SHAFTS.

It is not intended to give much length to the description of the Shafts

or the Land Tunnels, as more interest will probably center in the River

Tunnels.

The shafts did not form part of the regular tunnel contract, but were

built under contract by the United Engineering and Contracting Company

while the contract plans for the tunnel were being prepared. In this

way, when the tunnel contracts were let, the contractor found the shafts

ready, and he could get at his work at once.

Two shafts were provided, one on the New York side and one on the New

Jersey side. Their exact situation is shown on Plate XXVIII. They were

placed as near as possible to the point at which the disappearance of

the rock from the tunnels made it necessary to start the shield-driven

portion of the work.

The details of the shafts will now be described briefly.

_The Manhattan Shaft._--The Manhattan Shaft is located about 100 ft.

north of the tunnel center; there was nothing noticeable about its

construction. General figures relating to both shafts are given in Table

1.

_The Weehawken Shaft._--The Weehawken Shaft is shown in Fig. 1. This, as

will be seen from Table 1, was a comparatively large piece of work. The

shaft is over the tunnels, and includes both of them. In the original

design the wall of the shaft was intended to follow in plan the property

line shown in Fig. 2, and merely to extend down to the surface of the

rock, which, as disclosed by the preliminary borings, was here about 15

ft. below the surface. However, as the excavation proceeded, it was

found that this plan would not do, as the depth to the rock surface

varied greatly, and was often much lower than expected; the rock itself,

moreover, was very treacherous, the cause being that the line of

junction between the triassic sandstone, which is here the country rock,

and the intrusive trap of the Bergen Hill ridge, occurs about one-third

of the length of the shaft from its western end, causing more or less

disintegration of both kinds of rock. Therefore it was decided to line

the shaft with concrete throughout its entire depth, the shape being

changed to a rectangular plan, as shown in the drawings. At the same

time that the shaft was excavated, a length of 40 ft. of tunnels at each

end of it was taken out, also on account of the treacherous nature of

the ground, thus avoiding risk of injury to the shaft when the tunnel

contractors commenced work. There was much trouble with floods during

the fall of 1903, and numerous heavy falls of ground occurred, in spite

of extreme care and much heavy timbering. The greatest care was also

taken in placing the concrete lining, and the framing to support the

forms was carefully designed and of heavy construction; the forms were

of first-class workmanship, and great care was taken to keep them true

to line. A smooth surface was given to the concrete by placing a 3-in.

layer of mortar at the front of the walls and tamping this dry facing

mixture well down with the rest of the concrete. The east and west walls

act as retaining walls, while those on the north and south are facing

walls, and are tied to the rock with steel rods embedded and grouted

into the rock and into the concrete. Ample drainage for water at the

back of the wall was provided by upright, open-joint, vitrified drains

at frequent intervals, with dry-laid stone drains leading to them from

all wet spots in the ground. A general view of the finished work is

shown in Fig. 1, Plate XXIX, and Table 1 gives the most important dates

and figures relating to this shaft.

TABLE 1.--PARTICULARS OF SHAFTS ON THE NORTH RIVER TUNNELS OF THE

PENNSYLVANIA RAILROAD TUNNELS INTO NEW YORK CITY.

+===========+=====+======+======+==========+========+===========+========+

|Location. |Depth| Width|Length|Excavation|Concrete| Date| Date|

| | in| in| in|(including|in cubic|commenced.|finished.|

| |feet.| feet.| feet.| drifts),| yards.| | |

| | | | | in cubic| | | |

| | | | | yards. | | | |

+-----------+-----+------+------+----------+--------+----------+---------+

|Manhattan: | 55| 22| 32| 2,010| 209|June 10th,| December|

|11th Avenue| | | | | | 1903.| 11th,|

|and 32d | | | | | | | 1903.|

|Street. | | | | | | | |

| | | | | | | | |

|Weehawken: | 76| At| At| 55,315| 9,810|June 11th,|September|

|Baldwin | |bottom|bottom| | | 1903.|1st, |

|Avenue. | |56, at|115.75| | | |1904. |

| | | top|at top| | | | |

| | | 100.| 154.| | | | |

|===========+=====+======+======+==========+========+==========+=========+

+==========+====================+=============+============+===========+

|Location. |Ground met: |Lined with: | Cost to | Cost per |

| | | | Railroad |cubic foot.|

| | | | Company. | |

+----------+--------------------+-------------+------------+-----------+

|Manhattan:|Top 13 ft. filled; |Concrete | $12,943.75 | $0.335 |

|11th |red mica schist and |reinforced | | |

|Avenue and|granite. |with steel | | |

|32d | |beams down to| | |

|Street. | |rock. | | |

| | | | | |

|Weehawken:|Top 6 ft. filled, 30|Concrete with| 166,162,98 | 0.337 |

|Baldwin |ft. sand and |steel | | |

|Avenue. |hardpan, decomposed |tie-rods in | | |

| |rock (trap and |rock. | | |

| |sandstone) below. | | | |

+==========+====================+=============+============+===========+

[Illustration: FINAL DESIGN OF WEEHAWKEN SHAFT PLAN LONGITUDINAL SECTION

TRANSVERSE SECTION FIG. 1.]

After the tunnel work was finished, both shafts were provided with

stairs leading to the surface, a protective head-house was placed over

the New York Shaft, and a reinforced concrete fence, 8 ft. high, was

built around the Weehawken Shaft on the Company's property line, that

is, following the outline of the shaft as originally designed.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 9 / 55 题