Ashland Hill Paving

Bids were called for on August 6, 1918, for the paving of the Ashland

Hill Section, but as no satisfactory bids were received the work was

undertaken by the Highway Department with State forces. This section of

paving is 4,200 feet in length, and the type of pavement laid is a

16-foot concrete, 51/2 inches thick at the sides and 61/2 inches thick at

the center. The mixture was a 1:2:31/2, and a ratio of 5.6 gallons of

water per sack of cement was used.

The average haul on material was 1.2 miles and hauling was done by means

of trucks. The cement was shipped to the job prior to the beginning of

construction and stored at convenient locations near the work.

A sixteen cubic foot Koehring mixer equipped with boom and bucket was

used for mixing the aggregate. The pavement, after being struck off, was

finished by the roller and belt method. The pavement first being rolled

from two to four times depending on the condition of the concrete and

later belted with eight and ten inch belts. The eight inch belt being

used first. A very satisfactory surface was obtained in this manner.

[Illustration: CONCRETE PAVEMENT ON ASHLAND HILL IN JACKSON COUNTY, ON

THE PACIFIC HIGHWAY NORTH OF ASHLAND. GRADED AND PAVED IN 1918]

Continuous forms were used on this work and 1/4x4 inch elastite joints

were placed at 30 foot intervals, leaving approximately two inches of

concrete above the elastite and giving the pavement the appearance of

monolithic construction. It was found that a better riding pavement

could be produced in this way as the inequalities at joints were

eliminated and we believe that the use of this pavement will justify the

adoption of this type on future work.

Gravel and crushed rock shoulders two feet wide were built on this

section and the pavement was not covered while curing as the weather was

cool and damp. However, the pavement was kept wet by sprinkling when

necessary.

The crusher and roller on this work were furnished by Jackson County

free of charge.

Mr. J. M. Baker was superintendent of construction on this work.