COST STATEMENT--SVENSEN-WESTPORT MACADAM

===========================+==========+=========+============+=======

Item | Unit | Quan- | Cost | Unit

| | tity | | Cost

---------------------------+----------+---------+------------+-------

By Warren Construction Co.,| | | |

on cost plus contract-- | | | |

Clearing and grubbing | Acres | 1 |$ 112.18 |$112.18

Excavation | Cu. Yd. | 9,069 | 6,468.95 | .71

6-inch by 12-inch pipe | Foot | 1,519 | 4,472.69 | 2.90

Waterbound macadam |[8]Cu. Yd.| 13,409 | 53,010.60 | 3.95

Engineering | ... | ... | 971.84 | ...

By State Forces-- | | | |

Excavation | Cu. Yd. | 11,512 | 7,540.71 | .64

6-inch by 12-inch pipe, | Foot | 1,760 | 328.80 | .19

laying only | | | |

Waterbound macadam | Cu. Yd. | 34,722 | 134,022.23 | 3.86

Engineering | | | 1,651.69 | ...

| | +------------+

Total | ... | ... |$208,579.69 | ...

---------------------------+----------+---------+------------+-------

[8] Including 1,839 cubic yards of gravel purchased at a cost of

$1,839.00 and 5,278 cubic yards crushed rock purchased at a cost of

$6,333.60. All other rock was crushed and cost of crushing is included

in the cost of the macadam.

[Illustration: COVERED WOOD DRAWBRIDGE ON THE COLUMBIA RIVER HIGHWAY IN

CLATSOP COUNTY, OVER THE JOHN DAY RIVER EAST OF ASTORIA. BUILT IN 1918.

LIFT SPAN--40 FEET]