(From Handbook of Cost Data, by H. P. Gillette)

───────────────────────────────────┬─────┬─────┬─────┬─────┬─────┬─────

Weight in tons │ 35 │ 45 │ 55 │ 65 │ 75 │ 90

Dipper, cubic yards │ 1¼ │ 1½ │ 1¾ │ 2 │ 2½ │ 3

Coal, tons per 10 hour day │ ¾ │ 1 │ 1¼ │ 1½ │ 2 │ 2¼

Water, gallons per 10 hour day │1500 │2000 │2500 │3000 │4000 │4500

───────────────────────────────────┴─────┴─────┴─────┴─────┴─────┴─────

TABLE 53

PERFORMANCE BY STEAM SHOVELS

──────┬──────┬──────┬───────┬───────────┬──────┬──────────────┬────────

Weight│Dipper│Depth │ Width │ 10–Hour │ Cost │ Authority │Remarks

in │Cubic │ of │of Cut │Performance│ in │ │

Tons │Yards │ Cut, │ │ │Cents,│ │

│ │ Feet │ │ │ per │ │

│ │ │ │ │Cubic │ │

│ │ │ │ │ Yard │ │

──────┼──────┼──────┼───────┼───────────┼──────┼──────────────┼────────

25 │ 1 │ 9 │36 in. │ 85 │ 22.6 │R. T. Dana │ 1

│ │ │ │ │ │ Eng. Rec., │

│ │ │ │ │ │ 69:581 │

25 │ 1 │ 8 │35 in. │ 96 │ 23.5 │ do. │ 2

70 │ 2 │ 26 │16 ft. │ 569 │ 6.7 │ do. │ 3

30 │ 1 │15–18 │60 in. │ 300 │ │A. B. McDaniel│ 4

│ │ │ │ │ │ Excavating │

│ │ │ │ │ │ Machinery │

15 │ ⅝ │ 14 │134 ft.│ 400 │ │Eng. Cont’r, │ 5

│ │ │ │ │ │ 8–25–09 │

│ 8 │ 36 │ Very │16 yd. cars│ │Marion Steam │ 6

│ │ │ wide │ │ │ Shovel Co. │

55 │ │ │ │ 296 │ │H. P. │ 7

│ │ │ │ │ │ Gillette’s │

│ │ │ │ │ │ Cost Data │

65 │ 2¼ │ │ │ 280 │ │ do. │

│ │ │Greater│ 700 │ 30.6 │G. C. D. │ 8

│ │ │than 78│ │ │ Lenth, Eng. │

│ │ │ in. │ │ │ News-Record,│

│ │ │ │ │ │ 85:22 │

──────┴──────┴──────┴───────┴───────────┴──────┴──────────────┴────────

Remarks:

1. One runner at $5.00, one fireman at $2.31, two laborers

at $1.70 each, supplies at $4.50, and interest and

depreciation on 200 days per year, $4.00. Total per

day, $19.21. Material, clay and gravel.

2. Average of 11 jobs with the same shovel.

3. Cost per day, one runner at $5.00, one crane-man at $3.60,

one fireman at $2.00, 7 roller men at $1.50 each, supplies

$9.00 and interest and depreciation on $9000 at 200 days

per year $8.00. Total, $38.10.

4. Hard clay.

5. Stiff clay for the basement of a building in Chicago.

6. Stripping ore. This is a maximum record. The average was

about three hundred and twenty 16 cubic yard cars per day.

7. Blasted mica-schist.

8. General average.

=134. Drag Line and Bucket Excavators.=—A drag line excavator is shown

in Fig. 94. The back of the bucket is attached to a drum on the engine

by means of a cable passing over the wheel in the end of the long boom.

The front of the bucket is attached by another cable directly to another

drum on the engine. In operation the bucket is raised by its rear end

and dropped out to the extremity of the boom. It is then dragged over

the ground towards the machine, digging itself in at the same time. When

filled the bucket is raised by tightening up on the two cables, swung to

one side by means of the movable boom, and dumped.

[Illustration:

FIG. 94.—Drag Line at Work on Trench for Drain Tile.

]

Drag line excavators will perform as much work as steam shovels under

favorable conditions. They are less expensive in first cost and

operation, and are equally reliable but they are not adapted to the more

difficult situations where steam shovels can be used to advantage. Drag

lines are suitable only for relatively wide trenches in material

requiring no bracing, and in a locality where relatively long stretches

of trench can be opened at one time.

The bucket excavator differs from the drag line in that the bucket can

be lifted vertically only and the types of buckets used in the two types

of machine are different. The bucket may be self filling of the

orange-peel or clam-shell type, or a cylindrical container which must be

filled by hand. A drag line can be easily converted into a boom and

bucket excavator. Boom and bucket excavators are well adapted to use in

deep, closely braced trenches and shafts.

=135. Excavation in Quicksand.=[85]—A sand or other granular material in

which there is sufficient upward flow of ground water to lift it, is

known as quicksand. Its most important property, from the viewpoint of

sewer construction, is its inability to support any weight unless the

sand is so confined as to prevent flowing of the sand, or unless the

water is removed from the sand.

Excavation in quicksand is troublesome and expensive and is frequently

dangerous. The material will flow sluggishly as a liquid, it cannot be

pumped easily, and its excavation causes the sides of the trench to fall

in or the bottom to rise. The foundations of nearby structures may be

undermined, causing collapse and serious damage. These conditions may

arise even after the backfilling has been placed unless proper care has

been taken. The greatest safeguard against such dangers is not only to

exercise care in the backfilling to see that it is compactly tamped and

placed, but to leave all sheeting in position after the completion of

the work.

The ordinary method of combating quicksand and in conducting work in wet

trenches is to drive water-tight sheeting 2 or 3 feet below the bottom

of the trench, and to dewater the sand by pumping. When dry it can be

excavated relatively easily. A more primitive but equally successful

method is to throw straw, brickbats, ashes, or other filling material

into the trench in order to hold the excavation once made, or this may

supplement the attempts at pumping, or the wet sand may be bailed out in

buckets. Successful excavation in quicksand requires experience,

resourcefulness. and a careful watch for unexpected developments. The

well points described in Art. 142 are used for dewatering quicksand.

=136. Pumping and Drainage.=—Ground water is to be expected in nearly

all sewer construction and provision should be made for its care. Where

geological conditions are well known or where previous excavations have

been made and it is known that no ground water exists it may be safe to

make no provision for encountering ground water. Where ground water is

to be expected the amount must remain uncertain within certain rather

wide limits until actually encountered.

In order to avoid the necessity for pumping, or working in wet trenches

it is sometimes possible to build the sewer from the low end upwards and

to drain the trench into the new sewer. The wettest trenches are the

most difficult to drain in this manner as the material is usually soft

and the water so laden with sediment as to threaten the clogging of the

sewer. It is undesirable to run water through the pipes until the cement

in the joints has set. This necessitates damming up the trench for a

period which may be so long as to flood the trench or delay the progress

of the work. If it is not possible to drain the trench through the sewer

already constructed the amount of water to be pumped can be reduced by

the use of tight sheeting.

[Illustration:

FIG. 95. Improvised Trench Pump.

]

Pumps for dewatering trenches must be proof against injury by sand, mud,

and other solids in the water. For this purpose pumps with wide passages

and without valves or packed joints are desirable. The types of pumps

used are: simple flap valve pumps improvised on the job, diaphragm

pumps, jet pumps, steam vacuum pumps, centrifugal pumps, and

reciprocating pumps. All are of the simplest of their type and little

attention is paid to the economy of operation because of the temporary

nature of their service.

=137. Trench Pump.=—A simple pump which can be improvised on the job is

shown in section in Fig. 95. Its capacity is about 20 gallons per minute

but its operation is backaching work. It is inexpensive, quickly put

together and may be a help in an emergency. It is to be noted that the

passages are large and straight, that there are no packed joints, and

that the velocity of flow is so small that it is not liable to clogging

by picking up small objects.

[Illustration:

FIG. 96.—Diaphragm Pump

Courtesy, Edson Manufacturing Co.

]

=138. Diaphragm Pump.=—The type of pump shown in Fig. 96 is the most

common in use for draining small quantities of water from excavations.

It is known as the diaphragm pump from the large rubber diaphragm on

which the operation depends. The pump is made of a short cast-iron

cylinder, divided by the rubber diaphragm or disk to the center of which

the handle is connected. The valve is shown at the center of the disk.

As the diaphragm is lifted the valve remains closed, creating a partial

vacuum in the suction pipe and at the same time discharging the water

which passed through the valve on the previous down stroke. When the

valve is lowered the foot valve on the suction pipe closes, holding the

water in place, and the valve in the pump opens allowing the water to

flow out on top of the disk to be discharged on the next up stroke.

Table 54 shows the capacities of some diaphragm pumps as rated by the

manufacturers. The smaller sizes are the more frequently used and are

equipped with a 3–inch suction hose with strainer and foot valve. They

are not adapted to suction lifts over 10 to 12 feet. Where greater lifts

are necessary one pump may discharge into a tub in which the foot valve

of a higher pump is submerged.

TABLE 54

CAPACITIES OF DIAPHRAGM PUMPS

─────────────────┬─────────────────┬─────────────────┬─────────────────

Diameter of │ Diameter of │Length of Stroke │ Capacity per

Cylinder, Inches │ Suction, Inches │ in Inches │ Stroke, Gallons

─────────────────┼─────────────────┼─────────────────┼─────────────────

6│ 3│ 4│ 0.49

8½│ 4│ 6│ 1.47

9[86]│ 2½│ │ 0.75

12½[86]│ 3│ │ 1.25

│ Power driven by 1 horse-power │

12½[86]│ engine │ 0.58[87]

─────────────────┴───────────────────────────────────┴─────────────────

[Illustration:

FIG. 97.—McGowan Steam Jet Pump.

Courtesy, The John H. McGowan Co.

]

=139. Jet Pump.=—The simplicity of the parts of the jet pump is shown in

Fig. 97. It has a distinct advantage over pumps containing valves and

moving parts in that there are no obstructions offered to the passage of

solids as well as liquids through the pump. It is not economical in the

use of steam, however. It operates by means of a steam jet entering a

pipe at high velocity through a nozzle. This action causes a vacuum

which will lift water from 6 to 10 feet. The lower the suction lift,

however, the greater the efficiency of the work. The sizes and

capacities of jet pumps as manufactured by the J. H. McGowan Co. are

shown in Table 55.

TABLE 55

CAPACITIES OF JET PUMPS

(J. H. McGowan Co.)

──────────────┬─────────────┬─────────────┬─────────────┬──────────────

Size of Pump │ │ │ Capacity, │ Approximate

and Suction │ Discharge │ Steam Pipe, │ Gallons per │ Horse-power

Pipe, Inches │Pipe, Inches │ Inches │ Minute │ Required

──────────────┼─────────────┼─────────────┼─────────────┼──────────────

¾│ ½│ ⅜│ 8│ 2

1│ ¾│ ½│ 15│ 3

1¼│ 1│ ½│ 20│ 4

1½│ 1¼│ ¾│ 30│ 6

2│ 1½│ ¾│ 40│ 8

2½│ 2│ 1│ 50│ 10

3│ 2½│ 1│ 60│ 15

4│ 3½│ 1¼│ 85│ 25

──────────────┴─────────────┴─────────────┴─────────────┴──────────────

=140. Steam Vacuum Pumps.=—This type of pump depends on the condensation

of steam in a closed chamber to create a vacuum which lifts water into

the chamber previously occupied by the steam and from which the water is

ejected by the admission of more steam. The best known pumps of this

type are the Pulsometer, manufactured by the Pulsometer Steam Pump Co.,

the Emerson, manufactured by the Emerson Pump and Valve Co., and the Nye

Pump, manufactured by the Nye Steam Pump and Machinery Co.

[Illustration:

FIG. 98.—Pulsometer Steam Vacuum Pump.

]

A section of a Pulsometer is shown in Fig. 98. It consists of two

bottle-shaped chambers _A_ and _B_ with their necks communicating at the

top and each opening into the outlet chamber _O_ through a check valve.

Steam is admitted at the top and enters chamber _A_ or _B_ according to

the position of the steam valve _C_ as shown. This steam valve is a ball

which is free to roll either to the right or left and forms a

steam-tight joint with whichever seat it rests upon. In normal operation

chamber _A_ would be filled with water as the steam enters the cylinder.

At the same time a check valve at the top opens to admit a small

quantity of air which forms a cushion insulating the steam from the

water, reduces the condensation of the steam, and serves as a cushion

for the incoming water on the opposite stroke. The pressure of the steam

depresses the surface of the water without agitation and forces the

water through the check valve _F_ into the discharge chamber _O_. When

the water falls to the level of the discharge chamber the even surface

is broken up and the intimate contact of the steam and water condenses

the former instantaneously. This forms a vacuum in chamber _A_ which,

assisted by a slight upward pressure in chamber _B_ caused by the

incoming water, immediately pulls the ball _C_ over to the other seat

and directs the steam into chamber _B_. The vacuum in chamber _A_ now

draws up a new charge of water through the suction pipe into the

chamber.

[Illustration:

FIG. 99.—Emerson Steam Vacuum Pump.

]

A section of the Emerson pump is shown in Fig. 99. The pump consists of

two vertical cylinders _B_ and _C_. Each chamber has a suction valve _L_

at the bottom, opening upward from a common chamber from which the

discharge pipe _U_ extends. On the top of each chamber is a baffle plate

_G_ which operates to distribute the steam evenly to the two chambers

and to prevent it from agitating the surface of the water in the

chambers. A condenser nozzle _F_ is connected with the bottom of the

opposite chamber by a pipe into which a check valve opens upward. As the

pressure in the chamber alternates water will be injected through _F_

into the opposite chamber and condense the steam therein, promptly

forming a vacuum. An air valve _P_ admits a small quantity of air while

the chamber is filling with water, the air acting as an insulating

cushion as in the Pulsometer. Valve _O_, just above the top connection

_S_ is used to regulate the amount of steam that enters the pump. The

top connection _S_ has two ports, one leading to each chamber. An

oscillating valve enclosed in it admits the steam through these ports to

the two chambers alternately. This valve is driven by a small

three-cylinder engine, the crank shaft of which extends into the top

connection in the center of the bearing on which the valve oscillates. A

positive geared connection is made between the valve and the engine and

so arranged that the engine will run faster than the valve.

The action of these pumps consists of alternately filling and emptying

the two chambers. They will continue operation without attention or

lubrication so long as the steam is turned on. In view of the simplicity

of their operation and make-up, their ability to handle liquids heavily

charged with solids, and their reasonable steam consumption these pumps

are widely used for pumping water in construction work. They have an

added advantage that no foundation or setting is required for them as

they can be hung by a chain from any available support.

These pumps are manufactured in sizes varying from 25 to 2500 gallons

per minute at a 25–foot head, and with a steam consumption of about 150

pounds per horse-power hour. They reduce about 4 per cent in capacity

for each 10 feet of additional lift. They will operate satisfactorily

between heads of 5 to 150 feet, with a suction lift not to exceed 15

feet. Lower suction lifts are desirable and the best operation is

obtained when the pump is partly submerged. The steam pressure should be

balanced against the total head. It varies from 50 to 75 pounds for

lifts up to 50 feet, and increases proportionally for higher lifts. The

dryer the steam the lower the necessary boiler pressure.

