PART II

_Main Thoroughfares_

[Sidenote:

Width of Thoroughfares]

In considering the economical widths for the main thoroughfares

of a city, so many complex factors are involved that no exact and

indisputable conclusions can be reached; but there are certain facts

and principles that ought to remove such decisions from the realm

of purely arbitrary whim and custom by which they are now generally

settled. Practically every normal main thoroughfare, even of the most

compact type, must provide for car tracks in the middle. On straight

runs, according to the present practice and with the new cars in

Pittsburgh, the width occupied from the outside of one car to the

outside of the other is 17 feet 8½ inches. At that, the cars are

narrower than the modern standard in some other American cities, and

the clearance between the cars is reduced to less than a reasonable

requirement for safety. On curving roads, such as the Pittsburgh

topography often imposes, the space occupied is greater. Without

allowing any clearance on the outside, a space not less than 18 feet,

and preferably more, should be allowed for the actual cars on straight

runs.

In Pittsburgh, the gauge of the car tracks was originally made to

conform to the prevailing local gauge of other vehicles, on the

mistaken theory that it was desirable to have the smooth tracks used

by wagons; and this has resulted in the almost invariable conformity

of the wagon gauge to that of the tracks, regardless of the size or

character of the vehicle. With the added fact that Pittsburgh pavements

are prevailingly bad, and that the form of rail is such that it is

very difficult for a wagon to turn out when it has once got into the

track, the teamsters in Pittsburgh are more inveterate in the habit of

driving in the car tracks, and less ready to turn aside for cars or

other vehicles, than in most cities. The severe and constantly repeated

strain of the horses, which is required to wrench heavily-loaded wagons

free from the tracks, is, in the aggregate, a serious economic loss;

and the delays not only to the street cars but to all forms of wheeled

traffic, caused by the conditions described, are incalculably great.

But even good pavements and the use of a grooved rail would not cure

the trouble in Pittsburgh streets as now laid out, because, almost

universally, there is not sufficient room for a vehicle to pass between

the cars and another vehicle standing or slowly moving next the curb.

In every street, vehicles must be free to stop for loading and

unloading, and on a busy thoroughfare the space next the curb is so

much used in this manner as to become merely a series of sidings into

which slow-moving vehicles can turn from time to time in order to clear

the main passageway. The result of the conditions above described is

that practically the whole wheeled traffic in Pittsburgh streets is

inevitably concentrated on the eighteen-foot width where the cars run.

The extent to which this reduces the average speed of travel and the

total capacity of the thoroughfare has been strikingly illustrated

for Pittsburghers by the contrast of the former sluggish congestion

of traffic on Smithfield Street with the sparse appearance and rapid

movement of the same traffic since the "one-way" regulations have made

it possible to get one free line in each direction for moving vehicles

separate from the cars. The same striking increase in capacity is to be

secured, without the grave inconveniences and drawbacks of the "one-way

street" regulations, where the space between the cars and the curb can

be made wide enough for two lines of vehicles, instead of just enough

for one or for one and a half, as is usual in Pittsburgh.

It is very difficult to determine just what is the most economical

allowance of width. There is much variation in the widths of the

vehicles themselves, and the necessary amount of clearance varies with

the average skill of the drivers and with the effectiveness of the

police control. The width of the line is plainly determined by the

widest vehicles in it rather than by the narrowest. In Pittsburgh the

customary width of the heavier and wider wagons is now controlled by

the practical necessity of fitting the wheels to the railway gauge of

5 feet 2½ inches, and the widths are considerably less than prevail

in New York, Boston, and other reasonably well-paved cities where the

wagons are not fitted to the car tracks. About 7 feet over all is now

the ordinary maximum in Pittsburgh, a few auto trucks and delivery vans

exceeding that figure slightly, and an occasional three-horse team

occupying over 8 feet. In New York and Boston, wagons measuring from 7

to 8 feet from hub to hub are common, and they sometimes considerably

exceed 8 feet.

Just as in the case of steam and electric railway equipment, the

tendency is constantly in the direction of heavier, longer, wider

vehicles, for the sake of the operating economy due to large units;

and, with the steady increase in the use of motor vehicles for business

purposes, this tendency is likely to be greatly accelerated. There

is every reason to expect that motor trucks will gradually increase

in size until a limit is fixed by the public authorities in order to

protect the pavements, and for the sake of standardizing the lines

of travel in relation to the street widths. But, in the interests of

economy of operation, the limit should be as high as practicable,

probably not less than 8 feet.

If 8 feet be allowed for each vehicle, plus only a foot of clearance,

the cars and one row of vehicles on each side, between them and the

vehicles standing at the curb, would require 54 feet between curbs.

A wagon _backed_ up to the curb on a busy street will seriously

discommode travel at that, and the clearance allowed is very small. A

width of 54 to 60 feet between curbs is, therefore, highly desirable in

the main thoroughfares.

As a matter of fact, with the widths of vehicles which now prevail

in Pittsburgh, if standing and slow-moving vehicles are compelled to

keep in contact with the curb, it is possible to keep open a line of

travel on each side of the car tracks, with only occasional blockades,

where the width between curbs is 50 feet, or, at a pinch, even 48 or

47 feet. That is to say, the difference in traffic capacity between a

thoroughfare 50 feet from curb to curb and one 45 feet is enormous;

while the difference between 45 feet and 40 feet is very slight.

Since a main thoroughfare is apt in time to become a retail trading

street, wide sidewalk space is important. It is a common rule to make

the distance of the curb from the property line one-third the width of

the roadway.

A total width of 90 feet, with a 54-foot roadway and 18-foot sidewalks,

is a satisfactory minimum for meeting the practical requirements of an

ordinary main traffic street; a width of 100 feet is preferable, and 80

feet may be regarded as a rather niggardly irreducible minimum.

In this connection it is interesting to note the standard widths

adopted in European cities. The standard in London is 48 feet[5]

between curbs and 80 feet between buildings for secondary avenues, and

100 feet over all for principal arteries; and 140 feet over all is

proposed for two great main arteries, the cutting of which, through

the midst of the city, is being considered. In German cities of the

second size, such as Leipzig, Frankfort and Hanover, the standards are

as follows: for strictly local streets, 33 to 47 feet; for secondary

thoroughfares, 50 to 80 feet, and for main thoroughfares, 85 to 118

feet. A Prussian law, in force since 1875, and apparently drawn up to

meet the requirements of Berlin with its heavier traffic, requires

the following dimensions for the laying out of new streets and for

the alteration of old ones: local streets, 40 to 65 feet; secondary

thoroughfares, 65 to 95 feet; main thoroughfares, over 95 feet.[6]

[Sidenote:

Special Types of Thoroughfares]

[Illustration: Park treatment of hillside street junction at Stuttgart]

The above considerations apply only to the ordinary main thoroughfares

of normal character. In most of the great cities of the world, there

has been a considerable development of special thoroughfares of much

greater width, including, for example, locations for transportation

lines (surface or elevated), on separate rights of way decorated with

trees; and including tree-shaded promenades and garden strips. These

have usually been laid out in suburban sections before they were much

built up; or, if within the built-up districts, on the sites of old

fortifications, canals, or other abandoned engineering works. The

latter opportunities are lacking at Pittsburgh, except in connection

with the river banks. In the suburban localities of Pittsburgh, so

much of the available building land is topographically divided into

narrow strips that it would be cut to pieces in an exceptionally

uneconomical manner by any boulevards, of the type usual in flatter

cities, where a substantially uniform width of 150, or 200, or 300

feet is not infrequently carried through for considerable distances.

