----+-------+-------+--------+-------+------+------+------+------+------+

|_Ko_|May | 4,332| 8,788 | 13,120| 250| 188| $175| $366| $561|

| |June | 7,132| 10,017 | 17,149| 496| 347| 324| 396| 720|

| |July | 3,070| 200 | 3,270| 626| 606| 134| 10| 144|

| |August | 10,704| 2,102 | 12,806| 718| 709| 481| 80| 561|

| |Sept. | 2,400| 245 | 2,645| 396| 324| 108| 8| 116|

| |Removal| | | | 209| 211| | | |

|----|-------+-------+--------+-------+------+------+------+------+------+

| |Total | 27,638| 21,352 |48,990 | 2,695| 2,385|$1,242| $860|$2,102|

|----|-------+-------+--------+-------+------+------+------+------+------+

| |Grand |136,255| 84,577 |220,832|12,923|11,649|$6,121|$3,314|$9,435|

| |total | | | | | | | | |

+====+=======+=======+========+=======+======+======+======+======+======+

+====+=======+=======+=======+=======+=======+======+=======+=====+=====|

| | | | | COST PER | COST PER |

| | | | | CUBIC YARD | CUBIC YARD |

| | |COST OF| TOTAL | (ACTUAL). | (PAID FOR). |

| | | Labor | Cost. |-------+-------+------+-------+-----+-----+

| |DATE | | |Timber.|Labor. |Total.|Timber.|Labor|Total|

| |-------+-------+-------+-------+-------+------+-------+-----+-----+

| | | | | _h_ | _i_ | _j_ | _h_ | _i_ | _j_ |

| | | | | --- | --- | --- | --- | --- | --- |

| |1907 | _i_ | _j_ | _d_ | _d_ | _d_ | _e_ | _e_ | _e_ |

|----+-------+-------+-------+-------+-------+------+-------+-----+-----+

|_Ke_|May | $1,792| $3,167| $0.79 | $1.03 | $1.82| $0.82 |$1.07|$1.90|

| |June | 1,576| 2,663| 1.34 | 1.95 | 3.29| 1.55 | 2.25| 3.81|

| |July | 1,580| 2,780| 1.16 | 1.55 | 2.72| 1.25 | 1.64| 2.89|

| |August | 300| 700| 0.53 | 0.40 | 0.94| 0.57 | 0.41| 0.98|

| |Sept. | 60| 227| 0.70 | 0.25 | 0.95| 0.70 | 0.25| 0.95|

| |Removal| 663| 663| | | | | | |

| |-------+-------+-------+-------+-------+------+-------+-----+-----+

| |Total | $5,971|$10,200| $0.91 | $1.51 | $2.22| $1.00 |$1.40|$2.40|

|----+-------+-------+-------+-------+-------+------+-------+-----+-----+

|_Ki_|May | $100| $250| $0.24 | $0.16 | $0.40| $0.28 |$0.19|$0.47|

| |June | 44| 58| 0.04 | 0.12 | 0.16| 0.05 | 0.17| 0.22|

| |July | 525| 7,108| 1.10 | 0.99 | 2.09| 1.44 | 1.30| 2.74|

| |August | 1,018| 2,125| 1.20 | 1.10 | 2.30| 1.24 | 1.14| 2.38|

| |Sept. | 1,028| 2,278| 0.79 | 0.65 | 1.44| 0.83 | 0.68| 1.51|

| |Removal| 1,139| 1,139| | 0.68 | 0.68| | 0.81| 0.81|

| |-------+-------+-------+-------+-------+------+-------+-----+-----+

| |Total | $3,854| $6,958| $0.55 | $0.68 | $1.23| $0.63 |$0.77|$1.40|

|----+-------+-------+-------+-------+-------+------+-------+-----+-----+

|_Ko_|May | $303| $864| $2.24 | $1.21 | $3.45| $3.00 |$1.61|$4.61|

| |June | 562| 1,282| 1.45 | 1.18 | 2.58| 2.07 | 1.61| 3.68|

| |July | 156| 300| 0.23 | 0.25 | 0.48| 0.23 | 0.26| 0.49|

| |August | 727| 1,288| 0.78 | 1.01 | 1.79| 0.80 | 1.02| 1.82|

| |Sept. | 400| 516| 0.29 | 1.01 | 1.30| 0.36 | 1.23| 1.59|

| |Removal| 535| 535| | 2.56 | 2.56| | 2.54| 2.54|

| |-------+-------+-------+-------+-------+------+-------+-----+-----+

| |Total | $2,683| $4,785| $0.78 | $1.00 | $1.78| $0.88 |$1.12|$2.00|

|----+-------+-------+-------+-------+-------+------+-------+-----+-----+

| |Grand |$12,508|$21,943| $0.73 | $0.97 | $1.70| $0.81 |$1.07|$1.88|

| |total | | | | | | | | |

+====+=======+=======+=======+=======+=======+======+=======+=====+=====+

+====+===========+======================+

| | | COST, PER 1,000 |

| | | FT., B. M., OF |

| | | TOTAL TIMBER. |

| | |-------+------+-------|

| | | Total | | |

| | Date |timber.|Labor.|Total. |

| |-----------+-------+------+-------|

| | | _h_ | _i_ | _j_ |

| | | --- | --- | --- |

| | 1907 | _c_ | _c_ | _c_ |

|----+-----------+-------+------+-------|

|_Ke_|May |$41.35 |$53.89| $95.24|

| |June | 42.50 | 61.62| 104.12|

| |July | 43.74 | 57.60| 101.34|

| |August | 43.87 | 32.90| 76.77|

| |Sept. | 43.31 | 15.56| 58.87|

| |Removal | | | |

| |-----------+-------+------+-------|

| |Total |$42.62 |$60.19|$102.81|

|----+-----------+-------+------+-------|

|_Ki_|May |$42.41 |$28.27| $70.68|

| |June | 46.66 |146.33| 193.33|

| |July | 42.91 | 38.64| 81.54|

| |August | 43.56 | 40.06| 83.61|

| |Sept. | 41.98 | 34.53| 76.51|

| |Removal | | | |

| |-----------+-------+------+-------|

| |Total |$42.75 |$53.09| $95.84|

|----+-----------+-------+------+-------|

|_Ko_|May |$42.76 |$23.10| $65.86|

| |June | 41.98 | 32.77| 74.75|

| |July | 44.04 | 47.70| 91.74|

| |August | 43.80 | 56.77| 100.57|

| |Sept. | 43.85 |151.23| 195.08|

| |Removal | | | |

| |-----------+-------+------+-------|

| |Total |$42.91 |$54.75| $97.65|

|----+-----------+-------+------+-------|

| |Grand total|$42.73 |$56.65| $99.38|

+====+===========+=======+======+=======+

Work was begun on September 1st, 1904, immediately on the completion of

the work on the shaft. The North and South Tunnels in this case are

completely independent, as will be seen from Plate XXXIV. The procedure

adopted was to drive a top heading on the center line of each tunnel and

to break down the bench from this. The drilling was at first supplied

with steam power from a temporary plant, as the contractor was at that

time installing his permanent plant, which was finished at the end of

November, 1904. At this time the rate of advance averaged 3½ lin. ft.

of full section per day of 24 hours. By the end of January the Weehawken

rock tunnels were completely excavated, and by the middle of April,

1905, the excavation for the shield chambers was finished; the erection

of the shields was started at the end of that month.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 14 / 55 题