Sheridan Paving--1918

Early in 1918, Yamhill County requested that the concrete pavement laid

in 1917 be continued to a total length of four miles, and offered to pay

for all grading necessary in connection therewith. This request was

granted by the Highway Commission and in the early spring, construction

was started on the additional 2.2 miles.

The type of pavement laid on this section was the same as that laid in

1917, except that crushed rock aggregate was used instead of gravel, and

the mix was reduced to 1:2:31/2.

[Illustration: STATE OWNED PAVING PLANT IN OPERATION NEAR SHERIDAN IN

YAMHILL COUNTY. ON THE YAMHILL NESTUCCA HIGHWAY]

The coarse aggregate consisted of crushed stone ranging from 1/4 inch to

21/2 inches. For the fine aggregate, both Columbia River and Willamette

River sand was used. The stone was crushed from a quarry operated by the

State on Deer Creek which was near the center of the job and consisted

of an altered basalt of rather coarse texture. The quality of this

stone is not equal to the true basalt; but tests made by the Oregon

Agricultural College showed that it was of good quality. The average

haul on this material was .6 of a mile.

Crushing was begun early in March and 1200 cubic yards of material

stored in a stock pile which was rehandled later by means of an

automatic loader purchased by the State Highway Department for this

class of work. The output of the crusher was insufficient to keep the

mixer running and by means of this stock pile it was possible to keep

the material coming on to the road steadily and finish the job in a

minimum length of time and with the least inconvenience to traffic.

In this connection the experience on this job shows the advisability of

using a stock pile of material to draw from in case of emergencies. When

this is done the work is allowed to go ahead steadily, although a

breakdown at the crusher may occur. The saving made by a steady run more

than offsets the cost of rehandling the material, which is done very

reasonably by the use of machinery.

The sand was shipped to Ballston and Sheridan by railroad, approximately

equal amounts being shipped to both places and was so divided as to get

a minimum length of haul on this material. The average haul was 3.5

miles. At Ballston the sand was unloaded from the cars into bunkers,

which dumped directly into trucks, while at Sheridan no bunkers were

available and the material was unloaded on the ground and rehandled by

means of an automatic loader. No delay was caused by car shortage as we

used our stock pile at Sheridan in emergencies. All the material was

hauled and handled by means of trucks, two of which belonged to the

State Highway Department, others working on a yardage basis.

The pavement, after being struck off, was finished by the roller and

belt method; being rolled from two to four times, according to the

condition of the concrete and later belted with eight and ten inch

belts. The eight inch belt being used first. By using this method of

finishing, we were able to eliminate the use of skilled labor, which

showed a material saving in the finishing item, and at the same time

secured a very satisfactory surface.

As soon as sufficiently hardened, the pavement was covered with earth

from the roadside and kept moist for at least one week while curing. The

earth covering was later removed by means of an ordinary road grader,

when ready to be opened for traffic, the elastite joints being trimmed

at the same operation.

A short stretch of pavement was left out at Deer Creek to allow a fill

to settle during the winter rains. In conformity with our general

practice, sufficient crushed rock was left on the job to complete this

stretch and make repairs.

Elastite joints were placed every thirty feet and extended the entire

width and depth of the pavement. Continuous forms were used on a portion

of this pavement and were found to be much superior to the ordinary

type, and the Department has adopted the continuous form for future

work. These forms are made by using two pieces of form lumber 11/2 inches

by 51/2 inches nailed together. The joints are lapped one-half the length

of the stick. The finished form is 3x51/2 inches and is easily placed on

either tangents or sharp curves.

The concrete was mixed with a sixteen cubic foot Koehring Mixer equipped

with bucket and boom. The plant is owned by the Department.

The grading was paid for by Yamhill County and the crusher, roller,

grader, and scarifier were also furnished by them free of charge. Earth

shoulders were built along the pavement by means of road grader.

Mr. J. M. Baker was Superintendent of Construction on this work.

COST STATEMENT--2.2 MILES, 16-FOOT CONCRETE PAVEMENT, EAST OF

SHERIDAN--BUILT IN 1918

Third biennial report of the Oregon State Highway Commission · 第 289 / 292 题