As a general rule, any width to be secured for esthetic purposes in

connection with Pittsburgh suburban thoroughfares, over and above that

needed for handling the expectable future street traffic, must not be

in the form of a general and continuous widening. But occasional pieces

here and there may be taken for park purposes, as, for instance, a

steep sidehill adjacent to the line and unavailable or difficult for

building. Or a narrow ridge, on which the thoroughfare runs, may have

at some point so little available building land fronting upon it that

the whole can reasonably be parked for a short distance, thus keeping

open the distant views.

[Illustration: Public resting place and outlook spot on a one-sided

hillside street in Heidelberg]

[Illustration: Section showing one type of hillside street]

There are two special forms of street, developed here and there in

hilly cities all over the world, of which Pittsburgh needs to take

account in its suburban development. In many instances, and for long

distances, existing suburban thoroughfares that must be enlarged and

improved, and others that must be laid out, are compelled to run along

the face of hills so steep that a street of level cross section,

even though limited to 80 feet, would leave the land on one or both

sides so far above or below the grade as to destroy its value for

building purposes. In such cases it is often practicable to make use of

one-sided streets or two-level streets. The former are designed to give

accessible frontage on one side only, usually the uphill side. The

property on the opposite side is reached by the next street, which is

laid out correspondingly nearer in order not to make the lots too deep.

The width of such a one-sided street may be curtailed without reducing

its thoroughfare capacity because it is freed from local business

all along one side. Bluff Street, though not a thoroughfare, is an

excellent Pittsburgh example of the one-sided street, and illustrates

the great attractiveness which such streets often possess. In a

two-level street a longitudinal bank, or retaining wall, is introduced

in the middle so as to adapt it to the topography and bring each

half of it nearer to the natural surface where the abutting property

fronts upon it. Such a street must normally be wider than a single

thoroughfare of the same capacity, the saving in construction and in

the development of abutting land more than counterbalancing the cost of

extra width.

[Illustration: Section of a two-level street at Zurich, Switzerland.]

Widths for outlying thoroughfares in a district like Pittsburgh,

therefore, cannot be determined by any general rule. Each must be laid

out as a problem by itself, the principal objects in each problem being

to select a tolerably direct line on reasonable gradient, and so to

fix the side lines of the location that it shall be possible to meet

the immediate needs by constructing an economical suburban road, where

it does not already exist, and ultimately to convert it into an ample

urban thoroughfare with the minimum of cost and inconvenience.

[Sidenote:

Widening Old Streets]

Whatever radical changes may be made to improve the present or

safeguard the future condition of the thoroughfare system in regions

that are now rural, there remains a huge problem within the district

where the street system has already crystallized into substantially its

final form. Here increased capacity can, for the most part, be secured

only by local improvements and widenings of existing thoroughfares.

Fortunately, the building up of the street frontage with solid blocks

of stores, apartments, and business structures, has at most points

followed rather slowly after the earlier wave of detached dwelling

houses, and a large proportion of the streets which are destined to be

the main arteries of the huge future city are still lined by buildings

which are set back at various distances from the street, leaving

front dooryards between them and the sidewalk. Outside of the down

town district, and a limited area in East Liberty, it is possible,

therefore, to provide for the ultimate widening of these streets

without the destruction of many valuable structures, _provided the

preliminary steps are promptly taken_.

As traffic increases and the lots come to be used for business

purposes, such a set-back becomes inconvenient and undesirable, and

one by one the buildings are either extended to the sidewalk by new

additions, or new buildings are erected on the sidewalk line. The

reason for this change is not usually that additional lot depth is

required, for often considerable yards are left unoccupied at the rear,

but is simply that on a commercial street the buildings need to be as

close to the stream of traffic as possible; and since the individual

lot owner cannot move the street as a whole up to his building, he has

to extend or move his building to the street. His immediate purpose is

thus served, and ultimately the whole row of buildings is similarly

advanced in response to changed conditions. But at just about the

time when this process is fully completed, the volume of traffic

flowing over the street is apt to have become so great that everybody

recognizes the street to be too narrow for the increased traffic it

has now to carry. If the case is a bad one, the inconvenience due to

overcrowding the traveled way will in time reach a point where, in

spite of the great cost of such an operation, the buildings all along

one or both sides of the street have to be destroyed and a new building

line established--it may be on the very line where most of the original

buildings stood before increasing traffic began to offer inducements to

move them forward to the sidewalk. Indeed, it may be said as a general

rule that on any street where the buildings are set back from the

sidewalk line the very advancement of a few buildings to the sidewalk

line is a sign which points directly to the growth of travel and

indicates that ample width will soon be needed in that thoroughfare.

As soon as these conditions appear, it is time to act. As already

noted, it is not, in most cases, the desire to utilize a greater depth

of lot which leads to the change, but the desire to get next to the

sidewalk and to do away with a front yard which has served its purpose

and is not wanted under the new conditions. If the street is one likely

to have a considerable amount of through travel, it would be reasonable

_at once_ to lay it out wide enough to handle such travel; and the cost

of the land taken for the widening would be charged, at least in part,

to the abutters, for they get, by the change, what many of them already

want and what the rest will soon be wanting--direct frontage on a busy

sidewalk.

A still wiser course of procedure would be to determine on the widening

of these future main thoroughfares before any buildings have been

advanced to the sidewalk line, and to establish building lines far

enough apart to leave room for all probable future requirements;

but to make no physical widening of the street until the growth of

travel--or the demands of the abutters--call for shifting the sidewalks

over to the established building line and enlarging the roadway to

correspond. This is the invariable practice in Washington and in most

well-conducted European cities. It is the plan to some extent in New

York, where just recently the sidewalks of Fifth Avenue have been

moved back against the building line on the space formerly occupied

by stoops, areaways, and dooryards. Pennsylvania Avenue and Sixteenth

Street, in Washington, are both laid out 160 feet wide from building

line to building line, although Pennsylvania Avenue is an important

business artery and Sixteenth Street is a residence street without

heavy traffic and with no commercial business. On the former, the wide

sidewalks are in immediate contact with the fronts of the buildings,

as is proper for a business street, and the roadway, with car tracks

in the middle, is more than wide enough to carry all traffic that

can ever be concentrated upon it. Whereas, on Sixteenth Street, the

traveled portion of the street, including sidewalks and the space for

sidewalk trees, is only 80 feet wide; and the remainder is occupied by

front dooryards 40 feet deep, which the householders are at liberty to

fence and use almost as freely as if they owned them in fee simple. At

the same time all the householders are protected against the premature

action of any individual lot owner who might see a possible advantage

in being among the first to bid for a commercial business by building

a flat-house with stores under it out upon the sidewalk line 40 feet

in advance of the other houses. This is the sort of thing that is

happening every now and then in Pittsburgh on streets where the great

majority of the owners would prefer to have the set-back continued for

some years longer. In Washington this crowding forward cannot be done;

but when a reasonably large proportion of the owners on any street,

or any block of a street, are ready for the change, the front yards

are abolished and the sidewalk is moved over into contact with the

buildings. If a single owner wants to put in a store long before his

neighbors are ready to give up their front yards and long before the

City is ready to widen the street to increase its traffic capacity, he

is of course at liberty to do so; but he must not move forward of the

general building line. What he usually does is to abolish his own front

dooryard and substitute an extra wide piece of sidewalk paving in place

of it, sometimes using the space for outdoor stands, or show cases,

to attract trade. He may even be permitted to erect light temporary

structures, such as awnings, on the space between his main building and

the present sidewalk line, under which, in good weather, he can do a

very good business.