=141. Centrifugal and Reciprocating Pumps.=—The details of these pumps,

their adaptability to various conditions, and their capacities are given

in Chapter VII. The centrifugal is better adapted to trench pumping as

it is not so affected by water containing sand and grit, but for clear

water, high suction lifts and fairly permanent installations,

reciprocating pumps can be used with satisfaction.

=142. Well Points.=—In dewatering quicksand a method frequently attended

with success is to drive a number of well points into the sand and

connect them all to a single pump. Figure 100 shows a well point system

used on sewer work in Indiana. The well points are 3 feet apart and are

connected to a 2½-inch header which in turn is connected to six Nye

pumps, each with a capacity of 200 gallons per minute for a lift of 50

feet. The number and size of well points and pumps to use will depend on

conditions as met on the job. On a piece of work in Atlantic City[88]

the equipment consisted of two complete outfits each comprising one

hundred 1½ inch by 36–inch No. 60 well points, one hundred 6–foot

lengths of rubber hose, about 600 feet of suction main, one hundred

valved T connections, and a 7 × 8–inch Gould Triplex Pump with a

capacity of 200 gallons per minute, belted to a 7½ horse-power motor.

[Illustration:

FIG. 100.—Well Points Pumped by Nye Steam Vacuum Pump.

]

=143. Rock Excavation.=—A common definition of rock used in

specifications is: whenever the word Rock is used as the name of an

excavated material it shall mean the ledge material removed or to be

removed properly by channeling, wedging, barring, or blasting; boulders

having a volume of 9 (this volume may be varied) cubic feet or more, and

any excavated masonry. No soft disintegrated rock which can be removed

with a pick, nor loose shale, nor previously blasted material, nor

material which may have fallen into the trench will be measured or

allowed as rock.

Channeling consists in cutting long narrow channels in the rock to free

the sides of large blocks of stone. The block is then loosened by

driving in wedges or it is pried loose with bars. It is a method used

more frequently in quarrying than in trench excavation where it is not

necessary to preserve the stone intact. In blasting, a hole is drilled

in the rock, and is loaded with an explosive which when fired shatters

the rock and loosens it from its position.

[Illustration:

FIG. 101.—Plug and Feathers for Splitting Rock.

]

In drilling rock by hand the drill is manipulated by one man who holds

it and turns it in the hole with one hand while striking it with a

hammer weighing about 4 pounds held in the other hand, or one man may

hold and turn the drill while one or two others strike it with heavier

hammers. In churn drilling a heavy drill is raised and dropped in the

hole, the force of the blow developing from the weight of the falling

drill. Hand drills are steel bars of a length suitable for the depth of

the hole, with the cutting edge widened and sharpened to an angle as

sharp as can be used without breaking. The drill bar is usually about

⅛th of an inch smaller than the diameter of the face of the drill.

Wedges used are called plugs and feathers. They are shown in Fig. 101

which shows also the method of their use. The feathers are wedges with

one round and one flat face on which the flat faces of the plug slide.

=144. Power Drilling.=—In power drilling the drill is driven by a

reciprocating machine which either strikes and turns the drill in the

hole, or lifts and turns it as in churn drilling, or the drill may be

driven by a rotary machine which is revolved by compressed air, steam,

or electricity. There are many different types of machines suitable for

drilling in the different classes of material encountered and for

utilizing the various forms of power available.

A jack hammer drill is shown in Fig. 102. In its lightest form the drill

weighs about 20 pounds and is capable of drilling ⅞-inch holes to a

depth of 4 feet. Heavier machines are available for drilling larger and

deeper holes. The same machine can be adapted to the use of steam or

compressed air. When in use the point of the drill is placed against the

rock and a pressure on the handle opens a valve admitting air or steam.

The piston is caused to reciprocate in the cylinder, striking the head

of the drill at each stroke. The drill is revolved in the hole by hand

or by a mechanism in the machine. A hollow drill can be used by means of

which the operator admits air or steam to the hole, thus blowing it out

and keeping it clean. These machines have the advantage of small size,

portability and simplicity. They can be easily and quickly set up and

the drills can be changed rapidly. Their undesirable features are the

vibration transmitted to the operator and the dust raised in the trench.

[Illustration:

FIG. 102.—Jack Hammer Rock Drill.

]

[Illustration:

FIG. 103.—Tripod Drill.

]

A type of drill heavier and larger than the jack hammer drill is shown

in Fig. 103. It requires some form of support such as a tripod, or in

tunnel work it can be braced against the roof or sides. Some data on

steam and air drills are given in Table 56. The effect of the length of

the transmission pipe, temperature of the outside air, pressure at the

boiler or compressor, etc., will have a marked effect on the amount of

steam or air to be delivered to the drill. Compressed air is affected

more than steam by these outside factors, but it has an advantage in

that as it loses in pressure it increases in volume so that the loss of

power is not so marked. Gillette states:

We may assume that a cubic foot of steam will do practically the

same work in a drill as a cubic foot of compressed air at the same

pressure, because neither the steam nor the air acts expansively

to any great extent in a drill cylinder, due to the late cut-off.

This being so ... one pound of steam is equivalent to nearly 30

cubic feet of free air ... all at the same pressure of 75 pounds

per square inch. If a drill consumes at the rate of 100 cubic feet

of free air per minute ... it would therefore consume 240 pounds

of steam (at 75 pounds pressure) per hour.... Where not more than

three or four drills are to be operated, probably no power can

equal compressed air generated by gasoline. It will require 12

horse-power to compress air for each drill, hence 1½ gallons of

gasoline will be required per hour per drill while actually

drilling.

TABLE 56

DATA ON ROCK DRILLS

(From H. P. Gillette)

───────────────────────────────────┬─────┬─────┬─────┬─────┬─────┬─────

Diameter of cylinder in inches │ 2¼│ 2½│ 2¾│ 3⅛│ 3¼│ 3⅜

Length of stroke in inches │ 5│ 6│ 6½│ 6⅝│ 6⅝│ 7¼

Length of drill from end of crank │ │ │ │ │ │

to end of piston │ 36│ 43│ 50│ 50│ 50│ 52

Depth of hole drilled without │ │ │ │ │ │

change of bit, inches │ 15│ 20│ 24│ 24│ 24│ 24

Diameter of supply inlet. Standard │ │ │ │ │ │

pipe, inches │ ¾│ ¾│ ¾│ 1│ 1│ 1¼

Approximate strokes per minute with│ │ │ │ │ │

60 pound pressure at the drill │ 500│ 450│ 375│ 350│ 325│ 300

Depth of vertical hole each machine│ │ │ │ │ │

will drill easily, feet │ 6│ 8│ 10│ 14│ 16│ 20

Diameter of holes drilled, inches │ ¾ to 1½ as desired

Diameter of octagon steel, inches │ ¾ to│ ⅞ to│ 1 to│1⅛ to│1⅛ to│1¼ to

│ ⅞│ 1│ 1⅛│ 1¼│ 1¼│ 1⅜

Best size of boiler to give plenty │ │ │ │ │ │

of steam at high pressure, │ │ │ │ │ │

horse-power │ 6│ 8│ 8│ 9│ 10│ 12

Best size of supply pipe to carry │ │ │ │ │ │

steam 100 to 200 feet, inches │ ¾│ ¾│ ¾│ 1│ 1│ 1¼

Weight of drill unmounted, with │ │ │ │ │ │

wrenches and fittings, hot boxed,│ │ │ │ │ │

pounds │ 128│ 190│ 265│ 315│ 385│ 390

Weight of tripod, without weights, │ │ │ │ │ │

not boxed, pounds │ 80│ 160│ 160│ 160│ 210│ 275

Weight of holding down weights, not│ │ │ │ │ │

boxed, pounds │ 120│ 270│ 270│ 285│ 330│ 375

Cubic feet of free air per minute │ │ │ │ │ │

required to run one drill at 100 │ │ │ │ │ │

pounds │ 92│ 104│ 126│ 146│ 154│ 160

───────────────────────────────────┴─────┴─────┴─────┴─────┴─────┴─────

For more than one drill, multiply the value in the above line by the

following factors: For 2 drills, 1.8; 5 by 4.1; 10 by 7.1; 15 by 9.5;

20 by 11.7; 30 by 15.8; 40 by 21.4; 70 by 33.2.

Since gasoline air compressors are self regulating, when the drill

is not using air very little gasoline is burned by the gasoline

engine driving the compressor. A gasoline compressor possesses

other very important economic advantages over a small steam-driven

plant. First, there is the saving in wages of firemen and second,

there is the saving in hauling and pumping of water and the

hauling of fuel. The cost of gasoline is often less than the cost

of coal for operating a small plant.

An electric drill[89] operated on the principle of the solenoid does

away with motor, valves, pipes, vapor, freezing, and other difficulties

attendant on the use of steam or air.

The rates of drilling in different classes of rock are shown in Table

57. Frequent changes of drills and relocation of tripods will materially

reduce the performance of a drill, for as much as 45 minutes may be lost

in making a new set up. In this the jack hammer drills show their

advantage as no time is lost in a set up.

TABLE 57

RATES OF ROCK DRILLING

Rates in Feet per Ten-hour Shift. Vertical Holes 10–20 Feet Deep.

(From Gillette)

Hard Adirondack granite 48

Maine and Massachusetts granite 45–50

Mica-schist of New York City. Possible 60–70

Mica-schist of New York City. Average 40–50

Hard, Hudson River trap rock 40

Soft red sand stone of Northern New Jersey 90

Hard limestone near Rochester, N. Y 70

Limestone of Chicago Drainage Canal 70–80

Douglass, Indiana, syenite. Difficult set ups 36

Canadian granite on Grand Trunk R. R 30

Windmill point, Ontario limestone:

3⅝-inch drills 75

2¾-inch drills 60

2¼-inch drills 37

=145. Steam or Air for Power=.—The choice between steam or air is

dependent on the conditions of the work. Steam is undesirable in tunnels

on account of the heat produced. In open cut work it is at a

disadvantage because of the loss of power due to radiation from the hose

or pipe. The life of the hose is not so long as when air is used,

escaping steam causes clouds of vapor which obscure the work, and

serious burns may occur due to hot water thrown from the exhaust. It is

advantageous since leaks may be easily discovered and remedied, it

requires less machinery than air, and it is sometimes less expensive.

With compressed air, gasoline or electric motors can be used for

operating the compressors.

TABLE 58

ROCK BLASTING

(From Gillette)

────────────────────┬────────────────────┬─────────┬─────────┬─────────

Character of │Powder Used per Hole│ │Distance │Distance

Material │ │Depth of │ Back of │ Hole to

│ │ Hole, │ Face, │ Hole,

│ │ Feet │ feet │ feet

────────────────────┼────────────────────┼─────────┼─────────┼─────────

Limestone of Chicago│40 per cent dynamite│ │ │

Drainage Canal │ │ 12│ 8│ 8

Sandstone │200 pounds black │ │ │

│ powder │ 20│ 18│ 14

Granite │2 pounds 60 per cent│ │ │

│ dynamite │ 12│ 1½│ 4½ to 5

Pit mining, │ │ │ │

Treadwell, Mine, │ │ │ │

Alaska │ │ 12│ 2½│ 6

────────────────────┴────────────────────┴─────────┴─────────┴─────────

=146. Depth of Drill Hole.=—The depth of the hole is dependent on the

character of the work. The deepest holes can be used in open cut work

where the shattered rock is to be removed by steam shovel. The face can

be made 10 to 15 feet high. The depth of the hole in center cut tunnel

facings are from 6 to 10 or even 12 feet. In the bench the depth is

equal to the height of the bench. In narrow trenches where the rock is

to be removed by derrick or thrown into a bucket by hand, the hole

should be sufficiently deep to shatter the rock to a depth of at least 6

inches below the finished sewer. Frequently shooting to this depth at

one shot cannot be done due to the built up condition of the

neighborhood or other local factors. The depth of the hole in trench

work should not much exceed the distance between holes. Deep holes are

usually desirable as a matter of economy in saving frequent set ups, but

the holes cannot be made much over 20 feet in depth without increasing

the friction on the drill to a prohibitive amount.

=147. Diameter of Drill Hole.=—The diameter of the hole should be such

as to take the desired size of explosive cartridge. The common sizes of

dynamite cartridges are from ⅞ inch to 2 inches in diameter. In

drilling, the diameter of the hole is reduced about one-eighth of an

inch at a time as the drill begins to stick. This reduction should be

allowed for, and experience is the best guide for the size of the hole

at the start. In general the softer or more faulty or seamy the rock,

the more frequent the necessary reductions in size of bit.[90] For hard

homogeneous rock the holes can be drilled 10 feet or more without

changing the size of the drill bit.

=148. Spacing of Drill Holes.=—The spacing of holes in open cut

excavation is commonly equal to the depth of the hole. The character of

the material being excavated has much to do with the spacing of the

holes. The spacing, diameter and depth of holes used on some jobs is

shown in Table 58. Gillette states:

It is obviously impossible to lay down any hard and fast rule for

drill holes. In stratified rock that is friable, and in traps that

are full of natural joints and seams, it is often possible to

space the holes a distance apart somewhat greater than their

depth, and still break the rock to comparatively small sizes upon

blasting. In tough granite, gneiss, syenite, and in trap where

joints are few and far between, the holes may have to be spaced 3

to 8 feet apart regardless of their depth for with wider spacing

the blocks thrown down will be too large to handle with ordinary

appliances. Since in shallow excavations the holes can seldom be

much further apart than one to one and one-half times their depth

we see that the cost of drilling per cubic yard increases very

rapidly the shallower the excavation. Furthermore the cost of

drilling a foot of hole is much increased where frequent shifting

of the drill tripod is necessary.

The common practice in placing drill holes is to put down holes in

pairs, one hole on each side of the proposed trench; and if the

trench is wide one or more holes are drilled between these two

side holes[91] but in narrow trench work, such as for a 12–inch

pipe, one hole in the middle of the trench will usually prove

sufficient.

The holes are spaced about 3 feet apart longitudinally. After the holes

have been completed they should be plugged to keep out dirt and water.

SHEETING AND BRACING

=149. Purposes and Types.=—Sheeting and bracing are used in trenching to

prevent caving of the banks and to prevent or retard the entrance of

ground water. The different methods of placing wooden sheeting are

called stay bracing, skeleton sheeting, poling boards, box sheeting, and

vertical sheeting. Steel sheeting is usually driven to secure

water-tightness and if braced the bracing is similar to the form used

for vertical wooden sheeting.

=150. Stay Bracing.=—This consists of boards placed vertically against

the sides of the trench and held in position by cross braces which are

wedged in place. The purpose of the board against the side of the trench

is to prevent the cross brace from sinking into the earth. The boards

should be from 1½ × 4 inches to 2 × 6 inches and 3 to 4 feet long. The

cross braces should not be less than 2 × 4 inches for the narrowest

trenches and larger sizes should be used for wider trenches. The spacing

between the cross braces is dependent on the character of the trench and

the judgment of the foreman. Stay bracing is used as a precautionary

measure in relatively shallow trenches with sides of stiff clay or other

cohesive material. It should not be used where a tendency towards caving

is pronounced. Stay bracing is dangerous in trenches where sliding has

commenced as it gives a false sense of security. The boards and cross

braces are placed in position after the trench has been excavated.

=151. Skeleton Sheeting.=—This consists of rangers and braces with a

piece of vertical sheeting behind each brace. A section of skeleton

sheeting is shown in Fig. 104 with the names of the different pieces

marked on them. This form of sheeting is used in uncertain soils which

apparently require only slight support, but may show a tendency to cave

with but little warning. When the warning is given vertical sheeting can

be quickly driven behind the rangers and additional braces placed if

necessary. The sizes of pieces, spacing and method of placing should be

the same as for complete vertical sheeting in order that this may be

placed if necessary.

