PROGRESS OF EXCAVATION.

Owing to the numerous sections of poor rock, interspersed throughout the

work with stretches of sound rock, the progress of the excavation was

very irregular, especially in 32d Street. The rate of excavation in good

ground is shown in Table 1. In the sections of bad ground, the

operations of excavation, timbering, and lining were often carried on

alternately, and it is impracticable to include them in the table.