There is, then, one course of action which overshadows, in permanent

importance and in urgency, all other things that Pittsburgh could do at

the present time for the improvement of its main thoroughfare system.

That is to establish new building lines, at a suitable distance apart,

along all of its present and prospective main thoroughfares which there

is any prospect of being able to widen.

Pittsburgh, in common with other cities in Pennsylvania, has a

remarkable power, which is of the utmost importance in connection

with the intelligent control of its street development, but of which

it has not hitherto taken adequate advantage; a power that appears to

be denied to the cities of every other state in the Union, although

effectively used in some other countries. Pittsburgh may legally

lay out a street in anticipation of a future need, and yet postpone

entering upon the land for construction or for opening it to the

public. Until the city legally enters on the street, the owner of the

land has the free use thereof, and he receives payment only when the

opening takes place; but if, in the interim, he shall have erected any

structure within the limits of the proposed street, he will receive no

compensation therefor when the street is opened. Although similar laws

have been declared unconstitutional in other states, this provision

has been sustained in Pennsylvania, and the power has been effectively

exercised in numberless cases since the middle of the last century.

Philadelphia has applied the same principle to street widenings, as for

example in the case of Chestnut Street. The procedure is to define a

building line, set back a certain distance from the street line, and to

permit no new buildings to be erected in front of that line, but to pay

damages only when the power to prevent the erection of a new building

is actually exercised.

The Chestnut Street widening was authorized by legislation which

provided merely that the street should be widened ten feet, without

specifying the procedure or method of awarding damages.[7]

The procedure used in the widening, as above described, had apparently

no other authority than the general acts under which Pittsburgh has

proceeded in laying out new streets.[8] This application of those

acts has been sustained by the courts. If it is held that a specific

extension of the principle of the Act of 1871 to the widening of

Chestnut Street was implied in the ordinance of 1874, under authority

of the Act of April, 1870, and that it is not generally applicable to

widenings, a general act so intending ought to be secured from the

legislature.

In the Chestnut Street case existing buildings covered most of the

space between the building line and the street line, and the exercise

of the power, with the consequent accruement of damages, occurred in

each case only when the original building was torn down by the owner

and he was required to set the new building back to the new building

line.

The same principle is equally applicable to those cases where the

existing buildings are mostly or wholly back of the new building line;

the damages becoming due in such a case only when a building permit

for the erection of a new structure encroaching on the designated open

space is actually withheld.

The advantages of such a method of procedure, in the case of those

highways where all, or nearly all, of the buildings are now set back

from the street and where a widening will ultimately be needed, are

obvious and very great. In a large percentage of cases, where the

street is still mainly residential, the majority of the abutters would

welcome the establishment of a building line for their own protection

from inconsiderate neighbors; just as the majority of people will pay

higher prices for lots in a neighborhood that is protected by properly

drawn restrictions for setbacks, etc., imposed by a land company. In

a great many such cases abutters could be induced to waive any claims

for damages on condition that the building line should be applied to

the whole street. Furthermore, the actual net damages to be paid would

be distributed over a long period, and a considerable proportion of

them, in many cases, could properly be assessed on adjacent benefited

property owners.

When the actual physical widening of the street takes place, through

absorbing the restricted zones on each side of it, the damages for land

taking will be comparatively small, because at that time most of the

abutters will want nothing so much as that very widening, if only to

bring the sidewalks in contact with the fronts of their buildings. But

regardless of its clear financial advantages to the City, in reducing

its total payments for street widening and especially in distributing

the burden of that cost over a long period without running up a large

bonded indebtedness and interest charges, the fundamental argument

for this method of procedure is that it avoids the absolute dead loss

to the whole community resulting from the destruction of valuable

buildings. It is not practicable to avoid this in any other way and

still accomplish the result of widened thoroughfares. Theoretically, it

could be done by a direct widening of all the highways in the ordinary

manner, if it were to be done promptly; but there are comparatively

few cases in which there would be enough immediate advantage in the

increased width to make the proposition attractive; and it is obvious

that any such wholesale immediate action would involve a sudden and

enormous financial burden which it is utterly impracticable for the

City to assume.

If, after the gradual piecemeal process of widening at moderate and

distributed expense has been begun, the City thinks it would prefer

to have the process over and done with promptly, it is just as able

to complete the widening immediately, by wholesale condemnation,

as if the gradual process had never been entered upon. If the City

begins on the gradual process, it can always change to the other when

it feels rich enough, or when the buildings on the old lines have

become few enough; and in the meantime the erection of new and costly

buildings, obstructive to the proposed widening, has been prevented at

comparatively slight expense. If the City does nothing, pending such

time as it can afford to make the widening at a single operation, the

cost of the operation is liable to mount at least as fast as the City's

ability to pay for it.

While the method proposed is peculiarly adapted to handling the

problem of a thoroughfare along which the majority of the frontage is

not yet occupied by buildings standing on the street line, it may be

objected that it is not suitable for widening one that is built up,

like Forbes Street. It is true that the patchwork appearance of such

a street during the process of gradual reconstruction is somewhat

unsightly,--with here and there a wide place where new buildings have

gone up, and between them narrow parts, thus exposing the blank side

walls of old buildings projecting beyond the new ones. Yet in cities

where the sense of civic beauty is far more acute than it generally is

in America, this temporarily ragged condition is accepted as a small

price to pay for the economical and certain accomplishment of a great

permanent improvement.

[Sidenote:

Unified Procedure For City, County and Borough]

It is obvious that the flow of traffic moves regardless of the

artificial boundaries of the city and the surrounding boroughs, and

that if an efficient system of thoroughfares is to be involved for

the Pittsburgh Industrial District it will be necessary to disregard

those boundaries in planning it. This has been done in the preliminary

studies which have resulted in this report, and the necessity for it

must control the form of any permanent organization for preparing

final plans and executing them. If these duties are to be entrusted

to officers of the City, and the city boundaries remain unchanged,

those officers must have authority from the legislature to deal with

territory beyond the boundaries of the city, as is the case in a

limited way in Wisconsin cities.[9]

The simplest and most logical procedure, if the boundaries of the city

and of the boroughs are to remain substantially unchanged, would be to

establish a common agency for dealing with the general problems of city

planning for all of the municipalities and the related parts of the

country outside of them. The Constitution of Pennsylvania apparently

prevents the formation of a special metropolitan board for the

Pittsburgh Industrial District, but general authority might be obtained

under which the County could establish such a board. If the difficulty

should be met simply by extending the boundaries of the city, it is

important that the new boundaries should include not merely those areas

which are now seen to have close physical relations with the city, but

a great extent of territory within which the beginnings of urban or

suburban growth have started, or are likely to start, during the next

generation.