=152. Poling Boards.=—These are planks placed vertically against the

sides of the trench and held in place by rangers and braces. They differ

from vertical sheeting in that the poling board is about 3 or 4 feet

long. It is placed after the trench has been excavated; not driven down

with the excavation like vertical sheeting. An arrangement of poling

boards is shown in Fig. 105. This type of support is used in material

that will stand unsupported for from 3 to 4 feet in height. Its

advantages lie in that no driving is necessary, thus saving the trench

from jarring; no sheeting is sticking above the sides of the trench to

interfere with the excavation; and only short planks are necessary.

[Illustration:

FIG. 104.—Skeleton Sheeting.

]

[Illustration:

FIG. 105.—Poling Boards.

Showing Different Types of Cross Bracing.

]

The method of placing poling boards is as follows: Excavate the trench

as far as the cohesion of the bank will permit. Poling boards, 1½ inch

to 2 inch planks, 6 inches or more in width, are then stood on end at

the desired intervals along each side of the trench for the length of

one ranger. The poling boards may be held in place by one or two

rangers. Two are safer than one but may not always be necessary. If one

ranger is to be used it is placed at the center of the poling board.

After the poling boards are in position the rangers are laid in the

trench and the cross braces are cut to fit. If wedges are to be used for

tightening the cross braces, the cross braces are cut about 2 inches

short. If jacks are to be used the braces are cut short enough to

accommodate the jacks when closed, or adjustable trench braces may be

used as shown in Fig. 106. The use of extension braces saves the labor

of fitting wooden braces. With everything in readiness in the trench,

the cross brace is pressed against the ranger which is thus held in

place. The wedge or jack is then tightened holding the poling boards and

cross brace in position.

[Illustration:

FIG. 106.—Box Sheeting.

Showing Different Types of Cross Bracing.

]

=153. Box Sheeting.=—Box sheeting is composed of horizontal planks held

in position against the sides of the trench by vertical pieces supported

by braces extending across the trench. The arrangement of planks and

braces for box sheeting is shown in Fig. 106. This type of sheeting is

used in material not sufficiently cohesive to permit the use of poling

boards, and under such conditions that it is inadvisable to use vertical

sheeting which protrudes above the sides of the trench while being

driven. This sheeting is put in position as the trench is excavated. No

more of the excavation than the width of three or four planks need be

unsupported at any one time. In placing the sheeting the trench is

excavated for a depth of 12 to 24 inches. Three or four planks are then

placed against the sides of the trench and are caught in position by a

vertical brace which is in turn supported by a horizontal cross brace.

[Illustration:

FIG. 107.—Vertical Sheeting.

]

=154. Vertical Sheeting.=—This is the most complete and the strongest of

the methods for sheeting a trench. It consists of a system of rangers

and cross braces so arranged as to support a solid wall of vertical

planks against the sides of the trench. An arrangement of complete

vertical sheeting is shown in Fig. 107. This type can be made nearly

water-tight by the use of matched boards, Wakefield piling, steel

piling, etc. Wakefield piling is made up of three planks of the same

width and usually the same thickness. They are nailed together so that

the two outside planks protrude beyond the inside one on one side, and

the inside one protrudes beyond the two outside ones on the other side

as shown in Fig. 108. The protruding inside plank forms a tongue which

fits into the groove formed by the protruding outside planks of the

adjacent pile.

[Illustration:

FIG. 108.—Wakefield Sheet Piling.

]

[Illustration:

FIG. 109. Section through Malleable Steel Driving Cap.

]

In placing vertical sheeting the trench is excavated as far as it is

safe below the surface. Blocks of the same thickness as the sheeting are

then placed against the bank at the middle and at the ends of two

rangers on opposite sides of the trench. The ranger rest against blocks,

and are held away from the sides of the trench by them. Cross braces are

next tightened into position opposite the blocks to hold the rangers in

place. After the skeleton sheeting is in place the planks forming the

vertical sheeting are put in position with a chisel edge cut on the

lower end of the plank, with the flat side against the bank. The planks

should be driven with a maul, the edge of the plank following closely

behind the excavation. In relatively dry work the driving of the plank

is facilitated by excavating beneath the edge as it is driven. The upper

end of the sheeting should be protected by a malleable steel or iron cap

to prevent brooming of the lumber. A cap is shown in Fig. 109. A sledge

hammer may be used for driving when the lumber is protected. If the

sheeting is to start at the surface and is to be driven by hand, the

first length should not exceed 4 feet unless a platform is erected for

the driver. Succeeding lengths may be longer, the driver standing on

planks supported on the cross braces in the trench. Steam hammers and

pile drivers are sometimes used for driving sheeting.

The framework of the sheeting should be placed with a cross brace for

each end of each ranger and a cross brace for the middle of each ranger.

If the ends of two rangers rest on the same cross brace an accident

displacing one ranger will be passed on to the next and might cause a

progressive collapse of a length of trench, whereas the movement of an

independently supported ranger should have no effect on another ranger.

The cross braces should have horizontal cleats nailed on top of them as

shown in Fig. 107 to prevent the braces from being knocked out of place

by falling objects. In driving vertical sheeting a vacant place will be

left behind each cross brace corresponding to the original block placed

to hold the ranger away from the bank. This is an undesirable feature in

the use of vertical sheeting. It is ordinarily remedied by slipping in

planks the width of the slot and wedging or nailing them against the

convenient cross bracing. In extremely wet trenches, after all other

pieces of vertical sheeting are in place, the original cleat behind the

cross brace can be knocked out and a piece of sheeting slipped into this

opening and driven. Care must be taken in this event not to drive the

rangers down when driving the sheeting. If the bracing begins to drop,

it should be supported by vertical pieces between the rangers and

resting on a sill at the bottom of the trench.

[Illustration:

FIG. 110.—Steel Clamp for Pulling Wood Sheeting.

]

=155. Pulling Wood Sheeting.=—Wood sheeting is pulled after the

completion of the trench by a device shown in Fig. 110. In wet trenches

where the removal of the sheeting would permit a movement of the banks,

resulting in danger to the sewer or other structures, the sheeting

should be left in place in the trench. If sufficient saving can be made

the sheeting is cut off in the trench immediately above the danger line,

usually the ground water line. The cutting is done with an axe or by a

power driven saw devised for the purpose.

=156. Earth Pressures.[92]=—The various theories of earth pressure are

so conflicting in their conclusions as to be confusing. Rankine’s

theory, the most frequently used, assumes that the pressure increases

with the depth, whereas Meem’s theory[93] leads to an opposite

conclusion. The discussion following Meem’s article is very

illuminating. It indicates that no matter how good the theory, practical

experience together with the use of generous sizes and close spacing are

the best guides for bracing trenches and coffer dams. All are not

possessed with the desired practical experience and some basis on which

to commence work is essential. Another factor affecting computations of

sizes based on theory is the tendency in practice to use the same size

material for rangers and braces on any one job for all except very deep

trenches and other special cases. Occasionally where there is an

independent brace for each end of each ranger, the brace is made

thinner, but is of the same depth as the ranger.

The application of Rankine’s theory of earth pressure to the computation

of the sizes of rangers and braces will be shown. His formula for the

active earth pressure against a retaining wall is:

_P_ = _wh_ cosθ (cos θ − √(cos^2 θ − cos^2 φ))⁄(cos θ + √(cos^2 θ −

cos^2 φ))

in which _w_ = the weight of earth in pounds per cubic foot;

_h_ = depth in feet at point at which pressure is to be

determined;

θ = the angle of surcharge, or the angle which the surface

makes with the horizontal;

φ = the angle of repose of the earth. Usually taken as

33°–41′ = 1½ horizontal to 1 vertical;

_P_ = the intensity of pressure in pounds per square foot on

a vertical plane in a direction parallel to the

surface of the ground.

In studying the pressures for trenches the surface of the ground will be

assumed as horizontal and the formula reduces to

_P_ = (1 − sin φ)⁄(1 + sin φ)_wh_.

=157. Design of Sheeting and Bracing=.—The trench shown in Fig. 111 is

assumed to be constructed in moist sand weighing 110 pounds per cubic

foot, with an angle of repose of 30 degrees. The material used for

sheeting and bracing is yellow pine. The steps taken in the design of

the sheeting and bracing for this trench are as follows:

[Illustration:

FIG. 111.—Diagram for the Design of Wood Sheeting.

]

1. _Earth Pressure._—Substituting the units given in the data, in

Rankine’s formula for earth pressures,

_P_ = 36.7_h_.

Because the earth has been freshly cut and will not be kept open long

enough to break up the cohesiveness of the banks it is customary to

reduce the assumed pressure by dividing by 2, 3, or 4, according to the

natural cohesiveness of the material. The cohesiveness of sand is not

great, therefore the pressure will be assumed as one-half of the amount

given by the formula, or

_p_ = 18_h_.

2. _Thickness of Sheeting and Spacing of Rangers._—It is desirable to

use the same thickness of sheeting throughout the depth of the trench.

Computations should therefore be commenced at the bottom of the trench

where the pressures are the greatest and the thickest sheeting will be

required. It is necessary to determine by trial a spacing for the

rangers and a thickness of sheeting so that the sheeting is stressed to

its full working strength. Having determined the thickness of the

sheeting at the bottom, the remainder of the computations consists in

determining the spacing of the rangers.

In the example the lower ranger will be assumed as 3 feet from the

bottom of the trench and the distance to the next ranger as 4 feet.

The intensity of pressure at 22 feet 9 inches is 409.5 pounds per

square foot.

The intensity of pressure at 26 feet 9 inches is 481.5 pounds per

square foot.

The distribution of pressures is shown by the diagram on Fig. 111. The

maximum bending moment is slightly below the point midway between the

rangers and for a 12–inch strip is 10,500 inch-pounds.

Assuming 3 inch sheeting the maximum fiber stress is:

_f_ = _Mc_⁄_I_ = (10,400 × 1.5 × 12)⁄12 × 27 = 568 pounds per square

inch.

The working strength of yellow pine as given in Table 59, is 1200 pounds

per square inch. Thinner sheeting should therefore be used.

TABLE 59

WORKING UNIT STRESSES FOR TIMBER

The most used value in the Building Codes of Baltimore, Boston,

Cincinnati, Chicago, District of Columbia, and New York City

─────────────┬────────┬───────────┬───────────┬──────────┬──────┬──────

Wood │ │ │ │ │Shear │Shear

│ │ │ │ │ With │Across

│ │ │Compression│Transverse│Grain,│Grain,

│Tension,│Compression│ Across │ Bending, │ lb. │ lb.

│lb. sq. │With Grain,│Grain, lb. │ lb. sq. │ sq. │ sq.

│ in. │lb. sq. in.│ sq. in. │ in. │ in. │ in.

─────────────┼────────┼───────────┼───────────┼──────────┼──────┼──────

Yellow pine │ 1200│ 1000│ 600│ 1200│ 70│ 500

White pine │ 800│ 800│ 400│ 800│ 40│ 250

Spruce and │ │ │ │ │ │

Va. pine. │ 800│ 800│ 400│ 800│ 50│ 320

Oak │ 1000│ 900│ 800│ 1000│ 100│ 600

Hemlock │ 600│ 500│ 500│ 600│ 40│ 275

Chestnut │ 600│ 500│ 1000│ 800│ │ 150

Locust │ │ 1200│ 1000│ 1200│ 100│ 720

─────────────┴────────┴───────────┴───────────┴──────────┴──────┴──────

As published in American Civil Engineers Pocket Book.

Assuming 2–inch sheeting, the fiber stress is 1,300 pounds per square

inch. This stress is too large. By reducing the ranger spacing slightly

the stress can be brought within the required limits.

Assuming a ranger spacing of 3 feet 9 inches the depth to the upper

ranger is changed to 23 feet and the maximum stress in the 2–inch

sheeting becomes 1,140 pounds per square inch, a satisfactory result.

The results for the computations for the other ranger spacings are shown

in Table 60. The spacing of the rangers at the sheeting junctions is

controlled by convenience and is not computed so long as it is obviously

safe.

3. _Size of Rangers._—The rangers will be assumed as 16 feet long with

two end cross braces and one intermediate cross brace for each ranger.

Starting as before at the bottom of the trench.

The area of the panel below the ranger and between cross

braces is 24 square feet.

The average intensity of pressure is 28.25 × 18 = 508.5

pounds per square inch.

The load transmitted to the ranger is 6,000 pounds.

Similarly the load transmitted to the ranger from the

panel above is 6,890 pounds.

The total distributed load on the ranger is 12,890 pounds.

If _b_ is the vertical dimension of the ranger and _d_ is the horizontal

dimension in inches, then from the beam theory, using _f_ as 1,200

pounds per square inch, _bd_^2 = _M_⁄200, in which _M_ is expressed in

inch-pounds. The maximum bending moment is

(_Wl_)⁄8 = 12,200 × 8 × 12⁄8 = 155,000 inch-pounds

Therefore, _bd_^2 = 775.

An 8 × 10 inch beam will fulfill the conditions closely. Substituting

these dimensions in the beam formula

_f_ = (_Mc_)⁄_I_ = (155,000 × 5 × 12)⁄8 × 1000

= 1,160 pounds per square inch tension in outer fiber. The results of

the computations for other rangers are shown in Table 60.

