2. PREPARATIONS

_(A) Dimensions:_

Measure the dimensions of the principal parts of the apparatus to be

tested, so far as they bear on the objects in view, or determine these

from correct working drawings. Notice the general features of the same,

both exterior and interior, and make sketches, if needed, to show

unusual points of design.

The dimensions of the heating surfaces of boilers and

superheaters to be found are those of surfaces in contact with

the fire or hot gases. The submerged surfaces in boilers at the

mean water level should be considered as water-heating surfaces,

and other surfaces which are exposed to the gases as

superheating surfaces.

_(B) Examination of Plant:_

Make a thorough examination of the physical condition of all parts of

the plant or apparatus which concern the object in view, and record the

conditions found, together with any points in the matter of operation

which bear thereon.

In boilers, examine for leakage of tubes and riveted or other

metal joints. Note the condition of brick furnaces, grates and

baffles. Examine brick walls and cleaning doors for air leaks,

either by shutting the damper and observing the escaping smoke

or by candle-flame test. Determine the condition of heating

surfaces with reference to exterior deposits of soot and

interior deposits of mud or scale.

See that the steam main is so arranged that condensed and

entrained water cannot flow back into the boiler.

If the object of the test is to determine the highest efficiency or

capacity obtainable, any physical defects, or defects of operation,

tending to make the result unfavorable should first be remedied; all

foul parts being cleaned, and the whole put in first-class condition.

If, on the other hand, the object is to ascertain the performance under

existing conditions, no such preparation is either required or desired.

_(C) General Precautions against Leakage:_

In steam tests make sure that there is no leakage through blow-offs,

drips, etc., or any steam or water connections of the plant or apparatus

undergoing test, which would in any way affect the results. All such

connections should be blanked off, or satisfactory assurance should be

obtained that there is leakage neither out nor in. This is a most

important matter, and no assurance should be considered satisfactory

unless it is susceptible of absolute demonstration.