THE ROAD BETWEEN THE TUNNEL AND NORTH ADAMS.

It is proposed to change the course of, the road as it emerges from the

tunnel, and two lines have been surveyed, which, diverging near the

approach cut, unite again about midway from thence to the village. The

difference in length is about thirty feet. The northerly line is the

least expensive to construct, and best favors the landholders on the

route. It has the recommendation of the engineer, and the approval of

the consulting engineer, and will probably be selected. There are

reasons for an early location of this portion of the road which call for

a prompt action in this behalf on the part of the commissioners, which

will undoubtedly be taken.

The following table shows the expense of the tunnel and the land and

works connected therewith under the administration of the commissioners,

as found November 1, 1866:--

Deerfield Dam, $127,982 80

Race, 23,417 54

Excavation and Masonry at East

End of Dam, 12,802 46

Wheel pits, 70,723 23

Gates and Overflow, 9,986 26

---------- $244,912 29

East End Heading, 103,731 45

East End Enlargement, 80,317 10

East End Heading Enlargement, 17,559 46

Central Shaft, 144,423 75

West Shaft, 179,041 69

West Approach, 247,900 75

Building East End, 31,688 99

Building West End and Shaft, 40,010 13

Building Central Shaft, 12,026 83

Building General Account, 9,537 37

Engineering and Superintendent, 84,840 48

Machinery West Shaft, 57,111 73

Machinery East End, 87,032 38

Machinery Central Shaft, 51,364 01

Machinery Deerfield Dam, 10,820 93

Machinery General Account, 62,600 76

Machinery West End, 539 89

Land and Land Damages, 17,513 21

-------------

$1,482,973 20

The following table shows the cost of the works under the classification

of outside and inside expenditures, as given by the consulting

engineer.

_Outside Expenditures._

Deerfield Dam, $244,912 29

Buildings East End, $31,688 99

Buildings West End and West Shaft, 40,010 13

Buildings Central Shaft, 12,026 83

Buildings General Account, 9,637 37

---------- 93,263 32

Machinery East End, $87,032 38

Machinery West End, 539 89

Machinery West Shaft, 57,111 73

Machinery Central Shaft, 51,364 01

Machinery Deerfield Dam, 10,820 93

Machinery General Account, 62,600 76

---------- 269,469 70

Land Damages and Land, 17,513 21

Engineering and Superintendence, 84,840 48

-----------

Total outside expenditures, $709,999 00

_Inside Expenditures._

East End Heading, $103,731 45

East End Enlargement, 17,559 46

East End Bottom, 80,317 10

-----------

$201,608 01

Central Shaft, 144,423 75

West Shaft Headings, &c., 179,041 69

West End approach cut, drifting

and arching, 247,900 75

Total inside expenditures, ---------- 772,974 20

-------------

Total expenditures to November 1, 1866, $1,482,973 20

The exact correctness of any classification of the expenditures is not

very important, inasmuch as the sum total is chargeable to the

construction of the tunnel; but the Committee do not see the propriety

of charging the engineering and superintendence exclusively to the

outside expenditure. They have seen a classification which gave,--

Amount put into buildings machinery, &c., $673,531 24

Spent in the work, 809,441 96

-------------

Total, $1,482,973 20

Report of the Hoosac Tunnel and Troy and Greenfield Railroad, by the Joint Standing Committee of 1866. · 第 29 / 51 题