COST STATEMENT--WESTPORT-CLATSKANIE MACADAM

===========================+==========+========+==============+========

Item | Unit | Quan- | Total cost | Unit

| | tity | | cost

---------------------------+----------+--------+--------------+--------

By Warren Construction Co. | | | |

on cost plus contract-- | | | |

Clearing and grubbing | Acres | 1/2 | $ 49.87 | $ 99.74

Excavation | Cu. yd. | 6,200 | 6,820.70 | 1.10

6-ft. by 12-in. drain pipe | Foot | 1,085 | 2,752.38 | 2.80

Water-bound macadam |[9]Cu. yd.| 7,742 | 27,698.87 | 3.59

Engineering | | | 497.03 |

By State Forces-- | | | |

Excavation | Cu. yd. | 8,299 | 5,594.75 | .67

6-ft. by 12-in. drain pipe | Foot | 298 | 21.05 | .07

(laying) | | | |

Water-bound macadam | Cu. yd. | 17,977 | 68,168.50 | 3.79

Engineering | | | 25.09 |

| | +--------------+

Total cost | | | $ 111,628.24 |

---------------------------+----------+--------+--------------+--------

[9] 4,972 cu. yds. purchased at cost of $5,966.40, all other rock

crushed on this job.