4. _Size of Cross Braces._—The cross braces act as columns. The

dimensions of the cross braces are determined by trial in such a manner

that the vertical dimension of the brace is equal to the vertical

dimension of the ranger and the compressive stress in pounds per square

inch is computed from the expression,

_S_ ⪙ _S__{1}(1 − _l_⁄(60_d_)),[94]

TABLE 60

COMPUTATIONS FOR SHEETING AND BRACING FOR TRENCH SHOWN IN FIG. 111

Material is moist sand weighing 110 pounds per cubic foot, with an angle of

repose of 30°. Lumber is yellow pine, with working stress as given in Table

59. Working stresses for columns given as _S_(1 − _l_⁄(60_d_)).

──────────────────────────────┬───────────────────────────────────────────────

Sheeting 2 inches × 12 Inches │ Cross Braces

──────────┬───────────┬───────┼───────────┬──────┬──────┬──────────┬──────────

│ │Maximum│ │ │ │ │

│ │ Fiber │ │ │ │ │

│ │Stress,│ │ │ │ Actual │Allowable

│ Maximum │Pounds │ │ │ │Intensity,│Intensity,

│ Bending │ per │ │Total │ │Pounds per│Pounds per

│ Moment, │Square │ Depth and │Load, │Size, │ Square │ Square

Depth │Inch-Pounds│ Inch │Description│Pounds│Inches│ Inch │ Inch

──────────┼───────────┼───────┼───────────┼──────┼──────┼──────────┼──────────

│ │ │end at 26′│ │ │ │

23′–26.75′│ 9100│ 1140│ 9″│ 6,445│ 4 × 8│ 202│ 784

│ │ │int. at 26′│ │ │ │

19′–23′│ 8800│ 1100│ 9″│12,890│ 4 × 8│ 403│ 784

│ │ │end at 23′│ │ │ │

13′–17.5′│ 8550│ 1070│ 0″│ 6,393│ 4 × 8│ 200│ 784

│ │ │int. at 23′│ │ │ │

8′–13′│ 7160│ 900│ 0″│12,785│ 4 × 8│ 400│ 784

│ │ │end at 19′│ │ │ │

0′–6′│ 3000│ 375│ 0″│ 3,930│ 4 × 8│ 123│ 784

│ │ │int. at 19′│ │ │ │

│ │ │ 0″│ 7,860│ 4 × 8│ 240│ 784

│ │ │end at 17′│ │ │ │

│ │ │ 6″│ 3,566│ 4 × 8│ 112│ 684

│ │ │int. at 17′│ │ │ │

│ │ │ 6″│ 7,132│ 4 × 8│ 224│ 684

│ │ │end at 13′│ │ │ │

│ │ │ 0″│ 4,385│ 4 × 8│ 137│ 684

│ │ │int. at 13′│ │ │ │

│ │ │ 0″│ 8,770│ 4 × 8│ 274│ 684

│ │ │end at 8′│ │ │ │

│ │ │ 0″│ 2,270│ 4 × 6│ 96│ 687

│ │ │int. at 8′│ │ │ │

│ │ │ 0″│ 4,540│ 4 × 6│ 189│ 667

│ │ │end at 6′│ │ │ │

│ │ │ 0″│ 1,344│ 4 × 6│ 60│ 584

│ │ │int. at 6′│ │ │ │

│ │ │ 0″│ 2,687│ 4 × 6│ 112│ 584

│ │ │end at 0′│ │ │ │

│ │ │ 0″│ 432│ 4 × 6│ 18│ 584

│ │ │int. at 0′│ │ │ │

│ │ │ 0″│ 863│ 4 × 6│ 36│ 584

──────────┴───────────┴───────┴───────────┴──────┴──────┴──────────┴──────────

Rangers

──────┬──────┬─────────┬──────┬────────────────────┬──────┬───────────┬───────

│ Area │ │ │ │ │ │

│ of │Intensity│ │ │ │ │

│Panel │ of │ │ │ │ │Maximum

│Below │Pressure,│ │ │ │ Maximum │Stress

│ this │ Pounds │Total │ │ │ Bending │Pounds

│Depth,│ per │ Load │ │ │ Moment in │ per

│Square│ Square │ in │Load Transmitted to │Size, │ Thousand │Square

Depth │ Feet │ Inch │Pounds│the Ranger from the │Inches│Inch-Pounds│ Inch

──────┼──────┼─────────┼──────┼──────┬──────┬──────┼──────┼───────────┼───────

│ │ │ │Panel │Panel │ Both │ │ │

│ │ │ │Below │Above │Panels│ │ │

──────┼──────┼─────────┼──────┼──────┼──────┼──────┼──────┼───────────┼───────

26′ 9″│ 24│ 508.5│12,200│ 6000│ 6890│12,890│8 × 10│ 155│ 1160

23′ 0″│ 30│ 448│13,440│ 6545│ 6240│12,785│8 × 10│ 153│ 1150

19′ 0″│ 32│ 378│12,100│ 5860│ 2000│ 7,860│8 × 10│ 94.3│ 708

17′ 6″│ 12│ 328.5│ 3,942│ 1942│ 5190│ 7,132│8 × 10│ 85.6│ 636

13′ 0″│ 36│ 274.5│ 9,880│ 4690│ 4080│ 8,770│8 × 10│ 105│ 790

8′ 0″│ 40│ 189│ 7,560│ 3480│ 1060│ 4,540│6 × 8│ 54.4│ 850

6′ 0″│ 16│ 126│ 2,020│ 960│ 1727│ 2,687│6 × 8│ 32.2│ 503

0′ 0″│ 48│ 54│ 2,590│ 863│ 0│ 863│6 × 8│ 10.4│ 161

──────┴──────┴─────────┴──────┴──────┴──────┴──────┴──────┴───────────┴───────

in which _S_ = permissible crushing across the grain in a column whose

length is greater than 15 diameters;

_S__{1} = unit working compressive strength of wood;

_l_ = length of the column;

_d_ = smallest dimension of the column;

_l_ and _d_ are in the same units.

The lower intermediate cross brace supports a length of 8 feet of the

lower ranger on which the load has been found to be 12,890 pounds. The

load on the end cross brace for the same ranger is one-half of this or

6,445 pounds. The length of each brace is 4 feet 4 inches. From Table

59, _S__{1} is 1,000 pounds per square inch. From the column formula,

_S_ is 784 pounds per square inch.

A 4 × 8 inch cross brace is the smallest that is feasible. This is

stressed only 12,890 pounds or 403 pounds per square inch, which is well

within the permissible limits. The results of the other computations for

cross braces are shown in Table 60.

=158. Steel Sheet Piling.=—This is coming into more general use with the

increased cost of lumber and better acquaintance with its superiority

over wood under many conditions. Although its first cost is higher than

that of wood, the fact that with proper care it can be used almost an

indefinite number of times renders it economical to contractors who may

have an opportunity to make repeated use of it. The life of good yellow

pine sheeting with the best of care may be as much as three or four

seasons. With no particular care it will be destroyed at the first

using. Fig. 112 shows various sections of steel piling used for trench

sheeting. These forms are practically water-tight and aid materially in

maintaining dry trenches. The piling can be made water tight by slipping

a piece of soft wood between the steel sections when they are being

driven, or by pouring in between the piles some dry material which will

swell when wet. The piling is generally driven by a steam hammer and is

pulled by attaching a ring through a bolt hole in the pile, or by

grasping the pile with a clutch that tightens its grasp as the pull

increases. An inverted steam hammer attached to the pile is sometimes

used in pulling it. The impulses of the hammer together with a steady

pull on the cable serve to drag out the most stubborn piece of piling.

[Illustration:

FIG. 112.—Sections of Lackawanna Steel Sheet Piling.

]

LINE AND GRADE

=159. Locating the Trench.=—In order to locate a trench a line of stakes

should be driven at about 50–foot intervals along the center line of the

proposed sewer before excavation is commenced. Reference stakes or

reference points to this line are located at some fixed offset or easily

described point, or the stakes marking the center line of the trench may

be driven at some constant offset distance one side of the trench, in

order to avoid danger of loss or disturbance of the stakes. Grade or cut

is seldom marked on the line of preliminary stakes, although the

approximate cut may be indicated.

For hand excavation the foreman lays out the trench from these stakes.

In machine work the operator guides the machine so as to follow the line

of the stakes.

=160. Final Line and Grade.=—After the excavation of the trench has

proceeded to within a foot or two of the final depth, the grade and line

are transferred to markers supported over the center of the trench. The

markers are horizontal boards spanning the trench and held in position

either by nails driven into stakes at the side of the trench, by nails

driven into the sheeting, or by weights holding the boards on the

ground. Two stakes driven in the ground at the side of the trench as

shown in Fig. 113 are the common method of support. If the banks are too

weak to stand under the jarring of the driving of the stakes, or

pavement or other causes prevent their use the horizontal cross piece

may be weighted down by bricks or a bank of earth. The cross pieces are

located about every 25 feet along the trench and at any convenient

distance above the surface of the ground. The nearer the ground the

stronger the support but the greater the interference with work in the

trench. The center line of the sewer is marked on the cross pieces after

they are set, and vertical struts are nailed on them with one edge of

the strut straight, vertical, and on the center line as shown in Fig. 1.

The corresponding edge should be used on all struts in order to avoid

confusion. The edge is placed in a vertical position by means of a plumb

bob or carpenter’s level.

[Illustration:

FIG. 113.—Methods for the Support of the Grade Line.

]

The cut to the invert of the sewer is recorded to an even number of feet

where practicable by driving a nail in the upright strut so that the top

edge of the nail is at the desired elevation above the sewer, or the

upright is nailed with its top at the proper number of feet above the

sewer invert. The cut is marked on the upright in feet, tenths, and

hundredths from the recorded point to the elevation of the invert.

The inspector should watch these grade markers with care by sighting

back along them to see that they are in line and have not moved. In

quicksand or caving material the marks may move during the setting of

the pipes and the levelman should be on the job constantly.

When excavation is being done by machine the depth of the excavation is

controlled by the operator who maintains a sighting rod on the machine

in line with the grade marks on the uprights.

[Illustration:

FIG. 114.—Diagram Showing the Use of the Grade Rod for Fixing the

Elevation of a Sewer.

]

=161. Transferring Grade and Line to the Pipe.=—In transferring grade

and line to the sewer a light strong string is stretched tightly from

nail to nail on the uprights marking the line and grade. A rod with a

right angle projection at the lower end, as shown in Fig. 114, is marked

with chalk or a notch at such a distance from the end that when the mark

is held on the grade cord the lower portion of the rod which projects

into the pipe will rest on the invert. The pipe is placed in line by

hanging a plumb bob so that the plumb bob string touches the grade and

center line cord. These marks are taken only as frequently as may be

necessary to keep the sewer in line. An experienced workman can maintain

the line by eye for considerable distances. Measurements should never be

taken to the top of the pipe in order to determine position and grade as

the variations in the diameter of the pipe may cause appreciable errors.

The position and elevation of the forms for brick, concrete, and unit

block sewers are located by reference to the grade line, or they may be

placed under the immediate direction of the survey party, or by

specially located stakes. For large sewers requiring deep and wide

excavation the grade and line stakes are driven in the bottom of the

trench about a foot above the finished grade. This requires the constant

presence of an engineer who is usually available on work of such

magnitude.

=162. Line and Grade in Tunnel.=—In tunnels, line and grade are given by

nails driven in the roof, the progress of excavation or the shield being

followed by eye and the forms set by direct measurement to the nails.

TUNNELING

=163. Depth.=—The depth at which it becomes economical to tunnel depends

mainly upon the character of the material to be excavated and on the

surface conditions. In soft dry material with unobstructed working space

at the surface, open cut may be desirable to depths as great as 35 or 40

feet. Tunnels are cut in rock at depths of 15 feet or less. In some very

wet and running quicksand encountered in the construction of sewers for

the Sanitary District of Chicago it was found economical to tunnel at

depths of 20 feet and less. Crowded conditions on the surface, expensive

pavements, or extensive underground structures near the surface may make

it advantageous to tunnel at shallower depths than would otherwise be

economical. Winter is the best season for tunneling as the workmen are

protected from the elements and labor is more plentiful.

=164. Shafts.=—In sinking a shaft in soft material, the excavation is

usually done by hand, the material being thrown into a bucket which is

hoisted to the surface and dumped. The size of the shaft is independent

of the size of the sewer and depends principally on the machinery which

it is necessary to lower into the tunnel. Ordinarily a shaft 6 feet in

the clear is satisfactory. A method of timbering a shaft is shown in

Fig. 115. Because of the timbering the shaft must be started

sufficiently large at the top to finish with the desired dimensions at

the bottom. This excess size is sometimes obviated by driving the

sheeting at an angle to maintain the same size of shaft from top to

bottom.

In timbering a shaft as shown in Fig. 115 the upper frame is staked

securely in position at the surface of the ground. This frame is

composed of timbers fastened together in the form of a square with the

ends of the timbers extending about 12 inches on all sides. The

protruding ends are used to hold the frame in position. Excavation is

begun inside the frame, and sheeting is driven around the outside of it

as excavation progresses. Only two or three men can work advantageously

at one time in these small shafts. The second frame is made up of the

same size timbers, but all are cut off flush with the outside of the

square. The outside dimensions of this frame are such as to allow

sheeting to be slipped in between it and the sheeting already driven.

The frame is lowered into position and supported from the upper frame by

vertical struts nailed to it. The lower end of the sheeting already

driven is held out from the lower frame by blocks of the thickness of

the next length of sheeting. These blocks are removed as the next length

of sheeting is placed and driven. The driving of the sheeting is

facilitated by excavating beneath it as it descends.

[Illustration:

FIG. 115.—Section of Shaft Timbering.

Abbot, Journal Western Society of Engineers, Vol. 22.

]

The sizes of sheeting and timbering should be computed on the same basis

as that for trench sheeting except that for depths greater than 30 to 35

feet Rankine’s Theory is not applicable and judgment must be relied on

for computing the sizes for deep shafts. In stiff dry material the

pressures will change very little as the depth increases. Sheeting is

needed in shaft excavation in rock only to protect the workmen from

falling fragments, but in sand, particularly in quicksand and in wet

ground, the pressures increase directly with the depth and the sheeting

should be computed accordingly. Care must be taken to prevent the

formation of cavities behind the sheeting, to fill them if formed, and

to see that all pieces of the sheeting and bracing have a firm bearing.

It is difficult to prevent the collapse of the shaft once the movement

of earth against the sheeting has commenced.

Shafts are also sunk in soft ground by constructing a concrete or metal

shell resting on a cutting shoe on the surface. The material inside is

dug out and the shell sinks of its own or added weight. The first

section of the shell may be from 5 to 10 feet long. As this section

sinks other sections are added. This is called the caisson method. It is

advantageous in wet ground and when the shafts are to be left as a

permanent manhole. If a permanent shaft is to be left in an excavation

being braced with wood, the permanent lining should follow within 20 to

30 feet of the shaft excavation. This is done to avoid the difficulty of

maintaining a great length of temporary wood shaft with the danger of

collapse, or of blocks or other objects falling on the workers below.

The distance between shafts is controlled by the depth and size of the

tunnel, surface conditions, and the character of the material being

tunneled. Except where surface conditions are crowded the shallower the

cover to the tunnel the more frequent the shafts. The advantage of

frequent shafts lies in the possibility of removing excavated material

from the tunnel promptly, and in making ventilation of the tunnel

easier. The saving made by the construction of numerous shafts must be

balanced against the extra cost of the shafts. For the shallowest

tunnels the shafts are seldom placed closer than every 500 feet.

=165. Timbering.=—After the shaft has been excavated to the proper grade

the tunnel is struck out either by cutting through the wooden sheeting

or by removing portions of the caisson lining. Practically all tunnels

except those in solid rock must be framed to some extent. Some of the

types of frames used in tunnel construction are shown in Fig. 116.

Different combinations of these may be used in different classes of

materials. In solid rock which remains firm on exposure no timbering is

necessary. Where the roof only need be supported and the sides are

strong enough to be used for support, a timber “hitch” or frame

supported on the sides of the tunnel may be used. This is suitable for

loose rock roofs with solid rock sides. Timbering such as is shown in

the lower left hand corner of Fig. 116 becomes necessary in extremely

soft, wet, or swelling material, where the bottom and sides as well as

the roof tend to push in. The remaining frame in Fig. 116 shows a form

frequently used and lying between the two extremes indicated. In wet

tunnels a channel may be cut in the bottom below the sill for drainage

purposes as shown in this form. The needle beam method of timbering is

also shown in Fig. 116. This method of timbering is used mainly near the

heading because of the speed and ease with which it can be installed,

but it is undesirable because of the space occupied.

The distance between frames is dependent on the size of the tunnel and

the character of the material. It is seldom greater than 6 feet and the

frames are sometimes placed touching each other. The size of the

timbering is a matter of experience and is generally determined by the

judgment of the responsible person in charge of the construction as the

result of observation during the progress of the work.

The sheeting between frames is called poling boards, or spiling or

lagging according as it is sharpened and driven ahead of the excavation

or placed after the excavation has progressed. The horizontal strips

placed between the frames to keep them apart are called wales.

[Illustration:

FIG. 116.—Types of Frames and Timbering for Tunnels.

