THREE-TRACK TUNNEL EXCAVATION.

When it became evident that the work through the Fifth Avenue section

would be extremely slow, shafts were sunk in each street between Sixth

and Seventh Avenues. The shafts, as shown on Plate XIV, were located in

the streets, but in such a way as to block only half of the roadway. At

the same time it was decided to construct in open cut about 200 ft. of

the Three-Track Tunnel at the west end of the contract in 32d Street,

where the rock surface was below the top of the tunnel. It was hoped

that the remainder of the work could be built without opening the

street, but further investigation showed that this was impracticable,

and eventually all the Three-Track Tunnel in 32d Street, except 120 ft.

east of the shaft, was built in open cut.

_Thirty-second Street Work in Tunnel._--Following the sinking of the

shaft, a drift was driven across the street at the crown of the tunnel,

and a top heading on the south side was excavated in both directions.

Frequent cross-drifts to the north side showed that the rock was nowhere

very sound and that, except for a short distance east of the shaft, it

was distinctly unfavorable for the wide Three-Track excavation. In this

stretch the north ends of these cross-cuts were connected by a second

heading, and wall-plates and sets of three-segment arch timbering were

set up to support the roof of the drifts. The cross-cuttings were

gradually widened and timbered until the entire excavation had been made

down to the level of the wall-plates, as shown in Fig. 3, Plate LX. The

bench was then excavated in two lifts, leaving the wall-plates supported

on narrow longitudinal berms, which were removed in short sections to

permit the placing of posts under the wall-plates.

_Thirty-second Street Open-Cut Work._--Before actual open-cut excavation

was started, all buildings facing it were underpinned to rock. For this

purpose, a trench was dug along the face of the buildings and of the

same depth as their cellars. Holes were cut in the front foundation

walls through which long needle-beams (Fig. 4, Plate LX) were inserted

and jacked up on blocking placed on the cellar floor and in the trench,

until the weight of the building had been taken off its foundations. A

close-sheeted trench was then sunk to rock under the front building

walls, and a light rubble masonry retaining wall was built in it to

support the building permanently. Frequently, the excavation for the

underpinning wall, which was taken out in sections from 30 to 40 ft.

long, and in places was carried to a depth of 40 ft., was very

troublesome on account of the large quantity of water encountered and

the fineness of the sand, which exhibited a tendency to flow when

saturated.

The Elevated Railroad columns in Sixth Avenue, near the north and south

lines of 32d Street, were underpinned in a manner similar to the

building foundations, while those on the center line of the street were

supported by girders riveted to them close under the track level. The

girders in turn were supported on posts footed on the new underpinning

of the adjacent columns. On the completion of the tunnels, concrete

piers were built up from the roof of the tunnel to form a permanent

foundation for the center-line columns. The area to be excavated under

Sixth Avenue was enclosed by a rubble masonry retaining wall constructed

in a trench.

Open-cut excavation was started by planking over the street on stringers

resting on transverse 12 by 12-in. caps. The caps were gradually

undermined and supported on temporary posts which were then replaced by

short posts resting on 12 by 12-in. sills about 7 ft. below the cap. The

operation was then repeated and the sill was supported on another set of

short posts resting on a second sill. When the excavation had been

carried down in this manner to the level of the top of the tunnel,

diagonal 3 by 10-in. timbers were cut in between the posts and sills to

form a species of double A-frame, the legs of which rested in niches cut

in the rock and on posts carried up the face of the underpinning wall,

and the whole was stiffened with vertical tie-rods. This construction is

shown by Fig. 3, Plate LXII. The brick sewer was replaced temporarily by

one of riveted steel pipe. This pipe and the water and gas pipes and

electric conduits were suspended from the timbers as the pipes were

uncovered.

Excavation in rock was made by sinking a pit to sub-grade for the full

width of the tunnel and advancing the face of the pit in several lifts,

the muck being blown over the slope and loaded into buckets at its foot.

The work was attacked at several places simultaneously, and the spoil

was hoisted by derricks located at convenient points along the side of

the cut.

_Thirty-third Street Work in Tunnel and Open Cut._--The West 33d Street

Shaft was similar to the one in 32d Street, and was sunk during

February, March, and April, 1907, through 10 ft. of earth, 21 ft. of

soft rock, and 29 ft. of fairly hard rock. It was necessary to timber

heavily the upper 30 ft. of the shaft. The timber later showed evidences

of severe strain, and had to be reinforced.

[Illustration: Plate LXI.--EXCAVATION AND TIMBERING IN HEAVY GROUND

OF THREE-TRACK TUNNEL OF 33D ST.]

As soon as the shaft excavation was deep enough, a drift was driven

part way across the tunnels, and top headings were started both east and

west to explore the rock. The heading to the west was divided into two

drifts, as shown on Plate LXI. These two drifts were continued to the

west end of the contract, and were then enlarged to a full-sized heading

and timbered, as shown on Plate LXI and Fig. 3, Plate LX. The rock near

the shaft contained many wet rusty seams, and settlement was detected in

the segmental tunnel timbering soon after the widening of the heading

was completed. Short props were placed under the timbers, and the street

surface was opened with a view of stripping the earth down to the rock

and thus lightening the load on the timbering. Street traffic was

maintained on a timber structure with posts eventually carried down to

the rock surface, and the walls of the buildings on the north side of

the street were underpinned to rock. The settlement of the tunnel

timbering was checked for a time, and the bench was excavated as shown

on Plate LXI. In this work the cut in the center was first made, and the

short props were replaced by struts, as shown; after this the berms were

removed and the side posts were placed. While building the brick arches,

holes were left in the masonry around the struts. After the masonry had

hardened, piers were built on the arches to support the segmental

timbers. The struts were then removed and the openings filled with

masonry. The voids above the arch were packed with rock and afterward

thoroughly grouted.

The timbers near the shaft continued to settle, and, although they had

been placed from 9 to 12 in. above the level of the top of the masonry,

by October 1st, they encroached 9 in. within the line of masonry. It was

then decided to remove the rock for a distance of 48 ft. west of the

shaft, and build this portion of the tunnel in open cut. The posts

supporting the deck forming the street surface were replaced by an

A-frame structure similar to that developed for the 32d Street open cut,

without interruption of the street traffic.

After making the open cut to the westward of the shaft, there was a slip

in the rock north of and adjoining the shaft. Fortunately, the timbers

did not give way entirely, and no damage was done. The open cut was

extended eastward for a distance of 46 ft., making the total length of

tunnel built in open cut on this street 94 ft.

East of the shaft, for a distance of about 125 ft., the rock was broken

and could not be excavated to full size without timbering the roof, but

between this section of poor rock and those already mentioned in

connection with the work at Fifth Avenue, there was a stretch of 600 ft.

of good rock where all the spoil was handled with a steam shovel.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The Cross-Town Tunnels. Paper No. 1158 · 第 13 / 16 题