Item | Unit | Quan- | Total cost | Unit
| | tity | | cost
---------------------------+----------+--------+--------------+--------
By Warren Construction Co. | | | |
on cost plus contract-- | | | |
Clearing and grubbing | Acres | 1/2 | $ 49.87 | $ 99.74
Excavation | Cu. yd. | 6,200 | 6,820.70 | 1.10
6-ft. by 12-in. drain pipe | Foot | 1,085 | 2,752.38 | 2.80
Water-bound macadam |[9]Cu. yd.| 7,742 | 27,698.87 | 3.59
Engineering | | | 497.03 |
By State Forces-- | | | |
Excavation | Cu. yd. | 8,299 | 5,594.75 | .67
6-ft. by 12-in. drain pipe | Foot | 298 | 21.05 | .07
(laying) | | | |
Water-bound macadam | Cu. yd. | 17,977 | 68,168.50 | 3.79
Engineering | | | 25.09 |
| | +--------------+
Total cost | | | $ 111,628.24 |
---------------------------+----------+--------+--------------+--------
[9] 4,972 cu. yds. purchased at cost of $5,966.40, all other rock
crushed on this job.