]

In cutting out from the shaft in soft materials requiring support, where

the width of the tunnel is the same or smaller than that of the shaft, a

frame with a maximum width four thicknesses of sheeting less than the

width of the tunnel is set up against the lining of the shaft. The

vertical side pieces of the tunnel frame rest on the bottom frame of the

shaft as a sill and are securely wedged into position. As the lining of

the shaft at the top is cut away the top poling boards of the tunnel are

slipped in between the cap of the first tunnel frame and the shaft frame

immediately above it. The poling boards are driven with an upward pitch

so that there may be room to slip the second length of boards between

the next tunnel frame and the first length of boards. The placing of the

side sheeting follows in a similar manner. Excavation is then started

and the poling boards driven to keep pace with it. The next frame is

placed in position and the previous sheeting or boards wedged out a

sufficient distance to allow the advance lining to be slipped in when

the wedges are removed. Waling pieces are nailed firmly between the

frames to hold them in position. The various phases in the driving of a

12–foot sewer tunnel in Seattle are shown in Fig. 117.

[Illustration:

FIG. 117.—Stages of Sewer Tunneling.

Eng. Record, Vol. 69, 1914, p. 195.

]

In soft or running material it may be necessary to protect the face of

the tunnel by horizontal boards, called breast boards, wedged back to

the last frame placed. The excavation is performed by removing one board

at a time, excavating behind it and then replacing it in the advance

position. The advance is made from the top downwards. This represents

the method pursued in the most difficult material where wooden sheeting

without a shield is used. The timbering during the advance may be

modified in any manner that the character of the material will permit.

The timbering may lag behind the excavation a distance of two or more

frames, or it may be omitted altogether. Heavier timbering may be

necessary in soft, slipping or shattered rock.

[Illustration:

FIG. 118.—Shield for Driving Milwaukee Sewer Tunnel.

Eng. News-Record, Vol. 80, 1918, p. 669.

]

=166. Shields.=—Shields are used in tunneling in soft wet material and

are particularly suitable for work under air pressure. They are used in

rock tunnels where water is anticipated or air pressure is used. The

shields often save the expense and difficulty of timbering as the

masonry of the sewer follows closely behind the shield. Fig. 118 shows

the arrangement for a shield for tunneling in soft material in the

construction of the Milwaukee sewers. The shield has an exterior

diameter of 9 feet 4 inches and an overall length of 9 feet 8⅛ inches.

The cutting edge section is 20 inches long. The shell is made of one

inch plate to the back of the jack chambers and one-half inch plate in

the tail. The shield is driven by ten 60–ton hydraulic jacks. The jacks

are shown in position in the figure. These jacks rest against the

finished tunnel lining and serve to consolidate it at the same time that

they push the shield into the material to be excavated. The face of the

tunnel is cut with a pick and shovel while the jacks are removed one at

a time and a new ring of lining is put in place. The lining may be

temporary timbering to receive the thrust of the jacks, but it is

usually desirable that the permanent lining follow immediately behind

the shield. Since the shield is larger than the outside of the lining

the space left by its passage should be grouted immediately after it has

passed.

=167. Tunnel Machines.=—Tunnel machines have been used successfully on

sewer tunnels in soft materials, but not in rock.[95] The machines are

of different types, but in general consist of a revolving cutting head,

equipped with knives, and driven by an electric motor. The bearing on

which the shaft for the cutting head rests is supported against the

sides of the tunnel. The muck is carried away by means of a conveyor and

dumped into muck cars without rehandling. Rapid progress can be made

with these machines in suitable conditions.

[Illustration:

FIG. 119.—Method of Drilling and Loading Rock Tunnel Face.

Courtesy, Aetna Power Co.

]

=168. Rock Tunnels.=—Tunnels in rock are advanced by drilling into the

face as shown in diagrammatic form in Fig. 119. The holes near the

center are driven in at an angle towards the center and to depths from 6

to 15 feet. The harder the rock the greater the angle with the tunnel.

This is called the center cut. Other holes are driven near the outer

edge of the tunnel and parallel to its axis. When fired, the wedge of

rock between the center cut holes is thrown back into the tunnel and a

delayed explosion then throws the sides into the hole thus made. A final

delay thrusting shot throws the muck so formed away from the face of the

tunnel. For tunnels up to 6 or 8 feet in height the entire bore is cut

out in this fashion. For larger tunnels, the upper portion called the

heading, is taken out in this way, and the remainder, called the bench,

is taken out by drilling and blowing holes normal to the axis of the

tunnel. The amount of powder necessary in the bench holes is much less

than that required in the heading.

=169. Ventilation.=—No tunnel more than 50 feet long should be built

without ventilation. A fair amount of air for ordinary conditions is 75

cubic feet of free air per minute per person in the tunnel, and double

this amount for each animal. Where explosive gases are met, or under

conditions where the tunnel is hot, five or six times as much air may be

needed in order to cool the tunnel or to dilute the gases. In order that

the air may be fresh and cool at the face of the tunnel where work is

going on it should be conducted to the tunnel face in a pipe and blown

out into the tunnel. Immediately following a blast at the face the

current should be reversed so as to draw the poisonous gases out of the

tunnel through the duct. The high pressure air line leading to the

drills should be opened at the same time to create a current towards the

face in order to accelerate the clearing of the air at the heading. The

capacity of the air machines should be sufficient to exhaust four times

the volume of the gases created by the explosion, in 15 minutes. This

will ordinarily call for a capacity of about 4,000 cubic feet of free

air per minute. If the same blower is to be used for exhausting the

gases as for ventilation while work is going on, it should have a high

overload capacity to care for this situation. The air line should be

arranged to allow for reversal of flow.

The diameter of the air pipe should be determined by a study of the

saving of the cost and operation of the air equipment compared to the

increased cost of a larger pipe line. Other factors affecting the size

of the pipe line to be used are: the available space in the tunnel, the

temporary character of the installation, the use of the exhaust from

high-pressure air machines for the purpose of ventilation, etc.

Cast-iron, spiral-riveted galvanized sheet iron, and canvas pipes have

been used for conducting low-pressure ventilating air.

Ventilation in tunnels working under air pressure is supplied from the

compressors, and the air is delivered near the face of the heading,

except that being used in the locks. In tunnels using air drills, the

air for the drills is conducted through a separate pipe as it is not

economical to compress the ventilating air to the pressure necessary to

operate the drills.

=170. Compressed Air.=—Compressed air is used in tunnel work to prevent

the entrance of water into the tunnel and to keep the work dry. The

pressure of air used is closely that of the pressure of the ground water

but in a large tunnel or a tunnel with a weak roof the pressure may be

somewhat lower on account of the danger of blowing through the roof. It

is evident that the water pressure cannot be balanced at the top and the

bottom of the tunnel. To balance it at the bottom makes a blow out near

the top more probable. To balance the pressure at the top may leave the

bottom wet. Judgment and care must be exercised during construction and

if the pressure is balanced at or near the bottom the roof must be

carefully guarded by grouting and puddling with clay, or the surface,

particularly if under water, may be covered with a clay bank. If the

cavities in the tunnel lining are large, sawdust can be mixed with the

grout to advantage, the mixture being pumped through holes in the roof

by hand or power operated force pumps. “Blows” must be carefully guarded

against as they endanger the lives of the workmen and threaten the loss

of the tunnel. The pressure and volume of air supplied for some large

subaqueous tunnels is shown in Table 61.

Labor under compressed air is arduous and dangerous with the best of

safeguards.[96] Pressure more than about 43 pounds per square inch

cannot be used and at this high pressure men cannot work more than four

hours at a time. Little or no distress is noted at pressures less than

15 pounds.

TABLE 61

VOLUME AND PRESSURE OF COMPRESSED AIR IN TUNNELS

(American Civil Engineers Pocket Book)

──────────┬────────┬───────┬─────────┬─────────┬───────────────────────

Tunnel │ │ │ Maximum │ Average │ Conditions and Cubic

│Maximum │ │ Air │ Air │ Feet of Free Air per

│Distance│ │Pressure,│Pressure,│ Minute

│ High │ │ Pounds │ Pounds │

│Water to│Minimum│ per │ per │

│Invert, │ Cover │ Square │ Square │

│ Feet │in Feet│ Inch │ Inch │

──────────┼────────┼───────┼─────────┼─────────┼───────────────────────

City and │ │ │ │ │In water bearing-sand.

South │ │ │ │ │ 1660 cubic feet per

London │ │ │ │ │ minute per face. When

│ │ │ │ │ grouted 1000 to 1300

│ │ │ │ │ cubic feet per minute

│ 34│ 42│ 15│ │ per face

──────────┼────────┼───────┼─────────┼─────────┼───────────────────────

Blackwall │ │ │ │ │10,000 cubic feet per

│ │ │ │ │ minute per face in

│ │ │ │ │ open ballast for some

│ 80│ 5│ 37│ 35│ time

──────────┼────────┼───────┼─────────┼─────────┼───────────────────────

Baker St. │ │ │ │ │In gravel, 3300 cubic

and │ │ │ │ │ feet of air per

Waterloo│ │ │ │ │ minute per face.

│ │ │ │ │ Parallel tunnel 1650

│ │ │ │ │ cubic feet per min.

│ 70│ 18│ 35│ 28│ per face

──────────┼────────┼───────┼─────────┼─────────┼───────────────────────

Greenwich │ │ │ │ │Average 83.5 per man

│ │ │ │ │ per minute. Never

│ 70│ 30│ 28│ 20│ less than 66.7

──────────┼────────┼───────┼─────────┼─────────┼───────────────────────

Battery, │ │ │ │ │In sand. Two working

East │ │ │ │ │ faces. Maximum 32,000

River. │ │ │ │ │

N. Y. │ 94│ 12│ 42│ 26│

──────────┼────────┼───────┼─────────┼─────────┼───────────────────────

East │ │ │ │ │Maximum for one face

River, │ │ │ │ │ 25,000 cubic feet per

N. Y., │ │ │ │ │ minute for 24 hours.

Penn. │ │ │ │ │ Capacity of plant for

R.R. │ │ │ │ │ 8 faces, 80,400 cubic

│ 93│ 8│ 42│ 27│ feet per minute

──────────┼────────┼───────┼─────────┼─────────┼───────────────────────

North │ │ │ │ │Maximum in gravel

River, │ │ │ │ │ 10,000 cubic feet per

N. Y., │ │ │ │ │ man per hour.

Penn. │ │ │ │ │ Generally ranged

R.R. │ 98│ 20│ 37│ 26│ between 1500 and 5000

──────────┴────────┴───────┴─────────┴─────────┴───────────────────────

Entrance and exit to the tunnel are gained through air locks. These are

sheet iron cylinders concreted into the lining of the tunnel or shaft.

Air-tight iron doors are provided at both ends, which open inwards

towards the tunnel. On entering the lock from the outside the door to

the tunnel is found tightly closed. The outside door is then closed by

hand, the air valve is opened and air is admitted to the lock until the

pressure on the lock side of the tunnel door equalizes that on the

tunnel side and the tunnel door is swung open by hand. When the lock is

open to the tunnel the pressure in the tunnel keeps the outside door

closed. In order to leave the tunnel the process is reversed. Materials

are passed through the lock by the lock tender or tenders who pass

through the lock with the material if the pressure is low, or who

manipulate the air outside of the lock if the pressure is high. If

pressures of 30 to 40 pounds are being used, two or even three locks may

be necessary.

EXPLOSIVES AND BLASTING[97]

=171. Requirements.=—The desirable features in an explosive to be used

in trenching and tunneling in rock are: (1) stability in make up so as

not to deteriorate in strength or to become dangerous during storage,

(2) imperviousness to ordinary variations in temperature and moisture,

(3) insensibility to ordinary shocks received in transportation and

handling, (4) not too difficult of detonation, (5) convenient form for

transportation and loading and for making up charges of different

weights, (6) the non-formation of poisonous gases when fired, (7)

imperviousness to water and usefulness in wet holes, (8) power without

bulk, etc.

=172. Types of Explosives.=—Explosives which fill some or all these

requirements can be divided into two classes, deflagrating and

detonating. A deflagration is an explosion transmitted progressively

from grain to grain. A detonation is a sudden disruption caused by

synchronous vibrations of a wave-like character. The deflagrating

explosives are represented by gun-powders and contractors’ powders. They

must be carefully tamped in the hole to develop their full power and

they must be ignited by a fuse or flame. They are valueless in water or

moist holes. These powders are used mainly for loosening frozen earth,

soft sandstone, cemented gravels and similar materials where a thrusting

action rather than a disruption is desired. The detonating explosives

are most commonly represented by the dynamites. These are exploded by a

shock usually caused by another explosive which has been ignited by a

fuse or electric spark, and which is known as the “detonator.”

Detonating explosives are more powerful than deflagrating explosives and

are used in all but the softest materials.

_Gunpowder._—This is a mechanical mixture of sulphur, charcoal, and

saltpeter generally in the proportions of 10 parts sulphur, 15 parts

charcoal, and 75 parts saltpeter (sodium nitrate). It weighs about 62½

pounds per cubic foot and produces about 280 times its own volume in gas

at a pressure of 4.68 tons per square inch at a temperature of 32

degrees F., which amounts to a pressure of approximately 38 tons per

square inch at the temperature of explosion of 4,000 degrees F.

_Blasting Powder._—This is a mixture of 19 parts sulphur, 15 parts

charcoal, and 66 parts saltpeter. These powders are made in different

size angular polished grains, from the size of a pin head to sizes just

passing a ⅜ to ½ inch hole. The larger the grains the slower the action

of the powder.

_Nitro-Substitution Compounds._—These compounds are formed by the action

of nitric acid on hydrocarbons. Triton, T.N.T., or trinitrotoluene, made

famous during the war, is an example of these compounds. It is made by

the successive nitration of toluene, a coal tar derivative. It melts at

80 degrees C., is very stable, and is of great explosive strength. It is

manufactured in a convenient form, being compressed into blocks about 2

inches square by about 4 inches long with a specific gravity of about

1.5. The blocks are usually copper plated to protect the T.N.T. from

moisture. The more dense it is the less its sensitiveness. It is also

put up in crystalline form in cartridges like dynamite, in which

condition it is practically equal to 40 per cent dynamite. It can be cut

with a knife, pounded with a hammer, and will burn freely and slowly in

small quantities in the open air without exploding. It is suitable for

all but the hardest rocks. It creates poisonous gases on detonation

which are quickly dissipated in the open air but which render it

unsuitable for use in tunnel work.

_Nitro-glycerine._—This is formed by the action of nitric and sulphuric

acids on animal compounds such as gelatine or glycerine. Nitro-glycerine

is a yellowish, oily, highly unstable explosive liquid with a specific

gravity of about 1.6. It will burn quietly when ignited in the open air.

It will freeze at 41 degrees F., and will explode at 388 degrees F., or

on concussion at a lower temperature. It develops about 1,500 times its

volume in gas, which due to the heat of combustion is increased to about

10,000 times its volume. It is a very dangerous explosive to handle, and

is unsuitable for use in the liquid form.

_Blasting Gelatine._—This is made by soaking guncotton in

nitro-glycerine. Gelatine dynamite is a combination of blasting gelatine

and an absorbent. Forcite is a gelatine dynamite in which the blasting

gelatine, forming 50 per cent of the compound, contains 90 per cent

nitro-glycerine and 2 per cent guncotton; and the absorbent, forming the

other 50 per cent of the compound, contains 76 per cent of sodium

nitrate, 3 per cent sulphur, 20 per cent of wood tar, and 1 per cent of

wood pulp.

