TUNNEL EXCAVATION.

During the early part of the work, the contractor devoted his entire

attention to the work of excavation. Nearly all the excavation east of

Fifth Avenue was done before any of the lining was placed. At a number

of points west of Fifth Avenue and at a few points to the east the

nature of the rock was such that the two operations had to be done

simultaneously.

_Single-Tunnel Method._--For an average distance of 350 ft. west from

the First Avenue Shafts there were four single tunnels. The rock was

sound and comparatively dry. A top heading of the full size of the

tunnel and about 8 ft. high was first driven. It was drilled by four

drills mounted on two columns, and was blasted in the ordinary way. The

bench was about 13 ft. high. Tripod drills, standing on the bench,

drilled the usual holes, but, owing to the lack of head-room, steels

long enough to reach the bottom of the bench could not be used. Tripod

drills were set as low as possible at the foot of the bench and drilled

lifting holes. These holes were inclined downward from 10° to 15° to the

horizontal, and were spaced to converge at the location of the drainage

ditches. The heading was usually driven from 10 to 20 ft. in advance of

the bench. At this distance a large part of the muck from the heading

was shot backward over the bench. In the single tunnels the muck was

loaded by hand.

_Twin-Tunnel Methods._--From the end of the single-track tunnel westward

to Fifth Avenue on 33d Street, and to Madison Avenue on 32d Street, with

some exceptions, each pair of tunnels was excavated for the entire width

at one operation. Three different methods of work were extensively used.

They were the double-heading method, the center-heading method, and the

full-sized-heading method, and these differed only in the manner of

drilling and blasting. The bench was usually within 10 or 15 ft. of the

face of the heading, and was drilled and fired in the same way as in the

single tunnels. After the installation of the permanent plant, most of

the muck was handled by steam shovels.

In the double-heading method, shown on Plate LVII, the top headings for

each tunnel of the pair were driven separately, leaving a short rock

core-wall between them. The headings were drilled from columns in the

manner described for the single tunnels. The temporary rock dividing

wall between the headings was drilled by a tripod drill on the bench of

one of the headings, and was fired with the bench.

In the center-heading method, also shown on Plate LVII, only one heading

was driven. It was rectangular in shape, about 8 ft. high and 14 ft.

wide. It was located on the center line between the tunnels. In general,

the face was from 6 to 12 ft., or the length of one or two rounds, in

advance of the remainder of the face at the top. The center heading was

drilled by four drills mounted on two columns. By turning these drills

to the side, they were used for holes at right angles to the line of the

tunnels, by which the remainder of the face of the heading was blasted.

By turning the drills downward, the bench holes under the center heading

were also drilled. The center heading explored the rock in advance of

the full-width heading, and gave a good idea as to the care needed in

firing.

For the full-width-heading method, Fig. 2, ten drills were mounted on

five columns set abreast across the face. Holes were drilled to form a

cut near the center line between the tunnels. The remainder of the holes

were located so that they would draw into the cut. The bench was

frequently drilled from the same set-up of columns by turning the

drills downward. In sound rock this method proved to be the most rapid

of any.

Practically all trimming was left until immediately before the

concreting. It was then taken up as a separate operation, but proved to

be costly and tedious, and a hindrance to the placing of the lining.

_Materials Encountered._--All the rock encountered was the familiar

Hudson schist, but it varied widely in its mineral constituents and in

its physical characteristics. In many places where the rock surface was

penetrated, a fine sand was found that was probably quicksand. The

material above the rock in the open-cut sections was mostly sand.

[Illustration: FIG. 2. METHOD OF EXCAVATING WITH FULL-WIDTH HEADING

CROSS-TOWN TUNNELS, MANHATTAN

SIDE ELEVATION

FRONT ELEVATION

PLAN SHOWING POSITION OF COLUMNS FOR DRILLING FACE]

The concurrence of the watercourse, shown on General Viele's map of

Manhattan Island (Plate IX[D]), with the points where difficulties in

the construction of the tunnels were encountered has been noted in a

previous paper.

In all cases where the course of this ancient stream was crossed (except

at its final intersection of 33d Street), the rock was found to be very

soft and disintegrated, a large quantity of water was encountered, and

heavy timbering was required. The construction at these localities will

be taken up later. In addition, disintegrated rock, but of a less

troublesome character, was invariably met under the depressions in the

rock surface developed by the borings from the streets and test holes

from the tunnels. Many of these places required timbering, and no

timbering was elsewhere necessary except at the portals. These

coincident conditions were especially marked in 32d Street, which for a

long distance closely adjoins the course of the former creek.

_Disposal of Spoil._--The materials excavated from the tunnels were

dumped at the 35th Street pier on barges furnished by the Railroad

Company under another contract, and were towed to points near the

Bayonne peninsula where the spoil was used principally in the

construction of the Greenville Freight Yards and the line across the

Hackensack Meadows to the tunnels. Details of this work will be given in

a subsequent paper. After December, 1907, when the excavation was about

85% completed, the contractor furnished the barges and effected the

complete disposal of the spoil.

_Difficulties of Excavation._--As stated in a previous paper, the

excavation of the Twin Tunnel in 33d Street was continued westward to

the west line of Fifth Avenue on the original grade. At that point the

contractor started three drifts in the three-track section. The relation

of the drifts to each other and to the cross-section are shown by Fig. 3.

The center heading was driven a little in advance of those on the

sides. At a distance of 65 ft. west of Fifth Avenue the rock surface was

broken through in the top of the heading, and a very fine sand was

encountered. For some distance east of this point the rock was badly

disintegrated, and the heading required timbering. Through the soft

material, tight lagging was placed on the sides and roof of the heading,

and the face was protected by breast boards. There was a moderate flow

of water through the cracks, and, in spite of every effort, some of the

fine sand was constantly carried into the heading.

In one or two instances considerable ground was lost at the face. On the

evening of December 14th, 1906, as a heavy coal wagon was passing along

33d Street above the heading, the rear wheels dropped through the

asphalt pavement. An examination disclosed a cavity under the pavement

about 14 ft. long, 12 ft. wide and 14 ft. deep. Evidently, the fine sand

had gradually settled into the voids caused by the loss of material at

the face, and the settlement broke the brick sewer over the heading. The

sewer was temporarily repaired, and the hole in the street was filled

before morning. A tight bulkhead was built across the heading, and work

was abandoned at that point. The north drift was advanced to a point

108 ft. west of Fifth Avenue where sand was also encountered and a

considerable run occurred. After that time all work on the three-track

section was discontinued.

The Company then took up the consideration of changes in plan. To

determine the difficulties of driving a Twin Tunnel at a lower

elevation, an exploration drift, 8 ft. high and 12 ft. wide, was driven

on the center line of the street as a top heading on the proposed new

grade. