CHAPTER XIII.

CRANES.

It appears that Mr. Stevenson was much perplexed as to what sort

of cranes he should use in building the Bell Rock Lighthouse. His

difficulties were twofold:--

_First_, In consequence of the dovetailed form of the stones he

required a crane that would drop them as nearly as possible on the beds

on which they were permanently to rest.

_Second_, Supposing he devised a _guy crane_ that overcame this

difficulty, what was to be done as the building rose in height, and the

guys became too nearly perpendicular to admit of such a crane being

used?

In his private notes Mr. Stevenson regrets that he could get no advice

from anybody he consulted, all of whom recommended him to employ common

sheer poles, such as had been used by Smeaton at the Eddystone; and he

adds, “I may say, morning, noon, and night, these difficulties have

haunted me.” But thrown back on his own resources, and appreciating the

difficulty as no one else could so well do, he found, as is often the

case, that he was his own best counsellor, and he succeeded in solving

the problem that had given him so much concern, by inventing what he

called the “moveable beam crane,” and also the “balance crane,” which

are shown in Plate XI. The former, as modified to suit particular

cases, is now in universal use for building purposes, and the latter

has been employed in rearing most of our Rock Lighthouses, so that I

think professional readers will not object to my giving Mr. Stevenson’s

description of these cranes, as designed by him at the beginning of

this century. He says:--

“In cranes of the common construction the beam is a fixture, and

is placed at right angles to the upright shaft: but in the machine

represented in the Plate (Fig. XI-1), its attachment is at the lower

extremity of the crane, where it is moveable up and down upon a journal

or bolt. This crane is therefore termed a moveable beam crane. The

moveable property of the beam, in so far as the writer knows, is new,

and possesses the advantage of laying any stone within its range

perpendicularly on its site. This, from the dovetailed form of the

stones at the Bell Rock, rendered it particularly fitted for this work,

to which a crane of the ordinary construction could hardly be said to

be applicable. At the Eddystone Lighthouse this operation was performed

by means of triangular sheers; but, from the greater extent of the Bell

Rock works, and their greater depth in the water, such means must have

rendered the process of building extremely tedious. These cranes were

necessarily immersed at high water, and were retained in their places

by four guys fixed at the top of the upright shaft, and the moveable

jib or beam being lowered down, was secured to an eyebolt batted into

the rock.”

[Illustration:

_PLATE XI._

_MOVEABLE JIB AND BALANCE CRANES._

_W. & A. K. Johnston, Edinburgh._

]

“The ‘balance crane’ (Fig. XI-2) was constructed on a new principle

for building the upper part of the Bell Rock Lighthouse, when the guy

ropes of the moveable beam crane became ‘too taut,’ as sailors express

it, or were too near the perpendicular, thereby rendering the beam

cranes unstable. To remedy this, the balance crane was so arranged as

to be kept in equilibrium by a back weight of cast iron, so adapted

as to counteract the varying load upon the working arm or beam. The

elevation here represented is the same in principle with that used at

the Bell Rock, but differs somewhat in form, agreeably to improvements

made in order to adapt it to the erection of the Carr Rock Beacon.

The upright central column is a tube of cast iron put together in

convenient lengths with flush joints, after the manner of spigot and

faucet, fitted by turning and boring. The centre column of this machine

might have been carried to any suitable or convenient height, by adding

length to length, as the building advanced, without once moving the

foot on which it rested, but at the Bell Rock not more than three

lengths of from six to nine feet were generally in use. A malleable

iron cross head was stepped into the void of the central shaft or

column when the body of the crane was to be elevated. This operation

was accomplished simply by hooking the main ‘purchase’ and ‘traveller’

chains into the eyes of the crosshead, when the machinery of the crane

was employed with great facility as a locomotive power for lifting

itself as each new length of central column was added. The weight of

this crane as used at the Carr Rock did not exceed two tons.”

Life of Robert Stevenson, Civil Engineer · 第 13 / 18 章