Blasting gelatine is packed in a jelly-like mass in metal lined wooden

boxes. It is less sensitive than straight dynamite and is one of the

most powerful explosives known. It can be made up to equal 100 per cent

dynamite. It is suitable for use in the hardest rocks and for subaqueous

work as it is not affected by moisture. It is suitable for use in

tunnels as the amount of carbon monoxide, peroxide of nitrogen, hydrogen

sulphide and other dangerous gases is comparatively low when fully

detonated. Gelatine dynamite[98] is sold as 30 per cent to 70 per cent

dynamite, the actual percentage of nitro-glycerine being less than the

nominal quantity given.

_Dynamite._—The dynamites are made by soaking nitro-glycerine in some

absorbent. If the absorbent is some neutral substance such as infusorial

earth the combination is known as a true dynamite. The false or active

dynamites are those in which the absorbent is also an explosive

compound. The false dynamites form the best known contractors’

explosives. Among the materials mixed with the nitro-glycerine are:

magnesium carbonate, sulphur, wood meal, wood pulp, wood fiber, wood

tar, nut galls, kieselguhr, sawdust, resin, pitch, sugar, charcoal, and

guncotton. The strength of dynamites is noted by the per cent of

nitro-glycerine and nitro substitutes contained. Dualin and Hercules

powder both contain 40 per cent nitro-glycerine. Dualin contains 30 per

cent sawdust and 30 per cent potassium nitrate, but the Hercules powder,

which is stronger, contains 16 per cent sugar, 3 per cent potassium

chlorate, 31 per cent potassium nitrate, and 10 per cent magnesium

carbonate.

Dynamite is the most common explosive used on construction work. It is

supplied in cylindrical sticks wrapped in paper, the diameter of the

sticks varying between ⅞ and 2 inches. They are about 8 inches long.

Forty per cent dynamite is the common strength found on the market. It

is suitable for ordinary work in all but very hard rocks or very soft

material. Direct contact with water separates the nitro-glycerine from

the base and is dangerous when the explosive is used in wet places

unless it is fired immediately after the hole is loaded. It freezes at

about 42 degrees F., or at even higher temperatures and in the frozen

state it is highly dangerous, requiring powerful detonators for firing,

but exploding spontaneously from a slight jar, or the breaking of the

stick. Special low-freezing dynamites are made that will not freeze

above 35 degrees F.

_Ammonia Compounds._—Ammonia dynamite is a combination of

nitro-glycerine, ammonium nitrate and such other ingredients as sodium

nitrate, calcium carbonate and combustible material. This form of

explosive is advantageous for underground work because, like gelatine

dynamite, its explosion does not create large quantities of poisonous

gases. It has a low freezing point and is relatively low in cost. It is

seriously affected by moisture, however, and can not be used in wet

places. Ammonium nitrate explosives which do not contain nitro-glycerine

include 70 per cent to 95 per cent ammonium nitrate and some combustible

material. Ammonal is a special type of this class formed by a mixture of

ammonium nitrate, aluminum, and triton. All of these explosives are

deliquescent, insensitive to shock, and are cheaper than the dynamites.

=173. Permissible Explosives.=—As specified by the United States Bureau

of Mines explosives whose rapidity, detonation, and temperature of

explosion will not ignite explosive mixtures of pit gases and air are

known as permissible explosives. They include nitrate explosives,

ammonia dynamite, and others.

Gunpowder, triton, picric acid, blasting gelatine, dynamite, guncotton,

etc., are not classed as permissible explosives.

=174. Strength.=—The relative weights for equal strength of various

explosives are given in Table 62.

TABLE 62

RELATIVE WEIGHTS OF EXPLOSIVES WITH THE SAME STRENGTH AS A UNIT WEIGHT

OF 40 PER CENT DYNAMITE

───────────────────────────────────────────────────────┬───────────────

Explosive │Relative Weight

───────────────────────────────────────────────────────┼───────────────

Picric acid │ 0.86

Gun powder (well tamped) │ 3.10

Straight dynamite, 15% │ 1.45

Straight dynamite, 20 │ 1.33

Straight dynamite, 25 │ 1.28

Straight dynamite, 30 │ 1.18

Straight dynamite, 35 │ 1.07

Straight dynamite, 40 │ 1.00

Straight dynamite, 45 │ 0.93

Straight dynamite, 50 │ 0.86

Straight dynamite, 55 │ 0.83

Straight dynamite, 60 │ 0.78

│

Low-freezing dynamites are the same as straight │

dynamites │

Smokeless powder, well tamped │ 0.74

│

Triton │ 0.86

Blasting gelatine │ 0.43

Gelatine dynamite, 30% │ 1.28

Gelatine dynamite, 35 │ 1.21

Gelatine dynamite, 40 │ 1.14

Gelatine dynamite, 50 │ 1.04

Gelatine dynamite, 55 │ 0.97

Gelatine dynamite, 60 │ 0.90

Gelatine dynamite, 70 │ 0.83

│

Ammonia dynamites are the same as gelatine dynamites. │

Chlorates (sprengle) Rack-a-rock │ 1.33

Guncotton │ 0.72

───────────────────────────────────────────────────────┴───────────────

=175. Fuses and Detonators.=—The explosion of gunpowder and other

deflagrating explosives is caused by the direct application of a flame

led to the charge by a powder fuse, or they may be fired by a blasting

cap which is itself exploded by the heat from a fuse or an electric

spark. The powder fuse is a cord made up of a train of powder securely

wrapped in a number of thicknesses of woven cotton or linen threads and

usually made waterproof. Ordinary fuse burns at about 2 feet per minute

but there may be wide variations from this rate due to the quality of

the fuse, moisture, temperature, or pressure. Moisture tends to retard

the rate, pressure to increase it. Instantaneous fuse will burn at about

120 feet per second. It is distinguished from the ordinary safety fuse

both by eye and touch due to the rough red braid with which it is

covered. It is used in firing a number of charges simultaneously. Powder

fuses are lighted by the application of a flame or smoldering torch to

the freshly cut or opened end exposing the powder grains. Cordeau

Bickford is lead tubing filled with triton, in which the flame travels

at about 17,000 feet per second. This is also used for igniting charges

simultaneously.

The detonation of an explosive is caused by the shock or heat of the

explosion of a more sensitive substance which has been exploded by a

powder fuse or electric spark. The common method of detonating explosive

charges is by the firing of a blasting cap. These caps are copper

cylinders, closed at one end, about 1½ inches long and ¼ to ⅜ of an inch

in diameter, or larger. They contain a mixture of about 85 per cent

fulminate of mercury and 15 per cent potassium chlorate held in place by

a wad of shellac, collodion, or paper. The strength of detonators is

based on the weight of fulminate of mercury and is designated as shown

in Table 63.

TABLE 63

STRENGTH OF BLASTING CAPS

────────────────────────────────────────┬──────────────────────────────

Blasting Cap, Commercial Grade │ Grains Fulminate of Mercury

────────────────────────────────────────┼──────────────────────────────

3X or Triple │ 8.3

4X or Quadruple │ 10.0

5X or Quintuple │ 12.3

6X or Sextuple │ 15.4

7X or Number 20 │ 23.1

8X or Number 30 │ 30.9

Single strength │ 12.3

Double strength │ 15.4

Triple strength │ 23.1

Quadruple strength │ 30.9

────────────────────────────────────────┴──────────────────────────────

The force of the explosion is markedly affected by the strength of the

caps, the effect being greater for low-grade powders. For 40 per cent

dynamite the explosion caused by a 5X cap is 15 per cent stronger than

that caused by a 3X cap. For 60 per cent dynamite the difference is only

6 per cent. The deterioration of the caps will reduce the strength of an

explosion noticeably. With straight dynamite, 3X caps are generally

used, but with gelatine dynamite 6X or heavier caps must be used. Caps

may be tested by exploding them in a confined space and noting the

report and the effect on the shell. A full strength cap will tear the

shell into minute pieces, while a deteriorated cap will merely tear it

into three or four large pieces. An ordinary blasting cap is shown in

Fig. 120 together with other equipment for blasting.

Firing by electricity is generally safer and more satisfactory than by

the use of ordinary caps and powder fuses. The explosion is more certain

and its exact time is under the control of the operator. Fig. 121 shows

a section through an electric blasting cap or detonator, commonly called

an electric fuse. Delayed action electric detonators are made by

inserting a slow-burning substance between the platinum bridge and the

detonating substance. The time of delay is controlled by the depth of

the slow-burning substance. Delayed action detonators are useful in

tunnel work where it is desired to explode the charge in three or four

stages in order that the debris from one charge may be out of the way of

the following, and that the forces of the explosions may not serve to

nullify each other.

[Illustration:

FIG. 120.—Blasting Supplies.

Courtesy, Aetna Powder Co.

]

=176. Care in Handling.=—Some of the don’ts in the handling of

explosives recommended by the U. S. Army Engineer Field Manual are: in

the use of nitro-glycerine explosives of all kinds—

(_a_) Don’t store detonators with explosives. Detonators should be

kept by themselves.

(_b_) Don’t open packages of explosives in a store house.

(_c_) Don’t open packages of explosives with a nail puller, pick

or chisel. Packages should be opened with a hard wood wedge and

mallet, outside of the magazine and at some distance from it.

(_d_) Don’t store explosives in a hot or damp place. All

explosives spoil rapidly if so stored.

(_e_) Don’t store explosives containing nitro-glycerine so that

the cartridges stand on end. The nitro-glycerine is more likely to

leak from the cartridges when they stand on end than it is when

they lie on their sides.

(_f_) Don’t use explosives that are frozen or partly frozen. The

charge may not explode completely and serious accidents may

result. If the explosion is not complete the full strength of the

charge is not exerted and larger quantities of harmful gases are

given off.

[Illustration:

FIG. 121.—Electric Fuse.

Full size.

]

(_g_) Don’t thaw frozen explosives in front of an open fire, nor

in a stove, nor over a lamp, nor near a boiler, nor near steam

pipes, nor by placing cartridges in hot water. Use a commercial or

improvised thawer.

(_h_) Don’t put hot water or steam pipes in a magazine for thawing

purposes.

(_i_) Don’t carry detonators and explosives in the same package.

Detonators are extremely sensitive to heat, friction, or blows of

any kind.

(_j_) Don’t handle detonators or explosives near an open flame.

(_k_) Don’t expose detonators or explosives to direct sunlight for

any length of time. Such exposure may increase the danger in their

use.

(_l_) Don’t open a package of explosives until ready to use the

explosive, then use it promptly.

(_m_) Don’t handle explosives carelessly. They are all sensitive

to blows, friction, and fire.

(_n_) Don’t crimp a detonator (blasting cap) around a fuse with

the teeth. Use a cap crimper, which is supplied for this purpose.

(_o_) Don’t economize by using a short length of fuse.

(_p_) Don’t return to a charge for at least one-half hour after a

miss fire. Hang fires are likely to happen.

(_q_) Don’t attempt to draw nor to dig out the charge in case of a

miss fire.

Some of the positive rules in connection with the handling of explosives

are: build the magazine on an earth foundation remote from any other

structures, protect it with earth embankments that will direct the force

of the explosion upwards, and build it of materials that will supply as

few missiles as possible. Hollow tile brick, double-walled galvanized

iron filled with sand, and similar constructions are satisfactory. The

magazine may be heated by steam or hot-water pipes so located that

explosives cannot come in contact with them, or by a cluster of

incandescent bulbs, but if the explosives become frozen they must not be

thawed out by turning on the steam or hot water. If powder or

nitro-glycerine is dropped on the floor the magazine should be emptied,

washed out with a hose and spots of nitro-glycerine scrubbed with a

brush and a mixture of ½ gallon of wood alcohol, ½ gallon of water and 2

pounds of sodium sulphide. Frozen explosives may be thawed by spreading

out on special shelves in a warm thaw house—not in the magazine proper,

by burying in a manure pile so that the explosive may not become

moistened, or more commonly by heating slowly in a water bath. This is a

dry kettle in which the explosives are placed and covered. The kettle is

then put in another containing water which is heated gently to about 120

degrees F. It should not be boiled.

In case of a miss fire, instead of digging out the old charge put a new

charge on top of the old and fire the two simultaneously.

=177. Priming, Loading, and Firing.=—Priming is the act of placing the

cap or detonator in the cartridge of explosive. The primer is either the

cap or the cap and cartridge which are to be detonated by the fuse. If a

cap and safety fuse are to be used the paper at the upper end of the

cartridge is opened, a hole is poked in the explosive with the finger or

a piece of wood, the cap and the attached fuse are pushed into the hole

and gently embedded in the explosive so that the end of the cap is

exposed sufficiently to prevent the fuse from igniting the dynamite

directly. The paper is then folded up and tied firmly around the fuse

with a piece of string. The result is shown in Fig. 122.

[Illustration:

FIG. 122.—Dynamite Cartridge, Safety Fuse, and Cap.

]

In placing the fuse in the cap the end of the fuse is cut off square,

and inserted in the open end of the cap, care being taken not to spill

the loose grains of powder or to grind the fuse down on top of the cap.

When the fuse is shoved firmly into place the upper portion of the

copper cap is pressed or crimped with the cap crimpers shown in Fig.

120.

The number of primers to be used is dependent on the size and location

of the charge, but in practically all sewer work only one primer is used

to each hole. In bulky charges the primer should be placed near the

center of the charge and the fuse so protected that it will not ignite

the charge prematurely. In drill holes the primer is put in last with

the cap end down.

In loading a hole, it is first pumped and cleaned out. This can be done

satisfactorily with the end of a stick frayed out into a broom.

Cartridges which very nearly fill the hole are dropped in one at a time

and are pressed firmly together, with a light wooden tamping bar. They

should not be pounded. After the primer is placed, a wad of clay or

similar material is pressed gently into the hole against it and the hole

is then filled with well-tamped clay. In tunnel work tamping is not so

essential as an overcharge of powder is usually used and the time of

tamping, which is worth more than two or three sticks of dynamite, is

saved. In handling bulk explosives, such as gunpowder, they are poured

into the hole, the fuse is set in the upper portion and the remainder of

the hole is tamped with clay as for dynamite cartridges.

[Illustration:

FIG. 123.—Methods for Cutting Safety Fuse for Splicing.

]

If a large number of charges are to be fired simultaneously with a

safety fuse, the length of the fuse to each charge should be made equal

or a safety fuse used to a common center and approximately equal lengths

of instantaneous fuse or Cordeau Bickford used from there to the charge.

In splicing the fuses for such connections they are cut diagonally as

shown in Fig. 123 and bound together firmly with tape. Electric

connections are particularly advantageous under such conditions as they

avoid the dangers incidental to spliced fuses and are less expensive. In

tunnel work simultaneous electric detonation is not desirable as the

holes should be fired progressively: 1st, the cuts; 2nd, the relievers;

3rd, the backs; 4th, the sides; and 5th, the lifters. Different lengths

of safety fuse, or delayed action electric fuses can be used for these

delay shots.

In igniting a safety fuse an open flame such as that furnished by a

match or candle is the most satisfactory. For electric fuses the current

is generated by a magneto shown in Fig. 120. Pressing vigorously down on

the handle closes the circuit and generates an electric current which

heats the platinum bridges and explodes the charges. For the small

number of charges used in ordinary construction they are connected in

series so that if there is a broken connection anywhere no charge will

be exploded. If many charges are to be fired and a line circuit is to be

used, the final connection should not be made until just before the

charge is to be fired in order to obviate the danger of stray currents

firing the charge prematurely. Care should be taken to see that all

connections are good and that there are no broken wires on the line.

=178. Quantity of Explosive.=—The quantity of explosive to be used can

be determined satisfactorily only by experience on the job in question,

as the factors affecting the necessary quantity are so diverse. The

figures in Table 64 indicate the relative amounts needed under different

conditions.

