BUILDING THE ROOF

The roof is built by nailing 2 by 4 rafters to the inside studs of the

side wall forms, on a line 1 inch lower than the bottom of the roof.

The rafters are given the pitch desired for the roof, and are securely

fastened where they meet at the ridge. To stiffen the roof form until

the concrete has become hard tie the opposite rafters together at the

bottom (with a 1-inch strip) in the form of a capital “A.” One-inch

boards are nailed on the rafters. The cornice shown in the sketch

extending beyond the wall can be easily built by nailing a board the

width of the cornice to the tops of the outside studs of both side and

end walls. To hold the concrete in place as the roof is being built

nail a 5-inch upright strip along the outside edge of this board. Bend

the bolts projecting above the walls down to within 1 inch of the roof

boards. Spread a layer of heavy woven wire fencing over the entire

roof, allowing it to extend to the outside of the cornice. Wire the

fencing securely to the bent bolts. Place two ½-inch steel rods near

the outside of the cornice all the way around the roof, and fasten

these securely to the woven wire fencing. The roof should be made 3

inches thick and the stone used for the concrete should not be larger

than ½ inch.

[Illustration]

Mix the concrete fairly stiff and start placing it at the cornice,

working toward the ridge. Spread the concrete out in a thin layer and

then lift the woven wire fencing and the two rods in the cornice so

that the concrete is 1 inch thick below the wire. Cover the rods and

wire with more concrete to a depth of 2 inches. When finished the

roof will then be 3 inches thick, 1 inch below the wire and 2 inches

over it. Always work from the low edge of the roof and finish to the

complete depth of 3 inches at once. Imbed a width of woven wire fencing

lengthwise over the ridge of the roof 1 inch beneath the surface. The

work must be carried on without interruption. The concrete must not be

allowed to dry along an unfinished edge, as there is danger of a leak

where fresh concrete is joined to that already hard. Tamp the concrete

until moisture comes to the surface and smooth off the top of the roof

with a wooden float and steel trowel.

The forms must be left in place for at least a week and the concrete

in the roof must be protected from the sun and wind while it is

hardening. A method for doing this is described on page 26 under

SIDEWALKS.

Concrete Construction for the Home and the Farm · 第 106 / 131 题