CHAPTER XII

CECIL RHODES’ DREAM--FROM THE CAPE TO CAIRO

II.--_Southwards from Cairo._

While the southern arm of the great line has been pushed on

energetically northwards from Cape Town, the northern limb has

descended almost as rapidly down the Valley of the Nile to the great

interior, so that the heart of the continent is being eaten into

spiritedly from both ends. The two branches have been built under

totally different auspices. Whereas the southern section was carried

out by private enterprise, the northern division is the work of

Government effort.

In the north the railway has made history rapidly, and its conquest has

been of a complex character. It placed a unique weapon in the hands

of the Government, and it wrested a vast track of Africa, aggregating

950,000 square miles, from barbarity and religious fanaticism in the

form of Mahdism.

Owing to the impoverished condition of the country, the railway in

Egypt has experienced a very chequered career. It commenced its pacific

invasion promisingly enough, but it was found to be a highly expensive

settling influence for a land whose coffers had been depleted almost to

the extent of emptiness.

The early lines, when laid, were neglected, and consequently fell into

a sorry condition. The majority of people who had regard for their

lives and limbs preferred other vehicles of transport. Everything in

connection with the iron road was conducted in a haphazard manner.

Trains started without any one having the faintest idea as to where

they were going or what time they would reach some destination. Lord

Cromer relates that when he first went to the Land of the Pharaohs all

the lines were single track. No staff or block system of any kind was

in vogue, and there were no signals. A train started from a station

on the off-chance that another train was not coming in the opposite

direction. Needless to say, as he tersely remarks, “he avoided those

lines.”

In the Sudan matters were even worse. The Khedive embarked upon

a laudable enterprise when he decided to carry the iron highway

southwards from Wadi Haifa. Khartoum was the objective, but nearly

half a century passed before the iron horse appeared at the latter

point, for when the Khedive’s railway got so far as Sarras, 33 miles

south, funds became exhausted and the scheme was abandoned. Another

attempt was made in 1885–6, on the occasion of the Nile Expedition,

to resuscitate the scheme, and by great effort another 53 miles were

tacked on from Sarras to Akasha. The life of the second section was

short, for when the British forces retired the track was pulled up by

the dervishes, and Sarras reverted to its position as the southern

terminus.

When Lord Kitchener was deputed to crush the Mahdi for once and for

all, he found 1,200 miles of sandy desert between him in the north

and the seat of the fanatic’s power. The river was available for the

movement of troops as in the previous campaign, but the latter had

emphasised the disadvantages of that highway through hostile territory.

He foresaw that only one agency would enable him to accomplish the

desired end, and that was the railway. Among his officers was a

Canadian engineer, Sir Percy Girouard, and he discussed the possibility

of building a line across the desert to span that inhospitable gap

in order to pour his troops against the Mahdi forces. The engineer

realised the situation and undertook to carry the line southwards from

Wadi Haifa.

The task was commenced in 1896, and railway construction was

pushed forward with such spirited energy that Kerma, at the head

of the cataracts, was gained in a short time. No great engineering

difficulties were offered because the desert is tolerably level, and

the sand provided a good foundation for the steel sleepers, or ties,

with the minimum of ballasting. The greater question was to maintain

the steady supply of requisite material southwards from Alexandria.

Yet an average speed of two miles per day was maintained, the rails

being laid for the most part by natives, assisted by both British and

Egyptians, under the military engineers.

The objective was Abu Hamed, where the Nile describes a big elbow, and

at that time this point was in the hands of the enemy. Its capture,

however, by the Anglo-Egyptian troops resulted in a speeding-up in

constructional work on the advancing railway, and the 80 miles of line

into this town were laid in about two months. Clinging to the east bank

of the river, it was driven southwards to Atbara, where a halt was

called, and where the headquarters were established for the Omdurman

campaign. Curiously enough, although the railway has reached the

capital of the Sudan, Atbara has not yet lost its importance from the

railway point of view, being the administration centre for the whole

Sudan Government railway system.