Whether the duty of planning and providing for the main transportation

lines is made a city affair or a county affair, those who are charged

with it should be free to go as far in any given direction as the

demands of the traffic lead them. They should neither be limited by

arbitrary boundaries in those directions where scattering but connected

urban development may reach out furthest from the center, nor

compelled to extend their operations to an arbitrary boundary in those

directions where such development falls short.

SPECIFIC RECOMMENDATIONS

MAIN ARTERIES

[Sidenote:

Penn Avenue Artery]

As noted earlier in this report, one of the two main eastward

thoroughfare routes, from the Point District, must lie along the

flat land between the Allegheny River and the bluff southeast of the

Pennsylvania tracks. Through this bottle-neck must pass the trunk line

(or lines) of one of the largest thoroughfare systems leading from the

down town district of Pittsburgh. At the foot of the Lawrenceville hill

the system branches into two main lines of extension. On the one hand

are Penn and Liberty Avenues, extending, by different routes, through

the Garfield, Bloomfield, Friendship and Shadyside Districts to East

Liberty; and from there connecting directly to Squirrel Hill, Highland

Park, Homewood, Brushton, Wilkinsburg and all points further east.

On the other hand is Butler Street, following the low land along the

river through Lawrenceville to Morningside and Highland Park. Via the

Forty-third Street bridge, this line reaches Millvale and the country

north thereof; via the Sharpsburg and Aspinwall bridges it reaches

Etna, Sharpsburg, Aspinwall, and Shaler and O'Hara townships, and

connects directly with the Freeport Road, the only thoroughfare leading

up the Allegheny River. The trunk line of this system is composed of

two narrow streets, Penn Avenue and Liberty Avenue, the one 60 and the

other 50 feet in width. Even now this accommodation is inadequate,

and, considering the extent of territory served and the increase of

through traffic to be expected as the city grows and the outlying lands

develop, a much greater capacity for general traffic through this

throat will very soon be needed.

There are four different ways in which this greater capacity might be

realized.

In the first place, a new street might be cut through north of Penn

Avenue. Smallman Street, from Twenty-first to Thirty-sixth Street,

already forms a good sized piece of such a thoroughfare. Pike

Street would be its normal extension in town to Eleventh Street,

but, like Try Street near Second Avenue, it has been surrendered to

the Pennsylvania Railroad for a connecting line and spur tracks.

Furthermore, it is very narrow (not over 40 feet) and is difficult to

widen on account of the many industrial plants abutting thereon. The

connections from such a thoroughfare with Penn Avenue, Liberty Avenue

and Butler Street at one end, and with the down town thoroughfares at

the other, are quite indirect; and they could be improved only at great

expense.

The only other place for a new thoroughfare is along Spring Alley,

between Penn and Liberty Avenues. As this whole block is only 220 feet

wide, including the alley, it is obvious that a broad avenue through

the middle of it would leave the abutting property in very uneconomical

shape.

As a modification of this plan, the widening of Spring Alley entirely

on the south side was considered. As this would leave lots 40 feet

or less in depth between the new street and Liberty Avenue, it would

mean the practical destruction of the half-block from Spring Alley to

Liberty Avenue. The remaining strip could be taken as a central parking

space in a wide boulevard thoroughfare, extending from Spring Alley to

the railroad; or Liberty Avenue could be abandoned, and the space, left

between the new street and the railroad, could be used for warehouses

or for business wanting direct railroad connections; or it might be

sold in whole or in part to the Pennsylvania Railroad, for additional

track space. It is obvious that each of these plans cuts up the

property undesirably: the first is not only costly but is extravagantly

wasteful of land in a region where available land is strictly limited

and should therefore be put to its most efficient use: and the other

plans both involve an entire redistribution of the land south of the

new street. They could hardly be executed without powers of "excess

condemnation" for which constitutional authority is lacking.

A third plan would be to widen Liberty Avenue on the north side. There

is no special difficulty in the way of this scheme, and it could

certainly be more easily carried out, and at less cost, than any of the

Spring Alley plans. Merely as a traffic way between two points, Liberty

Avenue widened would be perfectly satisfactory, but several incidental

considerations must be borne in mind. First, the lots on the north side

of the street would be cut at least to 70 and probably to 50 feet,

neither of which is a desirable depth for lots on a main thoroughfare;

and second, the street would have business frontage on one side only.

The latter is an uneconomic arrangement from the point of view both of

the real estate owner and of the City, and the street would be much

less agreeable than if it were separated from the railroad.

The fourth plan would be to widen Penn Avenue. This street is now 60

feet in width, and most of the lots on each side are 100 feet deep,

except for several blocks on the north side where they are about 120

feet. The street is built up solidly on both sides, but scarcely any

of the buildings are new or costly. The property values are almost

uniformly a little higher than on Liberty Avenue. If Penn Avenue were

widened 10 feet on each side, making an 80-foot thoroughfare, the

abutting lots would still be 90 feet or over in depth; and if the

street were made 100 feet wide, the lots would still be 80 feet deep.

Though it might cost somewhat more to widen Penn Avenue than Liberty

Avenue, it is evident that the abutting property would be left in far

better shape, and the benefit to be had from increased frontage value

would be much greater.

After due consideration of each of the above plans, bearing in mind

the cost, the difficulty of carrying it out, and the value of the

result, both as an important main thoroughfare artery and as a local

improvement, it is recommended that Penn Avenue be widened to 100 feet.

If the widening is to be accomplished by the gradual process,[10]

that is by merely establishing the new building lines at the present

time, and by paying damages only when new buildings are set back to

this line, the widening should probably be made on both sides: for

in this way the minimum set-back will be required for individual new

developments and the lots will be left of a good depth on both sides

of the street. But if the widening is all to be made at once, it will

be less costly to make it entirely on the south side. In either case,

the lots remaining will be none too deep, and it is suggested that

ultimately Spring Alley may be abandoned and the opportunity furnished

for deep lots for warehouses and similar purposes, fronting on a large

thoroughfare and having direct railroad connections over Liberty Avenue

in the rear.

[Sidenote:

Forbes Street Artery]

The other eastward thoroughfare system lies south of the Hill District.

From Soho eastward there are two main branches to the system: on the

one hand are Forbes Street and Fifth Avenue, leading through Oakland

to Bellefield, Shadyside, East Liberty, Squirrel Hill, and all points

east; on the other hand is a possible and much-needed thoroughfare

reaching Greenfield, Hazelwood, Glenwood, and Hays, and from there, by

branches and extensions, connecting to Homestead, Duquesne, McKeesport,

and points up the Monongahela and Youghiogheny Rivers, as well as to

the country south in Baldwin, Mifflin, Snowden, and Jefferson townships.

At present the trunk-line of this system (from the Point District past

Soho hill) is composed of three narrow streets, Second Avenue, Forbes

Street, and Fifth Avenue, which all together are no more than adequate

to accommodate the present surface travel. Future developments in the

East End, up the Monongahela, and in the country south of Homestead,

and improved thoroughfare connections with the two latter regions, will

undoubtedly increase the through traffic on these streets to such an

extent that their capacity will soon be taxed beyond its limit. There

can be no doubt that more accommodations will be needed in the near

future.

[Illustration: Section of Second Avenue between Try Street and Tenth

Street Bridge]

At first thought it was hoped that Second Avenue might be improved to

accommodate a reasonable increase in east and west traffic; but the

Baltimore & Ohio Railroad on one side, and several large industrial

plants on the other, present serious obstacles to widening it. A plan

to exchange locations with the railroad was considered, but it did not

appear to offer sufficient advantage to the railroad to tempt them to

cooperate in the matter.

Incidentally, Second Avenue can and should be widened to 80 feet, from

Ross Street to the Tenth Street bridge, thus making a good connection

between the Point District and the South Side.

It remained then to secure the desired street capacity, in some way,

through the valley now occupied by Forbes Street and Fifth Avenue. To

avoid the higher land values on these streets, various schemes were

tried to get a third thoroughfare in this valley, first on the south

and then on the north side, but without success. The indirectness of

line and the seriousness of grade difficulties, coupled with cost

of cutting new connections at either end, more than outweighed the

advantages offered by the cheaper land.

One proposition, however, is worthy of special remark. That was to

cut a new street from Fifth Avenue, near Sixth Avenue, to the end of

Colwell Street, widen the latter, carry it over the Moultrie Street

valley on a high viaduct, skirt around Soho hill, partly above and

partly below Beelen Street, and either join Fifth Avenue at Robinson

Street, or, going over this street, follow along the hillside and meet

the southerly end of Bayard Street. The cost of constructing this line,

the complication of grades with cross-streets (owing to the width of

the new street), and the difficulty of getting good connections with

any thoroughfares leading up the Monongahela, practically put it out

of the question as a solution of the main problem in hand. But it

offers many advantages as a specialized thoroughfare for fast-moving

automobiles for the East End. It is well up on the hill, furnishing,

at times, fine outlooks over the river; the gradient need nowhere be

over 4 per cent, and the line could be easily laid out so as to have

very few grade crossings with other important streets. It is urged that

this route be borne in mind when the demand is felt for another "Grant

Boulevard," south of the Hill.

It remained, then, to consider adequate widenings of Fifth Avenue or

Forbes Street. The former is now 60 feet wide throughout; it is by

far the more important thoroughfare at present, land values are much

higher than on Forbes Street, and new and somewhat costly buildings are

already crowding out the cheap houses of an older generation. Forbes

Street is also 60 feet in width, except near its westerly end where

it is only 50 feet, but the buildings, on the whole, are much less

valuable than those on Fifth Avenue. Lot depths are practically the

same, and so are the street gradients. It is evident, therefore, that

the widening of Forbes Street should be a far less costly undertaking

than the widening of Fifth Avenue.

A thorough study of the possible eastward extensions of Forbes Street

has developed no obstacles to using it as the principal thoroughfare.

By referring to "Outlying Thoroughfare Improvements" below (Sections

11, 14, 15, 16, 17 and 19), it will be seen that a cross connection can

easily be secured at Brady Street to Fifth Avenue--the latter being

the easier street to widen beyond this point, as well as offering

somewhat better gradients. It will also be seen that the thoroughfare

extension to Greenfield, Hazelwood, Glenwood, and eastward, can branch

from Forbes Street (just east of Brady) more easily and cheaply than

it could from Fifth Avenue. Forbes Street, moreover, enters the down

town district at a slightly more central, and, considering the proposed

improvements in the down town district, a more advantageous point.

It is recommended, therefore, that Forbes Street be made the main

artery of this eastbound thoroughfare system, and that it be widened to

100 feet. As in the case of Penn Avenue, the widening should be made on

both sides if done by the gradual process; but if done all at one time,

it should be made entirely on the south side.

[Sidenote:

South Hills Artery]

Between the Point District and the South Hills there is now urgent need

for a thoroughfare connection of adequate capacity and on reasonable

gradients. At present the only access for surface traffic--except

electric cars--is via the Brownsville Road, or South Eighteenth Street,

or the inclines. The two roads are steep, from 7 to 8 per cent, and the

inclines are expensive and of very limited capacity. The South Hills

country is sparsely developed as yet, but, being comparatively free

from smoke and very near to the business district, it offers unusually

desirable opportunities for homes, and it must soon be thickly settled.

The need for a good thoroughfare to this region will then be of far

greater importance even than now.

Only two reasonable ways of securing such a thoroughfare appear. One is

by a new slanting road up the hillside south of the river, much longer,

and so on an easier gradient, than Brownsville Road; the other is by

some high-level bridge and tunnel scheme, such as that proposed by

residents of the South Hills.

The opportunities for a hillside road have been studied with some care,

but the excessive length required to get a reasonable gradient, and

the difficulties and high cost of constructing a wide thoroughfare on

the steep hillside, have proved to be serious drawbacks to all possible

plans for such a street.

[Illustration: Entrance to a thoroughfare tunnel, Stuttgart]

In any thoroughfare scheme to the South Hills, it is reasonably clear

that the end to be attained is the _most direct_ access possible on

_easy gradients_ to the _higher levels_ of the South Hills country. For

it is on the upper levels, the hilltops and the upper slopes, that most

of the present development has taken place; and there can be little

doubt that in the future, even when building space is at a much higher

premium than it is now, the overwhelming majority of the population

will be found on the hills rather than in the narrow valleys.

[Illustration: Thoroughfare tunnel at Budapest]

[Illustration: Panther Hollow bridge--a good-looking viaduct in

Pittsburgh]

There are certain general tendencies which are observable, both in

America and in Europe, in cities which have a large area of hilltop

land separated by deep valleys. The hills are generally preferred for

residential purposes, and the earliest roads or trails often follow the

ridges, plunging down and climbing up again steeply to get from one

ridge to another. The main roads in the second stage of development

are apt to seek the valleys for the sake of good gradients, with a

corresponding development of the most active urban growth in the

valleys and on the lower slopes; the hilltop development being retarded

by lack of transportation facilities. Nevertheless the continued

attractiveness of the uplands slowly builds them up, and as the wealth

of the community grows there is an inevitable tendency to reduce the

obstacles to ready connection between one hill district and another by

raising the levels of the bridges which cross the intervening valleys.

Bolder and bolder viaducts are built, until finally there is a complete

and more or less independent highway system on the upper levels, and

the major part of the residential district comes to be there too.

Obviously, therefore, every opportunity should be utilized to gain

grade, in the approach to the South Hills District, by starting at a

high elevation and wasting no distance in level stretches, if the most

efficient thoroughfare artery to this district is to be secured.

[Illustration: A viaduct in Lausanne, showing how the valleys are

spanned by the main traffic ways]

The bridge and tunnel plan, proposed by residents of the South Hills,

is briefly as follows: to start from Forbes Street, at Sixth Avenue,

and rise steadily to the bluff north of Second Avenue; from here to

rise on a bridge over the river, at a uniform gradient, to the opposite

hill; to pierce the hill by a tunnel, at the same gradient, and reach

the level of the present highways at the junction of Washington Avenue

and Haberman Street. It is proposed also to have a lower deck on the

bridge, which would connect East Carson Street with Second Avenue and

an extension of Sixth Avenue.

This plan has the obvious advantage of starting some 40 feet higher

than any of the present bridge approaches in the down town district,

and at a point from 500 to 1000 feet north of any other feasible

point of departure. Considerable gain is thus made at the very start.

A uniform, uninterrupted gradient is proposed, from Forbes Street

to Washington Avenue, in order to climb the maximum amount possible

with a given distance and gradient. Information furnished us through

the office of Edwin K. Morse shows that the horizontal distance from

Forbes Street to Washington Avenue is 6800 feet and the difference

in elevation between the two points is 260 feet. It follows that a

uniform gradient, from one end to the other would be 3.82 per cent;

this could be reduced to 3.74 per cent by raising the grade of Forbes

Street about 6 feet, a change which is to be desired in connection

with the down town thoroughfare improvements and the Civic Center. At

first sight this gradient seems good for Pittsburgh; but bearing in

mind the distance--over a mile and a quarter--for which this gradient

is maintained without a break, considerable hesitancy is felt about

recommending it for the main artery of a large thoroughfare system. A

gradient of 3.5 per cent should probably be considered a maximum for

such a long climb on a main thoroughfare, and 3 per cent would be far

better. The former gradient could be secured by dropping the southern

end of the tunnel about 16 feet, the latter by dropping it about 50

feet. In either case, the southern end of the tunnel, or its approach,

would be bent westward and extended a little down the valley, north

of Washington Avenue, toward the mouth of the street car tunnel. The

exact amount of reduction to be desired in the tunnel gradient must

be finally determined in conjunction with a careful study of its

southerly extensions based on complete and accurate surveys of the

possible routes. There is no advantage in lengthening one portion of a

thoroughfare to get a 3 per cent gradient if nothing better than 3.5 or

4 per cent can be secured on the rest of the route. The surveys made

for the County Commissioners, under the direction of E. M. Bigelow,

and courteously shown to representatives of the Civic Commission,

unfortunately fail to furnish the needful data, as they do not extend

to the upland districts which are the ultimate objective of the

proposed route.

[Illustration: ROUGH PROFILES OF SOUTH HILLS TUNNEL AND THOROUGHFARE

ROUTES

The high-level tunnel reaches existing streets at Washington Avenue.

From this point is planned a system of thoroughfares, which, if

constructed, would reach all parts of the South Hills. These

thoroughfares are indicated by dashes beyond the junction of the tunnel

with Washington Avenue.

The Bell House, or low-level tunnel is indicated by a dotted line. It

is an approach to the West Liberty Road and would give easy access only

to the territory reached by that road and to other territory in the

nearby valley bottoms.]

[Illustration: The above diagrams show the areas that can be reached

via the low-level and high-level tunnel routes to the South Hills, on a

maximum gradient of 3½ per cent, by hauls of various lengths from City

Hall. The areas are given in the following table:

---------+---------------------+----------------------+---------------------

| |Amount of land sloping| Remaining land

| Total area reached | over 25 per cent | available for use

---------+---------------------+----------------------+---------------------

Length of| | |

haul from| | |

City Hall| | |

---------+----------+----------+----------+-----------+----------+----------

|Low-level |High-level|Low-level |High-level |Low-level |High-level

| route | route | route | route | route | route

---------+----------+----------+----------+-----------+----------+----------

2½ miles | 156 acres|1091 acres| 86 acres| 373 acres | 70 acres| 718 acres

3 miles | 672 " |2710 " | 293 " | 848 " | 379 " |1862 "

3½ miles |2763 " |4877 " |1053 " |1617 " |1710 " |3260 "

4 miles |6329 " |7408 " |1935 " |2449 " |4394 " |4959 "

---------+----------+----------+----------+-----------+----------+----------]

But even without precise data, it is clear that the best permanent

means of reaching those upland districts, whether on one side of

Sawmill Run or on the other, is not by a tunnel debouching in the

bottom of the valley--say at the Bell Tavern. This follows from the

fact that the tunnel _can_ reach a much higher level at a good gradient

and with a shorter distance. And from this higher outlet point a

viaduct high in the air above the Bell Tavern would give direct access

to the uplands of Beechview and Mt. Lebanon and southward, while

streets of easy gradient would reach the uplands east of Sawmill Run.

The high level tunnel, furthermore, will reach all the areas served by

the low level, or Bell Tavern, route, and in addition can reach the

other and more important lands on the hills which _cannot_ be reached

via the Bell Tavern route within a reasonable distance.

The thoroughfare extensions from the southern end of the tunnel are

briefly discussed under "Outlying Thoroughfare Improvements" below. At

its northern end the new bridge would fit admirably into the proposed

thoroughfare system of the Down Town District, main wide streets

extending directly from the end of the bridge approach to the north,

south, east, and west.

Owing to the importance of the South Side as a point for the delivery

of freight, a reasonably direct and easy approach from there to the

new tunnel seems desirable. Freight to be teamed to the South Hills

District seems likely to originate either near the Smithfield Street

bridge, or east of South Seventeenth Street. From the former point, it

is almost out of the question to get an approach of easy gradient to

the mouth of the tunnel, on account of the lack of distance; but it

must be remembered that the inclines will still be available, greatly

relieved by the new tunnel from their present congestion, and further

that freight for the South Hills could easily be shipped to points

from which access to the new tunnel would be easy and direct. From

the latter point, the connection can be secured by climbing over the

railroad on a viaduct, probably along South Twelfth Street, and thence

following the hillside westward on a more or less uniform gradient

to the mouth of the tunnel. An examination of the hillside below the

Brownsville Road indicates that such a street, though somewhat costly,

is not in the least impracticable. It might be best to construct

it with a minimum of cutting by the use of a sidehill viaduct of

reinforced concrete.

With the modifications above suggested the plan proposed by the

residents of the South Hills, for a bridge and tunnel to the South

Hills District, is eminently desirable. It is, therefore, urgently

recommended as the best method of securing an adequate main

thoroughfare artery to this region.

OUTLYING THOROUGHFARE IMPROVEMENTS

The following recommendations are in no sense the result of an

exhaustive study of the main thoroughfare system of the Pittsburgh

District. They comprise only the most desirable improvements noted

during a general study of the outlying branches and connections of

those thoroughfares which concentrate upon the down town district. The

fact that a study undertaken with such a point of view has led so far

afield that it has compelled the investigation of existing and probable

connections so remote as some of those noted below, is, in itself,

evidence of the complexity of the highway problem, and of the fact that

it cannot be dealt with locally, in a piecemeal manner, without great

sacrifice of opportunity.

The improvements are designated in the following text by numbers which

correspond with those on the accompanying folded map of the Pittsburgh

District.[11]

1. _Sixteenth Street Bridge._--The first thoroughfare branch of the

Penn Avenue artery is the Sixteenth Street bridge. Because of its

physical unfitness, and because it is, at present, an unreasonable

interference to navigation, it must soon be rebuilt.[12]

At the time of reconstruction, the railroad grade crossing on each

approach should be eliminated, probably by carrying the street over the

tracks. At the southern end, the grades make such a change very simple.

At the northern end, the separation of grades will be facilitated if

the tracks of the Pittsburgh and Western Division of the Pennsylvania

Railroad can be lowered a few feet. No physical objection to such a

change of track grade is apparent.

[Illustration: Diagram No. 1. Thirty-third Street improvement. Profile

of Liberty Avenue]

2. _Twenty-eighth Street Grade Crossings._--Near Twenty-eighth Street

the tracks of the Allegheny Valley Railroad cross both Liberty and

Penn Avenues at grade. These grade crossings should be eliminated, the

railroad tracks being raised to go over both streets.

[Illustration: Diagram No. 2. Penn-Liberty connection at Thirty-first

Street]

3. _Thirty-third Street Improvement._--At Thirty-third Street on

Liberty Avenue there is a railroad grade crossing. The street should be

lifted over the tracks and the filling extended west to Thirty-first

Street and east to Thirty-seventh Street; in this way the gradient of

the steep portion of the Lawrenceville hill can be reduced from 5.6 per

cent to 4 per cent, which is the present gradient on the rest of the

hill. (Diagram No. 1.) An easy connection should be made with the Penn

Avenue artery at about Thirty-first Street. (Diagram No. 2.) With these

changes the Penn-Liberty line would provide a thoroughfare from the

down town district to the East End with a 4 per cent maximum gradient,

which is easier than can be reasonably obtained on any other line.

The northern end of the Thirty-third Street bridge and the west end

of Ligonier Streets should be raised to meet the new grade of Liberty

Avenue; the bridge will then be about level, and Ligonier Street will

slope between 6 and 7 per cent down to Thirty-fourth Street.

[Illustration: Diagram No. 3. Penn-Liberty Connection at Howley Street.]

4. _Sassafras Street Outlet._--Raising the grade on Liberty Avenue will

seriously interfere with the western outlet of Sassafras Street. But

if this street becomes of sufficient importance--and its location in

the valley close to the railroads suggests a considerable development

of its frontage for freight houses, warehouses or manufacturing--it

will be simple and satisfactory to bring the western outlet to the

junction of Penn Avenue and Butler Street by means of a short tunnel

under Thirty-fourth Street from the south side of Liberty Avenue to the

northwest side of Ligonier Street.

5. _Penn-Liberty Connection at Howley Street._--A connection northeast

from the junction of Liberty Avenue and Main Street to Penn Avenue

will be needed. (Diagram No. 3). This can be secured by widening

and extending Howley Street. Thereby traffic bound for the Garfield

District and east thereof can climb the Lawrenceville hill by the

comparatively easy gradient (4 per cent) on Liberty Avenue, avoiding

the steeper hill (about 5 per cent) on Penn Avenue. This will also

connect with the proposed Bloomfield bridge to Grant Boulevard.

6. _Forty-third Street Bridge._--Butler Street is the main extension

of the Penn Avenue artery up the Allegheny River, and its first branch

thoroughfare is at Forty-third Street. The Forty-third Street bridge,

like the one at Sixteenth Street, must soon be rebuilt.[13] This bridge

connects Millvale and large sections of Shaler and Ross townships with

the Point District via the Penn Avenue artery. The new bridge should be

of ample width and should be high enough so that the approaches can be

carried over the railroad tracks at either end.

7. _Sharpsburg Bridge._--The Sharpsburg bridge is the next important

branch of the Butler Street thoroughfare. It forms the most direct

connection from Pittsburgh proper to the boroughs of Sharpsburg and

Etna and to large portions of Shaler and O'Hara townships. The bridge

should be widened--the present roadway being only 21 feet including car

tracks--and the northern approaches should be improved. (Sections 60

and 61 following.)

8. _Butler Street Improvement._--From a point nearly opposite the

western end of Baker Street east to Haights Run, there is no property

of value for manufacturing, or for dwellings, or stores, between

Butler Street and the railroad which runs below it on the river bank.

The same is true east of Haights Run as far as the Brilliant pumping

station or the present beginning of Beechwood Boulevard. It seems

very desirable that these portions of Butler Street, instead of being

widened merely enough for traffic accommodation, be developed as a

picturesque riverside parkway--a fitting approach to Highland Park and

a continuation of Beechwood Boulevard. This involves the control of the

narrow strip of property between Butler Street and the railroad; though

occasional houses might be allowed to remain therein without detriment

to the effect as a whole. The Bureau of Parks is working along these

general lines, and has already bought many parcels of the land north of

Highland Park between Butler Street and the railroad.

9. _Haights Run Bridge._--The present Butler Street bridge over Haights

Run is of light construction and has a total width of only 17 feet;

this should be rebuilt of ample strength and capacity.

10. _The Aspinwall Bridge._--The Aspinwall bridge, crossing the

river at Six Mile Island from Butler Street to the eastern portion of

Sharpsburg, is narrow (36 feet over all) and is of light construction.

It is so important that it will some day need to be rebuilt of ample

width and strength for main thoroughfare use. At its southern end it

connects (1) with the Butler Street thoroughfare, of which it forms

the northeastern extension, and (2) with a proposed cross-town line

(Section 25 following) up the Haights Run Valley to East Liberty. On

the north it connects directly with Guyasuta and Aspinwall, with most

of the country in O'Hara township, and with the Freeport Road leading

to Claremont, Montrose, Oakmont and all points up the Allegheny River.

This Freeport Road is destined to become _the_ main thoroughfare up

the Allegheny because the precipitous character of the south bank of

the river, and the consequent almost total absence of land suited

to residential or commercial development between Highland Park and

Verona, make the direct extension of Butler Street, as a riverside

thoroughfare, both expensive and impracticable.

[Illustration: Diagram No 4. Forbes Street--Fifth Avenue connection at

Soho]

[Illustration: Diagram No. 5. Fifth Avenue--Center Avenue connection at

Soho]

11. _Forbes Street--Fifth Avenue Connection at Soho._--At Soho the

connection between the Forbes Street artery and Fifth Avenue--the

principal thoroughfare to Bellefield and all points to the east

thereof--is most simply accomplished by splitting the Forbes Street

artery at Seneca Street into two levels, the upper, on the north side,

running on nearly a straight line and gradient to Fifth Avenue, joining

it just west of the school house. (Diagram No. 4.) The lower portion

would become the continuation of Forbes Street, and should be raised

at Brady Street about 17 feet, or so much that the gradient on Brady

Street, up from Forbes Street under the proposed high-level street

to Fifth Avenue, will not be over 6 or 7 per cent. A good gradient

will still be possible on the approach from Forbes Street to the

Twenty-second Street bridge; and the Forbes Street gradient, down from

Seneca Street, will be much reduced. These changes will greatly improve

the means of access to the Twenty-second Street bridge.

On Forbes Street, just west of Craft Avenue, there is a bad gradient

for a main thoroughfare (about 6½ per cent) which is not easy to

improve; but the above cross connection at Brady Street will give a

through line to the East End via the Forbes Street artery and Fifth

Avenue, with a maximum gradient of about 4½ per cent (on the Soho hill).