TABLE 64

QUANTITIES OF EXPLOSIVES

───────────┬──────┬────────┬─────────┬─────────────┬─────────┬──────────

Kind of │Drift │Feet[99]│Black[99]│Dynamite[99],│Grade of │

Rock │ in │of Hole │ Powder, │ Pounds │Dynamite,│ Remarks

│ Feet │ │ Pounds │ │Per Cent │

───────────┼──────┼────────┼─────────┼─────────────┼─────────┼──────────

Limestone, │ │ │ │ │ │

Chicago │ 12│ 0.40│ │ 0.75│ 40│Gillette

Drainage │ │ │ │ │ │

Canal │ │ │ │ │ │

Limestone │ │ │ │ │ │

for │ 6│ 1.00│ │ 0.70│ 40│Gillette

crushing │ │ │ │ │ │

Limestone │ │ │ │ │ │

for │ 20│ │ │ 0.37│ 50│Gillette

cement │ │ │ │ │ │

Limestone, │ │ │ │ │ │

holes │ 15│ 0.40│ │ 0.26│ 50│Gillette

sprung │ │ │ │ │ │

Sandstone, │ 20│ 0.10│ 1.0│ 0.10│ 40│Gillette

side cut │ │ │ │ │ │

Sandstone, │ │ │ │ │ │

thorough │ 20│ 0.20│ 2.0│ 0.20│ 40│Gillette

cut │ │ │ │ │ │

Shale, soft│ 24│ 0.08│ 0.7│ 0.03│ 40│Gillette.

side cut │ │ │ │ │ │ Open cut

Shale, hard│ │ │ │ │ │

thorough │ 24│ 0.20│ 1.5│ 0.10│ 40│Gillette

cut │ │ │ │ │ │

Granite for│ 16│ 1.36│ │ 0.20│ 60│Gillette

rubble │ │ │ │ │ │

Gneiss, New│ 12│ 1.33│ │ 0.60│ 40│Gillette

York City│ │ │ │ │ │

Gneiss, New│ 14│ 0.63│ │ 0.50│ 40│Gillette

York City│ │ │ │ │ │

Syenite, │ │ │ │ │ │

Treadwell│ 12│ 1.70│ │ 0.67│ 40│Gillette

Mine │ │ │ │ │ │

Magnetic │ 12½│ 0.32│ │ 0.44│ 52│Gillette

iron ore │ │ │ │ │ │

Trap, seamy│ 14│ 0.35│ │ 0.20│ 75│Gillette

Trap, │ 17│ 1.00│ │ 0.70│ 40│Gillette

massive │ │ │ │ │ │

│ │ │ │ │ │50%

Granite, │ │ │ │ │ │ dynamite

Grand │ 25│ 0.10│ │ 0.80│ 50│ used to

Trunk │ │ │ │ │ │ spring

│ │ │ │ │ │ holes

Clay, rock │ │ │ │ │ │

and │Tunnel│ │ │ 1.00│ │

Gypsum │ │ │ │ │ │

│ │ │ │ │Grade │

│ │ │ │ │ varied │

│ │ │ │ │ ⅗ at │

Hard shale │Tunnel│ │ │ 2.07│ 45%, ⅕ │

│ │ │ │ │ at 60%,│

│ │ │ │ │ some at│

│ │ │ │ │ 100% │

Hard rocky │Tunnel│ 1.60│ │ 3.57│ │

slate │ │ │ │ │ │

Hard rocky │Tunnel│ 1.46│ │ 3.57│ │

slate │ │ │ │ │ │

Mill Creek │ │ │ │ │ │Mun.

sewer, │Tunnel│ │ │ 4.00│ 60│ Eng’g.

St. Louis│ │ │ │ │ │ Vol. 52,

│ │ │ │ │ │ p. 14

───────────┴──────┴────────┴─────────┴─────────────┴─────────┴──────────

PIPE SEWERS

=179. The Trench Bottom.=—It is customary to dig the bottom of the

trench to conform to the shape of the lower 45 degrees to 90 degrees of

the sewer if the character of the material will allow such construction.

In soft material which will not hold its shape the sewer may be encased

in concrete or a concrete cradle may be prepared for the pipe. In rock

the trench is excavated to about 6 inches below grade and refilled with

well-tamped earth so as to form a cradle giving bearing to 60 to 90

degrees of the pipe circumference. For large sewers to be constructed in

the trench special foundations are sometimes built.

=180. Laying Pipe.=—Before the pipe is lowered into the trench the

sections which are to be adjacent should be fitted together on the

surface and the relative positions marked by chalk so that the same

position can be obtained in the trench.

Small pipes are lowered into the trench and swung into position on a

hook as shown in Fig. 124. Pipes up to 15 or 18 inches in diameter can

be handled by the pipe layer and helper in the trench without

assistance. Heavier pipes may be lowered into the trench by passing

ropes around each end of the pipe. One end of the rope is fastened at

the surface and the ropes are paid out by the men at the surface as the

pipe is lowered. If the pipes have been fitted together and marked at

the surface it is undesirable to use this method of lowering as the

position in which the pipes arrive in the bottom of the trench can not

be easily predicted. A cradle may be used for shoving the pipe into

position as is shown in Fig. 125.

[Illustration:

FIG. 124.—Hook for Lowering and Placing Sewer Pipe.

]

[Illustration:

FIG. 125.—Cradle for Placing Sewer Pipe.

]

Pipes above 24 to 27 inches in diameter are too large to be handled from

the side of the trench. A hook as shown in Fig. 124 is placed in the

pipe so that it will be in the proper position when lowered. It is

raised by a rope passing through a block at the peak of a stiff-legged

derrick which spans the trench, or by a crane. If a derrick is used the

rope passes to a windlass on the opposite side of the trench from the

pipe. Mechanical power may be used for raising pipes too heavy to be

raised by hand. The pipe is then lowered and swung into position while

supported from the derrick. Excessive swinging is prevented by holding

back on the guide rope as the pipe is raised and lowered.

Pipes are usually laid with the bell end up grade as it is easier to fit

the succeeding pipe into the bell so laid and to make the joint,

particularly on steep grades. The Baltimore specifications state:

The ends of the pipe shall abut against each other in such a

manner that there shall be no shoulder or unevenness of any kind

along the inside of the bottom half of the sewer or drain. Special

care should be taken that the pipe are well bedded on a solid

foundation.... The trenches where pipe laying is in progress shall

be kept dry, and no pipe shall be laid in water or upon a wet bed

unless especially allowed in writing by the Engineer. As the pipe

are laid throughout the work they must be thoroughly cleaned and

protected from dirt and water, no water being allowed to flow in

them in any case during the construction except such as may be

permitted in writing by the Engineer. No length of pipe shall be

laid until the preceding length has been thoroughly embedded and

secured in place, so as to prevent any movement or disturbance of

the finished joint.

The mouth of the pipe shall be provided with a board or stopper,

carefully fitted to the pipe, to prevent all earth and any other

substances from washing in.

=181. Joints.=—Pipes may be laid with open joints, mortar joints, cement

joints, or poured joints. Open joints are used for storm sewers in dry

ground close to the surface. Mortar and cement joints are commonly used

on all sewers except in special cases. Cement joints are more carefully

made than mortar joints and result in a greater percentage of

water-tight joints. Poured joints are used in wet trenches where it is

necessary to exclude ground water from the sewer.

A specification used in some cities for open joints is:

Pipes laid with open joints are to be laid with their inverts in

the same straight line and shall be firmly bedded throughout their

length on the bottom of the trench. No cement or mortar is to be

used in the joints. Not more than ⅛ inch shall be left between the

spigot end of the pipe and the shoulder of the hub of the pipe

into which it fits. The joints shall be surrounded with cheese

cloth, burlap, broken pipe, gravel or broken stone.

The purpose of the cheese cloth, etc., is to prevent fine earth from

sifting into the pipe until the cheese cloth or other material has

rotted away, by which time the earth has become arched over the opening.

Mortar joints are specified by Metcalf and Eddy as follows:

Before a pipe is laid the lower part of the bell of the preceding

pipe shall be plastered on the inside with stiff mortar of equal

parts of Portland cement and sand, of sufficient thickness to

bring the inner bottoms of the abutting pipe flush and even. After

the pipe is laid the remainder of the bell shall be thoroughly

filled with similar mortar and the joint wiped inside and finished

to a smooth bevel outside.

In some work a wood block or a stone is embedded in the mortar at the

bottom of the joint to bring the spigot in place concentric with the

next pipe.

Cement joints are specified in the Baltimore specifications as follows:

Cement joints shall be made with a narrow gasket of hemp or jute

and cement mortar, and special care shall be taken to secure tight

joints. The gasket shall be soaked in Portland cement grout and

then carefully inserted between the bell and the spigot, and well

calked with suitable hardwood or iron calking tools. It shall be

in one continuous piece for each joint, and of such thickness as

to bring the inverts of the two pipes smooth and even. The

remainder of the joint shall be filled with cement mortar all

around, on the bottom, top and sides, applied by hand with rubber

mittens, well pressed into the annular space and beveled off from

the outer edge of the bell to a distance of two inches therefrom,

or to an angle of 45 degrees. The inside of each joint shall be

thoroughly cleansed of all surplus mortar that may squeeze out in

making the joint; and to accomplish this some suitable scraper or

follower, or form shall be provided and always used immediately

after each joint is finished.

Cement joints so made, form the most satisfactory joint for ordinary

conditions and are the most frequently used. They are not always

water-tight and can be penetrated by roots. Some roots are able to

penetrate holes of almost microscopic size and to form growths in the

sewer or to split the joints.

Poured joints are made by pouring some jointing compound, while in a

fluid state, into the joint in which it hardens, thus sealing the joint.

Water-tightness in sewer lines to exclude ground water has also been

attempted by using the ordinary cement joint and surrounding the pipe

with a layer of cement or concrete. This has not always been successful

as it is difficult to obtain the proper class of workmanship in wet

sewer trenches.

The requisite qualities of a poured jointing material are:

(1) It should make a joint proof against the entrance of water and

roots.

(2) It should be inexpensive.

(3) It should have a long life.

(4) It should not deteriorate in sewage which may be either acid

or alkaline.

(5) It should adhere to the surface of the pipe.

(6) It should run at a temperature below about 400° F., as too

high temperatures will crack the pipe.

(7) It should neither melt nor soften at temperatures below 250°

F. in order to maintain the joint if hot liquids are poured into

the sewer.

(8) It should be elastic enough to permit slight movements of the

pipes.

(9) It should not require great skill in using as it must be

handled ordinarily by unskilled workers.

The materials used for poured joints are: cement grout; sulphur and

sand; and asphalt or some bituminous compound made of vulcanized linseed

oil, clay, and other substances the resulting mixture having the

appearance of vulcanized rubber or coal tar. The bituminous materials

most nearly approach the ideal conditions.

Cement grout is made up of pure cement and water mixed into a soupy

consistency. Its main advantages are its cheapness and ease in handling

in wet trenches or difficult situations. The result is no better than a

well made cement joint. There is no elasticity to the joint and a

movement of the pipe will break it.

Sulphur and sand are inexpensive, comparatively easy to handle, and make

an absolutely water-tight and rigid joint which is stronger than the

pipe itself. It frequently results in the cracking of the pipe and is

objected to by some engineers on that account. In making the mixture,

powdered sulphur and very fine sand are mixed in equal proportions. It

is essential that the sand be fine so that it will mix well with the

sulphur and not precipitate out when the sulphur is melted. Ninety per

cent of the sand should pass a No. 100 sieve and 50 per cent should pass

a No. 200 sieve. The mixture melts at about 260° F. and does not soften

at lower temperatures. For making a joint in an 8 inch pipe about 1½

pounds of sulphur, 1½ pounds of sand, ½ pound of jute, and 0.4 pound of

pitch are used. The pitch is used to paint the surface of the joint

while still hot in order to close up any possible cracks.

Among the better known of the bituminous joint compounds are: “G.K.”

Compound made by the Atlas Company, Mertztown, Pa., Jointite and

Filtite, manufactured by the Pacific Flush Tank Co., Chicago and New

York, and some of the products of the Warren Brothers Co., Boston. These

compounds fill nearly all of the ideal conditions except as to cost and

ease in handling. They are somewhat expensive and if overheated or

heated too long become carbonized and brittle. In cold weather they do

not stick to the pipe well unless the pipe is heated before the joint is

poured. On some work joints have been poured under water with these

compounds, but success is doubtful without skillful handling. An

overheated compound will make steam in the joint causing explosions

which will blow the joint clean, and an underheated compound will harden

before the joint is completed.

The materials should be heated in an iron kettle over a gasoline furnace

or other controllable fire, until they just commence to bubble and are

of the consistency of a thin sirup. Only a sufficient quantity of

material for immediate use should be prepared and it should be used

within 10 to 15 minutes after it has become properly heated. The ladle

used should be large enough to pour the entire joint without refilling.

There are other important points to be considered in pouring joints

which can be learned best by experience.

The quantity of material necessary for making these joints, as announced

by the manufacturers, is shown in Table 65.

TABLE 65

QUANTITY OF COMPOUND NEEDED FOR POURED JOINTS

───────────┬───────────────────────────────────────────────────────────

Diameter of│

Pipe, in │ Quantity of Material in Pounds per Joint

Inches │

───────────┼─────────────────────────────┬─────────────────────────────

│ Standard Socket │ Deep and Wide Socket

───────────┼─────────┬─────────┬─────────┼─────────┬─────────┬─────────

│Jointite │ Filtite │ G. K. │Jointite │ Filtite │ G. K.

───────────┼─────────┼─────────┼─────────┼─────────┼─────────┼─────────

6│ 0.82│ 0.72│ 0.42│ 1.46│ 1.28│ 0.72

8│ 1.06│ 0.95│ 0.73│ 1.82│ 1.60│ 1.25

10│ 1.30│ 1.15│ 0.89│ 2.26│ 1.98│ 1.52

12│ 2.08│ 1.82│ 1.42│ 2.65│ 2.32│ 1.80

15│ 2.52│ 2.20│ 1.74│ 3.20│ 2.80│ 2.20

18│ 3.02│ 2.64│ 2.58│ 3.75│ 3.29│ 3.25

20│ 3.44│ 3.00│ 2.86│ 4.30│ 3.78│ 3 60

22│ 3.62│ 3.16│ 3.13│ 4.62│ 4.07│ 3.97

24│ 4.03│ 3.50│ 3.41│ 4.91│ 4.31│ 4.27

───────────┴─────────┴─────────┴─────────┴─────────┴─────────┴─────────

In making a poured joint the pipes are first lined up in position. A

hemp or oakum gasket is forced into the joint to fill a space of about ¾

of an inch. An asbestos or other non-combustible gasket such as a rubber

hose smeared with clay is forced about ½ inch into the opening between

the bell and the spigot and the compound is poured down one side of the

pipe through a hole broken in the bell, until it appears on the other

side, and the hole is filled. Occasionally the non-combustible gasket is

wrapped tightly around the spigot of the pipe and pressed or tied firmly

to the bell. In pouring cement grout joints a paper gasket is used which

is held to the bell and spigot by draw strings. Greater speed in

construction and economy in the use of materials are obtained by joining

two or three lengths of pipe on the bank and lowering them into the

trench as a unit. The pipes are set in a vertical position on the bank

with the bell end up, one length resting in the other. The joint is

calked with hemp and poured without the use of the gasket. The joint

should always be poured immediately after being calked so that the hemp

can not become water soaked. The asbestos gasket should be removed as

soon as possible after the joint is poured in order to prevent sticking

with resultant danger of breaking of the joint when attempting to pull

the gasket free.