At this place the Nile is swelled by the waters of the Atbara River,

which flows in from the east. While the campaign was in progress

communication between the opposite banks was maintained by means

of a wooden bridge. As the river, however, is tempestuous when in

flood, during which period it rises to a high level, a more permanent

structure was demanded for the iron horse. The width of the waterway

called for the erection of over 1000 feet of steel bridging. When the

advance of the railhead was determined, it was decided to rush the

railway across the river before it once more rose in flood. Tenders

were invited, only to be received with dismay, because it was found

that the structure required was of such an elaborate character that no

English firm would undertake to complete it within two years.

[Illustration: CONSTRUCTION TRAIN ON THE WAY TO THE RAILHEAD CROSSING A

TEMPORARY TIMBER BRIDGE]

[Illustration:

_Photos by courtesy of A. L. Lawley, Esq._]

THE LONGEST BRIDGE IN AFRICA, 1,300 FEET IN LENGTH, ACROSS THE KAFUE

RIVER

THE CAPE TO CAIRO RAILWAY]

This upset official calculations severely, and accordingly fresh

tenders for a simpler type of bridge were called. The task was

thrown open to the world, and celerity of construction was the

primordial condition. The British firms re-tendered, but to their

disgust they were beaten hopelessly both in regard to the cost of the

structure and the time in which it could be erected by the American

engineers. The result was that the contract went to a Philadelphia

firm. Five weeks after the receipt of the order the steel-work left New

York, and within a further few weeks communication across the river was

provided by 7 spans of steel, each 147 feet long, resting on cast-iron

cylinders.

[Illustration:

[_See page 164_

THE “HANGING BRIDGE,” ONE OF THE RAILWAY ENGINEERING WONDERS OF THE

DENVER AND RIO GRANDE, IN THE ROYAL GORGE OF COLORADO]

The most remarkable feature about this contract was the public outcry

that ensued. British methods were held up in comparison with American

hustle, much to the disparity of the former. British builders were

assailed as lethargic, wedded to obsolete methods, and consequently had

suffered the penalty of such conservatism by being beaten in a most

hollow manner. The same critics, however, failed to shriek so loudly

in acclamation a year later in appreciation of a British firm which

accomplished a feat which even startled the Americans. This was in

connection with a bridge of five spans, each 105 feet long, which was

turned out of a Midland shop to replace the structure which had been

destroyed by the Boers across the Tugela River in Natal. Both British

and American engineers were invited to tender, and the American firms,

despite their wonderful organisation, hustling methods, and their

remarkable facilities for accomplishing quick work, were dismayed to

find that they had been beaten by their British rivals as hollow as

the latter had been vanquished some months before. The successful firm

rolled 100 tons of steel, had it inspected, tested and passed by the

Natal Government engineer in eight hours. It had undertaken to deliver

the first span within six weeks of the receipt of the order--as a

matter of fact, it was completed within nineteen days. The Americans

themselves admitted that the British performance was wonderful, and

that complete revenge had been taken for the Atbara contract.

As the railway pushed its way towards Khartoum, the ranks of the

labourers were swelled by large numbers of dervishes, who had grown

disheartened at the result of their resistance to the British advance

on the northern borders of the Mahdi’s stronghold, had realised the

impotency of their efforts, and consequently had decided to throw in

their lot on the railway. The increased labour enabled the work to be

prosecuted even more energetically, though a certain amount of time was

lost in drilling this raw material into the mysteries of wielding the

white man’s tools.

When the dervishes first saw the locomotive they marvelled. Steam was

beyond their comprehension. They believed stoutly that the engine’s

boiler was packed with animals, and when the driver blew his whistle

many fled in complete terror. To them the agonising shriek of the

animal on wheels was more terrifying than the hail of lead from a Maxim

gun. Indeed, it is reported that one chief, when he saw a locomotive

puffing along slowly and laboriously with its load of cars, went so far

as to assail the British officers for their callous cruelty in making

so small a beast pull such a heavy, long load!

The Atbara bridge, after fulfilling all requirements for eleven years,

had to be reconstructed. It was not found strong enough to withstand

the heavy loads of to-day, for on the Sudan railway weights, lengths

and speeds of trains have increased strikingly during a decade. When

overhaul became imperative, an English firm secured the commission to

rebuild the American structure, and to-day there is nothing left of the

bridge which provoked such acrimonious discussion at the time of its

erection. Owing to the elaborate nature of the building operations a

temporary bridge had to be thrown across the river to carry the railway

traffic.