[Illustration: Diagram No. 6. Ellsworth Avenue extension]

12. _Fifth Avenue--Center Avenue Connection at Soho._--As a main

thoroughfare feeding Minersville and the northern part of the Hill

District, either from the South Side via the Twenty-second Street

bridge, or from the Point District via Fifth Avenue or Forbes Street,

a connection is needed on a reasonable gradient from Fifth Avenue to

Center Avenue through the valley south of Soho hill. Such a street

(Diagram No. 5) could leave Fifth Avenue at Jumonville Street, start

along the location of Wyandotte Street, then curve around the nose

of the hill and follow the hillside on the west of the valley; thus,

by cutting away some of the recent filling at the upper end of the

valley, it could reach Center Avenue at the corner of Soho Street with

a uniform gradient of about 3 per cent. At present there is no way of

reaching this high land on a gradient less than 7 per cent.

The new street shown on the diagram is preferred to the improvement and

extension of Moultrie Street because (1) it gives a better gradient,

(2) it is a more direct approach from the down town district, and (3)

it leaves the bottom of the valley available for enlarging the Moultrie

Street playground.[14]

[Illustration: A one-sided hill-street in Geneva, possessing an

incidental recreative value]

13. _Ellsworth Avenue Extension._--As Fifth Avenue is the principal

thoroughfare to Bellefield, so Ellsworth Avenue becomes its main branch

or extension from Bellefield to East Liberty. This street should not

end at Neville Street, as at present, but should be extended to the

corner of Craig Street and Fifth Avenue. (Diagram No. 6.)

[Illustration: Diagram No. 7. Monongahela hillside thoroughfare--a

typical section]

14. _Monongahela Hillside Thoroughfare._--The thoroughfare requirements

from the Forbes Street artery up the Monongahela River can best be

met by a hillside street, partly new and partly following existing

streets, running substantially parallel to Second Avenue but along

the hillside above the railroad tracks. This thoroughfare would leave

Forbes Street at the bend about 1200 feet east of Brady Street, cross

the little valley (which should be filled north of the new street) and

extend eastward, crossing Bates Run on a viaduct, and using, where

possible, parts of Lawn and Frazier Streets, to the mouth of Four Mile

Run. Thence, by another viaduct, it would connect with Sylvan Avenue,

on the north side of the valley, and follow this street widened to

Hazelwood Avenue; by another viaduct it would cross the Flowers Avenue

valley to Glenwood Avenue and follow the latter widened and partially

regraded to Mansion Street. There it would bend to the northeast, cut

through the plateau land to the next ravine, cross this on a viaduct

and, bending southward again, descend around the nose of the hill to

the Glenwood bridge. So easy a gradient can be obtained on this new

street that it may reasonably be expected to carry nearly all the

through traffic. With proper connections (the most important of which

are described below), it will also take most of the travel to and from

the residential districts lying above it to the northeast.

The location of this street, high on the hillside above the Monongahela

River, presents unusual opportunities incidental to serving its primary

purpose as a main thoroughfare. With an ample roadway for all kinds of

traffic, with trees for shade and decoration, with a broad promenade

overlooking the river and the hills to the south, it would furnish rare

and much-needed facilities for recreation; and, further, it would have

a distinctive character most appropriate to the rugged topography of

the Pittsburgh District. (Diagram No. 7.)

15. _Bates Run Connection._--Starting from the western end of this new

street, the first important transverse street connection would be at

Bates Run. Here a street should be run up the east side of the valley,

not far from the present location of Romeo Street, to the intersection

of Wilmot and Bates Streets, thus reaching the Oakland District.

16. _Greenfield Avenue Connection._--On the southeast side of Four

Mile Run the new thoroughfare will pass over Greenfield Avenue. But

a connection should be made therewith by running a practically level

street, from about the junction point of Sylvan Avenue and the new

thoroughfare, northeast along the hillside adjacent to Greenfield

Avenue until it meets the Greenfield Avenue grade.

17. _Greenfield and Squirrel Hill Extension._--From this point

on Greenfield Avenue a new street should be built running to the

northeast. It would cross the first little ravine on a viaduct, thence

follow the south bank of the Four Mile Run valley, climbing at a

uniform gradient, and join Beechwood Boulevard at the southern end of

the bridge into Schenley Park. This will furnish a direct connection

from the new hillside thoroughfare to the eastern portion of the

Greenfield District and to Squirrel Hill; the maximum gradient will be

only about 3½ per cent instead of about 7 per cent as at present on

Greenfield Avenue.

This new street could be extended, from the point where it joins the

boulevard, underneath the Greenfield Avenue viaduct, along the side of

the valley to the south and up to the higher portions of the Greenfield

District. The gradient of such a street need not exceed 5 per cent.

18. _Hazelwood Grade Crossing._--Although the construction of the

hillside thoroughfare (Section 14 above) does away with the necessity

for widening Second Avenue east of the Tenth Street bridge, Second

Avenue is still an important main line, and all feasible improvements

should be made thereon. One of these is the elimination of the grade

crossing at Hazelwood, and here Second Avenue should probably be

carried under the tracks.

19. _Glenwood Bridge._--The Glenwood bridge becomes a most important

link in the thoroughfare system; it connects Second Avenue and the

proposed hillside line at one end, with Eighth Avenue in West Homestead

and with the mouth of Streets Run at the other. Eighth Avenue leads

up the Monongahela to Homestead, Munhall, Rankin, Braddock, Bessemer,

Duquesne and McKeesport; Streets Run is the starting point of several

important thoroughfare lines into the country south and east. One of

these thoroughfares will undoubtedly be a main line from the city

proper to Dravosburg and points above on the Monongahela River. The

bridge should certainly be widened and the gradients of the approaches

improved, especially that from Second Avenue.

20. _Baum Street Improvement._--Grant Boulevard will always be an

important line to the East End, especially for fast-moving travel. To

improve its outlet eastward from Herron Hill, Baum Street and South

Atlantic Avenue should be connected and extended west to Craig Street.

The connection between the two streets is easily made by cutting

through the corner between Liberty Avenue and Rebecca Street, leaving

a small triangular park. The extension of South Atlantic Avenue will

require a bridge over the Pennsylvania Railroad just east of Morewood

Avenue, a bridge over the Baltimore & Ohio tracks, and the grading and

paving of the street already located west to Melwood Avenue and Craig

Street.[15]

At its eastern end the outlet into Penn Avenue should be improved by

widening Whitfield Street on the east side and by rounding back the

corner of Baum Street and South Highland Avenue.

21. _Center Avenue Improvement._--The junction of Center, Ellsworth and

South Highland Avenues at East Liberty is certain to become a congested

point and to require more ample outlet into Penn Avenue. Several

possible solutions have been considered, but the simplest plan, and

probably in the end the most economical and satisfactory, is to widen

Center Avenue on the south side from South Highland Avenue to Penn

Avenue, cutting off the jog at the latter end. This improvement will

give ample connection with Penn Avenue and the more important streets

radiating from East Liberty. (Diagram No. 9.)

Pittsburgh Main Thoroughfares and the Down Town District Improvements Necessary to Meet the City's Present and Future Needs · 第 2 / 6 章