One man can pour about 33 eight-inch joints, and two men can complete

about 26 twelve-inch joints per hour on the bank where conditions are

more or less fixed.

=182. Labor and Progress.=—The labor required for the laying of pipe

sewers, exclusive of excavation, bracing and backfilling, consists of

pipe layers and helpers. For pipes 24 to 27 inches in diameter or

smaller one pipe layer and one or more helpers are necessary, dependent

on the size of the pipe and the depth of the trench. For larger pipes

two pipe layers can work economically each working on one-half of the

pipe and making half of the joint. The speed of pipe laying is

ordinarily limited by the speed of the excavation, but on a job in

Topeka, Kan.,[100] where the average day’s progress with a machine

excavator was 200 to 500 feet of trench per day, the pace was limited by

the speed of the pipe laying gang. This gang consisted of two pipe

layers in the trench and two helpers on the surface. The sizes of pipes

handled were from 8 to 27 inches.

BRICK AND BLOCK SEWERS

=183. The Invert.=—In good firm ground the excavation is cut to the

shape of the sewer and the bricks are laid directly on the ground, being

embedded in a thick layer of mortar. After the foundation has been

prepared and before the bricks are laid, two wooden templates, called

profiles, are prepared, similar to that shown in Fig. 126, to conform to

the shape of the inside and outside of the sewer. Each course of bricks

is represented by a row of nails in the profile and each nail

corresponds to a joint in the row. The two profiles are set true to line

and grade. A cord is stretched tightly between the two lowest nails on

opposite templates and a row of bricks is laid. The bricks are laid

radially and on edge with their long dimension parallel to the axis of

the sewer and with one edge just touching the string. As each one or two

or three rows are completed the guide line is moved up to the next

nails. When the bricks are laid on the ground all but large depressions

are filled in with tamped sand or mortar by the masons. Approximately

the same number of rows of bricks is kept completed on either side of

the center line. The succeeding courses follow within three to five rows

of each other, the only bond between courses being the mortar joint.

This is called row lock bond and with few exceptions has been used on

all brick sewers in the United States. As the sides of the sewer become

higher during the construction, platforms must be built for the masons.

These platforms are built of wood and rest directly on the green

brickwork. They should be designed to spread the load as much as

possible. The brickwork of the invert is continued up in this way to the

springing line. As soon as one section is completed one profile is moved

10 to 20 feet ahead along the trench according to the standard length of

sections, and set in position. The line is then strung from it to nails

driven or pushed into the cement joints of the last completed section.

Between work done on separate days the bricks are racked back in courses

to provide a satisfactory bond.

[Illustration:

FIG. 126.—Profile for Brick Sewers.

]

In ground too soft to support the brickwork directly a cradle is

prepared by placing profiles in position in the sewer and nailing 2–inch

planks to these profiles, first firmly tamping earth under the planks.

The bricks are laid in this cradle in a manner similar to that explained

for sewers with a firm foundation. In still softer ground it may be

necessary to construct a concrete cradle to support the bricks.

=184. The Arch.=—The arch centering consists of a wooden form made up of

wooden ribs as shown in Fig. 127. The center conforms to the shape of

the inside of the arch with allowance for the thickness of the lagging.

The lagging is nailed on the ribs in straight strips parallel to the

axis of the sewer. The center is supported on triangular struts resting

against the sides and on the bottom of the sewer and is lifted into

position by wedges driven between it and the support. The centers may be

placed immediately after the completion of the invert, or a day or two

may be allowed to pass to give the invert an opportunity to set. After

the centers are fixed in place the arch brick are carried up evenly on

each side and are pounded firmly into place. The center is usually, but

not always “struck” immediately, and the arch brick are cleaned and

pointed up from the inside. The outside is covered with a layer of ¼ to

¾ of an inch of cement mortar and may be backfilled to the top of the

arch in order to maintain the moisture of the mortar during setting and

to press the bricks of the arch together firmly. The centers are

sometimes made collapsible so that they can be carried or rolled through

the finished brickwork to the advanced position. In “striking” the

centers the wedges are removed and the wings folded in.

[Illustration:

FIG. 127.—Centering for Brick Sewer.

]

In tunneling, the invert of the sewer is constructed in the same fashion

as for open cut work. The arch centering is made in short sections and

the bricks are put in position by reaching in over the end of the

centering. All of the timbering of the tunnel is removed except the

poling boards or lagging against which the bricks or mortar are tightly

pressed, the boards being bricked in permanently.

=185. Block Sewers.=—Sewers made of unit blocks of concrete or vitrified

clay are constructed in a similar manner to brick sewers. Fig. 128 shows

the construction of a block sewer at Clinton, Iowa. In this sewer there

are two rings; an inside one of solid blocks and an outside one of

hollow blocks. Block sewers do not demand the skill in construction that

is demanded by brick sewers, as the blocks are so cast that the joints

are radial, whereas only experienced masons can lay bricks radially.

[Illustration:

FIG. 128.—Segmental Block Sewer at Clinton, Iowa.

]

=186. Organization.=—The number of men employed on a brick or block

sewer is proportioned according to the size of the sewer and the working

conditions. The number of men working on different tasks usually bears

the same ratio to the number of masons employed, regardless of the size

of the work. These proportions are shown for different jobs, in Table

66.

TABLE 66

ORGANIZATIONS FOR THE CONSTRUCTION OF BRICK AND BLOCK SEWERS

─────────────┬──────────────┬────────┬────────┬────────┬────────┬──────────

│ │ │ │ │ 84– to │

│General Ratio │15–foot,│66–inch │84–inch │108–inch│ 42–inch

Type of Work │ on Basis of │ 5–ring │Circular│Circular│ Sewer │Lock-Joint

│ Four Brick │ Brick, │ Brick, │ Brick, │Brick in│Tile Block

│ Layers │Chicago │ Gary │ Gary │Detroit │

│ │ │ │ │ Tunnel │

─────────────┼──────────────┼────────┼────────┼────────┼────────┼──────────

Foreman │ 1│ 1│ 1│ 1│ 1│ 1

Brick layers │ 4│ 12│ 6│ 6│ 5│ 2

Helpers │ 2│ 11│ 3│ 3│ │ 1

Scaffold men │ 2│ 21│ 3│ │ │

Brick tossers│ 2│ 7│ │ 15│ │ 2

Brick │ 2│ 2│ │ │ │ 2

carriers │ │ │ │ │ │

Cement mixers│ 2│ 6│ 6│ 5│ │ 1

Cement │ 2│ 10│ │ 8│ │

carriers │ │ │ │ │ │

Form setters │ 1│ │ 3│ 3│ │

Laborers │ 1│ 8│ 19│ 3│ 14│ 7

│ Municipal │

Source of │ Engineering, │ H. P. Gillette, Handbook of Cost Data

Information│ Vol. 54, p. │

│ 228 │

─────────────┴──────────────┴──────────────────────────────────────────────

=187. Rate of Progress.=—In a general way it can be assumed that the

laying of 1,000 bricks will require 3⅓ hours of the time of one mason,

10 man-hours for helpers and laborers, 2 barrels of cement, 0.6 cubic

yard of sand, and about 10 feet board measure of centering. One thousand

bricks will make about 2 cubic yards of brickwork. To the costs, as

estimated on the basis of materials and labor, must be added about 15

per cent for overhead and an additional amount for the contractor’s

profit. The number of bricks required in various size sewers is shown in

Table 67. A mason can lay more bricks per hour in a large sewer than in

a small one as there is a smaller percentage of face work, there is more

room to work, and it is easier to lay the bricks radially. The number of

bricks laid and the rate of progress on various jobs are shown in Table

68.

TABLE 67

BRICK MASONRY IN CIRCULAR SEWERS. CUBIC YARDS PER LINEAR FOOT

(From H. P. Gillette)

─────────────────┬─────────────────┬─────────────────┬─────────────────

Diameter, │ One Ring │ Two Ring │ Three ring

Feet and Inches │ (4½ Inches) │ (9 Inches) │ (13½ Inches)

─────────────────┼─────────────────┼─────────────────┼─────────────────

2 0│ 0.103│ 0.240│

2 6│ 0.125│ 0.280│

3 0│ 0.147│ 0.327│

3 6│ 0.169│ 0.371│

4 0│ 0.191│ 0.415│

4 6│ 0.213│ 0.458│

5 0│ 0.234│ 0.501│ 0.802

5 6│ 0.256│ 0.545│ 0.867

6 0│ 0.278│ 0.589│ 0.933

6 6│ │ 0.633│ 1.000

7 0│ │ 0.677│ 1.063

7 6│ │ 0.720│ 1.128

8 0│ │ 0.763│ 1.193

8 6│ │ 0.807│ 1.260

9 0│ │ 0.851│ 1.325

9 6│ │ 0.895│ 1.390

10 0│ │ 0.938│ 1.456

─────────────────┴─────────────────┴─────────────────┴─────────────────

CONCRETE SEWERS

=188. Construction in Open Cut.=—In the construction of sewer pipe of

cement and concrete one of two methods may be employed; 1st, to

manufacture the pipe in a plant at some distance from the place of final

use, or 2nd, to manufacture the pipe in place. The methods of the

manufacture of cement and concrete pipe which are to be transported to

the place of use are treated in Chapter VIII. The process of

constructing the pipes in place is ordinarily used for pipes 48 inches

or more in diameter. For smaller sizes, brick, vitrified clay, and

precast cement pipes are usually more economical.

The preparation of the foundation of a concrete sewer is similar to that

for a brick sewer. If the ground is suitable the trench is shaped to the

outside form of the sewer and the concrete poured directly on it. In

soft material which would give poor support to a sewer with a rounded

exterior, the bottom of the trench is cut horizontal and a concrete

cradle of poorer quality than that in the finished sewer is poured on

the soft ground, on a board platform, on piles, or on cribbing supported

on piles.

If the invert of the sewer is so flat that the concrete will stand

without an inside form the shape of the invert is obtained by a screed

or straight-edge which is passed over the surface of the concrete and

guided on two centers, or on one center and the face of the finished

work. The construction of a flat invert sewer at Baltimore is shown in

Fig. 1. The center for the concrete is shown in the foreground. When the

concrete for the next section is poured it will be smoothed to shape by

a screed or straight-edge resting on the face of the finished concrete

and the center. The center is shaped to conform to that of the finished

concrete. It is firmly staked in position and acts as a bulkhead for the

concrete as it is poured, as well as a guide for the screed.

TABLE 68

RATE OF PROGRESS ON BRICK SEWER CONSTRUCTION

(Based on 8–hour day)

────────┬────────┬──────┬──────┬──────┬────────

│ │ │ │Bricks│

Diameter│ │Number│Number│ per │ Number

of Sewer│ Shape │Rings,│Masons│Mason │Laborers

│ │Brick │ │ per │

│ │ │ │ Day │

────────┼────────┼──────┼──────┼──────┼────────

7′ 0″│Circular│ │ │ │

8′ 11″│ and │ 2½ │ 6│ 4710│ 39

│ Oval │ │ │ │

│ │ │ │ │

│ │ │ │ │

4′ 0″│Circular│ 2 │ 3│ 2500│

│ │ │ │ │

│ │3 arch│ │ │

6′ 8″│Circular│ 1 │ 18│ │ 62

│ │invert│ │ │

│ │ │ │ │

│ │1 arch│ │ │

2′ 9″│Egg │ 2 │ 2│ │ 3

│ │invert│ │ │

│ │ │ │ │

5′ 6″│Circular│ 2 │ 6│ 4570│ 35

6′ 6″│Circular│ │ 4│ 4800│

│ │ │ │ │

│ │ │ │ │

2′ 9″│Circular│ 2 │ 2│ 2080│ 5

│ │ │ │ │

16′ 0″│Circular│ 5 │ 8│ 5 cu.│

│ │ │ │ yd.│

16′ 0″│Circular│ 5 │ 12│ │ 70–75

3′ 6″│Egg │ │ │ 2300│

9′ 6″│Circular│ │ │ 3000│

│ │ │ │ │

│ │ │ │ │

3′ 6″│Circular│blocks│ 2│ │ 13

│ │ │ │ │

│ │ │ │ │

────────┴────────┴──────┴──────┴──────┴────────

────────┬────────┬────────────┬─────────┬───────────

│ │ │ │

Diameter│ Feet │ │ │

of Sewer│Progress│ Location │Authority│ Remarks

│per Day │ │ │

│ │ │ │

────────┼────────┼────────────┼─────────┼───────────

7′ 0″│ │ │ │

8′ 11″│ 60│Gary │Gillette │9–hour day

│ │ │ │

│ │ │ │

│ │ │Metcalf │General

4′ 0″│ 36│ │ and │ average

│ │ │ Eddy │

│ │ │ │Concrete

6′ 8″│ │Denver │Gillette │ invert

│ │ │ │

│ │ │Eng. │

│ │Springfield,│ Con., │

2′ 9″│ │ Mass. │ Jan. │

│ │ │ 16, │

│ │ │ 1907 │

5′ 6″│ 110│Gary │Gillette │

6′ 6″│ │ │Gillette │Exceptional

│ │ │ │ speed

│ │ │ │Tunnel

2′ 9″│ 13.9│Syracuse │Gillette │ 12–hour

│ │ │ │ day

16′ 0″│ 22│Chicago │Gillette │First year

│ │ │ │

16′ 0″│ 35│Chicago │Gillette │Second year

3′ 6″│ │St. Louis │Gillette │

9′ 6″│ 12.5│Chicago │H. R. │

│ │ │ Abbott │

│ │ │ │Lock joint

3′ 6″│ 30│ │ │ and tile.

│ │ │ │ 10–hour

│ │ │ │ day

────────┴────────┴────────────┴─────────┴───────────

If inside forms are to be used they are made as units in lengths of 12

or 16 feet for wooden forms, and 5 feet for steel forms. The inside form

is supported by precast concrete blocks placed under it and which are

concreted into the sewer. It is held in position by cleats nailed to the

outside form, to the sheeting, or wedged against the outside of the

trench. In some cases, particularly where steel forms are used, the

inside form is hung by chains from braces across the trench as is shown

in Fig. 129. The form is easily brought to proper grade by adjustment of

the turnbuckles and is then wedged into position to prevent movement

either sideways or upwards during the pouring of the concrete. It may be

necessary to weight the forms down to prevent flotation. Cross bracing

in the trench which interferes with the placing of the form is removed

and the braces are placed against the form until the concrete is poured.

They are removed immediately in advance of the rising concrete.

[Illustration:

FIG. 129.—Blaw Standard Half Round Sewer Form, Suspended from Overhead

Support.

Courtesy, Blaw Steel Form Co.

]

The sewer section may be built as a monolith, in two parts, or in three

parts. In casting the sewer as a monolith the complete full round inside

form is fixed in place by concrete blocks and wires. The full round

outside form is completed as far as possible without interfering too

much with the placing and tamping of the concrete. The concrete is

poured from the top, being kept at the same height on each side of the

form, and tamped while being poured. The remaining panels of the outside

form are placed in position as the concrete rises to them. An opening is

left at the top of the outside arch forms which is of such a width that

the concrete will stand without support. The casting of sewers as a

monolith is difficult and is usually undesirable because of the

uncertainty of the quality of the work. It has the advantage, however,

of eliminating longitudinal working joints in the sewers which may allow

the entrance of water or act as a line of weakness.