Section 141 a drainage course composed of broken stone, gravel or

boiler-plant cinders, ... inches[80] in thickness shall be laid. Broken

stone for this purpose may be of any durable stone crushed to such size

that all will pass through a screen with two inch openings. Crusher-run

material may be used unless it contains an excessive quantity of fine

material. Gravel for the purpose may be any sound durable gravel all of

which will pass through a two inch screen and be retained upon a

one-fourth (¼) inch screen. If cinders are used they must be good

boiler-plant cinders from which the ashes have been screened out. The

cinders must be thoroughly drenched with water at least one week before

they are placed in the sidewalk.[81]

=143.= This drainage material shall be placed on the sub-grade and

properly graded. After grading it shall be thoroughly compacted by

ramming or rolling, and its surface shall be brought to a plane parallel

to and ... inches below the designed surface of the sidewalk, after

which the surface inequalities may be leveled up with screenings or

small gravel.

The bottom of the drainage course shall be connected with the street

drains or sewer inlets by three-inch hard drain pipe at such points, not

more than three hundred feet apart, as will drain all standing water out

of the drainage course.

=144. Concrete, Bottom Course.=—The bottom course of concrete ...[82]

inches in depth, shall be constructed and placed in accordance with

Sections 28, 29, 30, 31, 32, 33, 34, 35 and 36 of these general

specifications, except that the maximum size of the crushed stone shall

not exceed one-half the thickness of the bottom course of concrete and

the concrete shall be uniformly composed of one part Portland cement,

three parts sand and six parts of crushed stone. Its upper surface shall

be brought to a plane parallel to and one inch below the designed

sidewalk surface.

=145. Surface or Finishing Course.=—The surface or finishing course

shall be of concrete, one inch thick, composed of one part Portland

cement, one and one-half parts sand and two and one-half parts of hard,

durable stone, crushed to such sizes that all will pass through a screen

having openings one-half (½) inch square and none will pass through a

screen having openings one-eighth (⅛) inch square.[83] This concrete

shall be made as specified in Sections 28, 29, 30, 31, 32, 33, 34, 35

and 36 except in the particulars named in the preceding paragraph. Care

must be taken to make the mixing very thorough. The quantity of water

used in this concrete shall be just sufficient to make a moderately wet

mixture, and care shall be taken to make the different batches as nearly

as practicable of the same consistency.

The surface concrete shall be spread over the bottom-course concrete

before the latter has begun to set,[84] properly graded, well compacted

by ramming, and its upper surface brought to the true designed plane and

surface of the sidewalk by the use of straight-edges and troweling,[85]

after which the surface shall be lightly gone over with a wire broom or

brush to slightly roughen the surface. The finished plane of the

sidewalk shall have a transverse downward slope toward the street of

one-fourth (¼) inch to one foot of horizontal width. At no place shall

the thickness of the surface-course be less than three-fourths of one

inch. The outer top corners of the sidewalk shall be rounded off with a

suitable tool to a radius of three-fourths (¾) inch.

=146. Forms.=—Substantial and suitable forms of wood or iron shall be

furnished and used by the contractor to support the concrete until it is

hard set, when they shall be removed at his expense.

=147. Expansion Joints.=—After the laying of both courses of concrete is

completed expansion joints at right angles to the sidewalk, and not more

than four (4) feet apart shall be constructed in the sidewalk in the

following manner: the joint will be located by a line on the surface of

the sidewalk and a straight-edged cutting tool one-fourth (¼) inch thick

will be used to cut entirely through both courses of concrete,

accurately along the line marked out, entirely across the sidewalk,

after which a T-shaped trowel or tool shall be used to smooth and

compact the cut surfaces for a depth of one inch, and to round off the

corners of the sidewalk blocks to a radius of one-fourth (¼) inch.[86]

Where the ends of the sidewalk abut against the curbing a clear

expansion joint one and one-fourth (1¼) inches wide shall be left

between the sidewalk and the curb.

=148.= After the concrete laying is completed it shall be protected from

use or injury until the concrete is set hard enough to withstand travel,

and it shall be kept continuously damp for at least five days after the

concrete is laid.

=149. Weather.=—Concrete in sidewalks shall not be laid in freezing

weather nor shall frozen materials be used in the work. Completed work

must be securely protected from frost for at least seven days after the

concrete is laid. Any concrete sidewalk that shall become frozen within

that period of time shall be wholly taken up and replaced with new work,

at the expense of the contractor.

=150. Regrading.=—Directly after the concrete is completed, the forms

removed, and the work inspected by the engineer, the space between the

outer edge of the sidewalk and the street curb shall be excavated or

filled up and dressed to a plane one inch below the top of the sidewalk

and the top of the street curb; and the space on the inner side of the

sidewalk shall be graded to a plane one inch below and parallel to the

surface of the sidewalk for a distance of two feet back from the edge of

the sidewalk and completed with a slope of one and one-half to one to

the natural surface of the ground. Where this regrading requires filling

up the filling material, for a depth of four inches from the surface,

shall be good, rich surface soil.

=151.= Should any defects due to faulty material or workmanship develop

in the sidewalk within one year after the completion of the same the

contractor shall repair or reconstruct all such defective places at his

expense, doing the work in accordance with these specifications.

=152. Measurement and Payment.=—Concrete sidewalk will be measured and

paid for by the square foot of completed sidewalk surface, and the unit

price per square foot shall cover the entire cost of the work, including

grading, drainage work, all material and labor, forms, and the regrading

or dressing up after the completion of the concrete work; except that

the drain pipe used will be paid for per linear foot at the price named

in the contract which price shall cover the cost of furnishing and

putting the pipe in place complete.