2498 cu. yds. Common Excavation }
652 cu. yds. Intermediate Excavation } $ 4,442.85 $ .906
1750 cu. yds. Solid Rock Excavation }
182 lin. ft. 12-inch Culvert Pipe 283.90 1.56
118 lin. ft. 18-inch Culvert Pipe 276.00 2.34
44 lin. ft. 24-inch Culvert Pipe 134.20 3.05
290 lin. ft. 6-inch Porous Drain Tile 52.25 .18
25 cu. yds. Class "C" Concrete 462.50 18.50
17,150 sq. yds. Concrete Pavement 31,198.87 1.82
5050 lin. ft. Expansion Joints 234.12 .046
-----------
Total Construction Cost $ 37,084.69
Engineering 1,131.35
-----------
Grand Total Cost $ 38,216.04
Paid by State $ 28,216.04
Paid by County 10,000.00
-----------
Total $ 38,216.04