THREE-TRACK TUNNEL LINING.

In the Three-Track Tunnels, a heavy brick arch was used for those

portions constructed in tunnel, while, in the open-cut sections, the

roof was of concrete. Both were completely water-proofed on the roof and

sides, and in the tunnel sections the space above the brick roof was

filled with rock packing. On account of the unstable nature of the rock

encountered throughout, the voids in the packing were afterward filled

with grout.

By reference to the cross-sections, Plate XII, it will be seen that the

haunches of the arch were tied together by steel I-beams anchored in the

concrete, with the object of making the structure self-supporting in the

event of the removal of the adjacent rock for deep cellar excavations.

This construction materially influenced the contractor's method of

placing the masonry lining.

After depositing the floor concrete, by the same method that was used in

the Twin Tunnels, a timber trestle (Fig. 2, Plate LXII) was erected to

the height of the underside of the I-beam ties, the posts being footed

in holes, about 3 in. deep, left in the concrete floor to prevent

slipping. In the open-cut sections the sand-wall forms were of undressed

plank tacked to the studding and braced from the trestle; in the tunnel

section they were spiked to the face of the posts supporting the

timbering.

The side-wall forms were made up in panels about 3 by 10 ft., and were

clamped to studs by U-shaped irons passing around the stud and bolted to

the cleats on the back of the panels, the studs being braced from the

trestle. The side-wall concrete was deposited in three sections. The

first was brought up just above the sidewalk and formed the bench for

the high-tension ducts; the second carried the wall up to the springing

line. Before placing the third section the I-beam ties were set in

position (Fig. 3, Plate LXII) on top of the trestle, and the reinforcing

rods in the haunch of the arch were hung from them. The concrete was

carried up to a skewback for the arch, as shown in the brick-roof

cross-section (Plate XII) and embedded the ends of the ties.

The centers for the arches stood on the I-beam ties, and the tops of the

hangers, for the permanent support of the ties near their center, were

inserted through the lagging. The brick arch, water-proofing, and rock

packing were laid up in lifts, in the same manner as in the Twin Tunnel,

with grout pipes built in at intervals of about 8 ft. The concrete arch

was placed in sections, from 25 to 50 ft. in length, with a rather wet

mixture and a back form on the steep slope of the extrados.

The concrete for the sand-walls and lower part of side-walls was handled

on tracks and platforms laid on cantilever beams at mid-height of the

trestle, as shown by Fig. 3, Plate LXII. For the walls above the

springing line, the tracks were laid on top of the I-beam ties, and some

of the arch concrete, also, was delivered from the mixer at that level

and hauled up an incline to the level of the top of the arch. By far the

greater part, however, was turned out from mixers set on the completed

arch, and was transported on tracks hung in part from the street

timbering.

_Completion._--Except in the heavily-timbered portions, such as at Fifth

Avenue, where the load had to be transferred from posts to the completed

masonry section by section, the lining of the tunnels presented no

special difficulty. The large number of small forms to be set, and the

mutual interference of the concreting and duct-laying operations proved

to be the most troublesome features of the work.

The restoration of the streets, public utilities, etc., at the open-cut

sections was a slow and tedious operation, but the tunnels themselves

were completed in March, 1909, 3 years and 10 months after the inception

of the work. The finished tunnels are shown by the photograph, Fig. 4,

Plate LXII, taken at the junction of the twin and three-track types.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The Cross-Town Tunnels. Paper No. 1158 · 第 15 / 16 题