When Khartoum was gained another pause was unavoidable owing to the

necessity to cross the Blue Nile in order to continue southwards to

Sennar. This arm of the great Egyptian river is fickle, for in times

of flood it rushes along at some 11 miles an hour. The contract for

carrying the railway to the opposite bank was secured by the firm

entrusted with the overhauling of the Atbara bridge, and it is a noble

work of its class. The river being navigable, facilities had to be

provided to permit vessels to pass up and down. This end was met by

introducing an electrically operated rolling lift span working like

a drawbridge. To enable railway construction to be carried on while

the river was being negotiated a temporary timber bridge was thrown

across the waterway. While this was in progress the power of the waters

rushing through this tributary when in flood was emphasised in no

uncertain manner. A considerable quantity of scaffolding intended for

the support of the steel bridge during erection was torn up and hurried

down-stream.

When Sennar was gained, a deviation directly eastward was made in order

to gain El Obeid, which is the centre of the gum trade, one of the most

prosperous and expanding industries of the Upper Sudan. Owing to its

more convenient situation on the main river, Omdurman always has been

the market for this article, the supplies being conveyed across country

by camel caravan. It is generally considered that now El Obeid has

been gained by the railway, that the decadence of Omdurman is certain,

but though this may be inevitable up to a point, the town is always

bound to command a certain position of importance inasmuch as it is the

centre of a considerable pilgrim traffic.

On the advance to El Obeid the bridging of the White Nile had to be

carried out, and here again British engineering triumphed, for the

contract was awarded to the builders of the Khartoum bridge. This

firm, with these two Nile bridges and the Victoria Bridge across the

Zambesi, may be said to have imprinted their name indelibly in Africa

in connection with bridge-engineering. The point of crossing is Goz Abu

Guma, and owing to the erratic character of the White Nile its design

occupied considerable deliberation. This river is sluggish both in time

of flood and in the dry season. Indeed, it might be described as a

huge ditch. When low the water occupies a channel about 1,500 feet in

width, but in the wet season it sprawls across the country for a matter

of three miles or so.

It was decided, however, that the bridging of the normal channel would

suffice, the line being carried over the part subject to periodical

inundation upon well-built embankments. The over-water structure

comprises 9 steel spans each 146 feet in length, and one swing-bridge

span 245½ feet in length to permit navigation up- and down-river,

because the Sudan Development & Exploration Company maintain a

steamship service between Khartoum and Gondoroko, the head of

navigation on the Nile, 1,081 miles from Gordon’s city. The spans are 6

feet above the level of High Nile, and are supported on masonry piers

sunk in steel caissons, or cylinders, under the agency of compressed

air, to a depth ranging between 30 to 50 feet below low water.

Although the iron link has stretched beyond Khartoum to the south,

Alexandria and Cairo are not in through railway communication with the

capital of Sudan, 1,480 miles away. The Egyptian railways have their

most southerly outpost at Shellal, just below Assuan, which is about 24

hours’ journey from the Mediterranean seaboard by the White _de luxe_

express. The terminal of the Sudan system is at Haifa, just south of

the border between the two countries. The river Nile constitutes the

artery of communication between these two railway points, the steamer

occupying about 40 hours. This break in the iron chain possesses

distinct drawbacks, the most serious of which is transhipment between

steamer and railway. The expense and inconvenience of this route,

with its breaking bulk, reacted severely upon the Upper Sudan, and

accordingly the latter Government decided to secure an independent

outlet to the coast. There was only one means of accomplishing this

end, and that was to strike eastwards across country to gain the Red

Sea.

This was not a simple enterprise, especially under conditions which

did not lend themselves to the expenditure of a large sum of money.

An easy graded line was imperative, and the surveyors had to search

diligently for such a route, because a range of hills breaks away from

the northern edge of the Abyssinian plateau, to run parallel with the

coast-line of the Red Sea to the Gulf of Suez. Investigations along the

coast resulted in Suakin, 305 miles distant from Atbara, being selected

as the sea terminus, and the surveyors succeeded in securing a location

giving no banks heavier than one per cent., and with no curves of a

sharper radius than 1,155 feet.

As the constructional engineers were confronted with some heavy work

shortly after leaving Suakin, in order to overcome the coast range,

building was commenced from both ends of the line simultaneously. This

procedure, however, did not prove entirely satisfactory, owing to the

cost and delay in bringing material down from Alexandria to Atbara,

so when the engineers at the Suakin end had subjugated their obstacle

and the material could be landed easily from vessels and hurried to

the railhead, operations were suspended from Atbara. The remoteness of

Suakin, however, produced individual handicaps, the greatest of which

was in regard to labour. The scattered natives were given employment,

but as they were unfamiliar with the tools and methods they did not

prove successful, and large numbers of Egyptians who had toiled on the

other lines were shipped to the Red Sea terminus. They were housed in

military tents, and a stranger happening suddenly upon a railway camp

might have been pardoned for labouring under the impression that he had

alighted upon an invading army under canvas, because the tents were

pitched in such regular rows as to indicate military occupation.

The mountains occasioned some little anxiety owing to the damage that

was caused by wash-outs due to the heavy rain, but these were soon

mastered. This abundance of water later on gave place to extreme

scarcity, for when the constructional forces had penetrated the heart

of the desert, this commodity was found only with great difficulty and

by infinite labour.

Despite these drawbacks, however, the 305 miles of line were laid and

opened for traffic within the short space of 14 months, which testifies

to the high standard of the constructional organisation and the energy

with which the undertaking was pushed forward. The significance of

this branch from the Nile to the sea was revealed instantly, but

unfortunately it was realised that the terminal point on the coast

left much to be desired. Further investigation revealed a better site

for a harbour 50 miles north of Suakin, and this point, now known as

Port Sudan, is the terminus of the line, the harbour being equipped

with modern facilities for handling traffic between ship and railway.

The new port is connected by rail with Suakin, however, which is being

retained as an outlet.

The railway will creep gradually southwards along the bank of the White

Nile in all probability, but in the meantime the river will constitute

the artery of communication. The waterway abounds with sand-bars and

other obstructions to navigation which provide very little depth of

water in some places, but the Sudan Development & Exploration Company

have met this situation by the utilisation of steamers which draw

extremely little water and are able to pass through the shallows

in perfect safety. The Sudan Government also maintains a steamship

connection between Khartoum and Gondoroko. This water link is about

1000 miles in length, and the round trip occupies about 23 days. A few

years ago the possibility of being able to proceed so far up the river

under steam was feared to be impracticable, owing to the dense masses

of floating tangled masses of vegetation, or “sudd,” which blocked the

river. But this has been broken up and a clear fairway is maintained.

As a result, Uganda now has an outlet to the Mediterranean which can be

developed considerably as the northern extremities of that country are

opened up.

Unfortunately, beyond Gondoroko the river cannot be used, because for

about 100 miles--from Rejaf to Dufile--there is a continuous chain

of rapids. These two points therefore will be connected by railway

probably. When Dufile is gained the river can be used once more so far

as Lake Albert Nyanza, where the line from Cape Town would be met,

although there is a belief that the Sudan Government intends to push

the railway to a far more southern point.

It will be seen that although Rhodes’ great scheme was for a continuous

steel road from north to south, this idea has had to be modified in

order to meet unexpected conditions, which at the time of the railway’s

inception were not apparent. In reality one will travel from the “Cape

to Cairo” over a combined rail and water route longitudinally through

the continent. At the present moment one can cover the whole journey

by rail and water, except for a distance of about 600 miles, and this

gap is being closed rapidly. As the settlement of the country along

the line of communication becomes effected, and the heavy drawbacks

incidental to transhipment become more and more emphasised, there is

no doubt but that the water route will be superseded gradually by the

railway, so that in time the original idea will be consummated, and

trains will pass right through from the Cape to Cairo over a continuous

path of steel some 6000 miles in length.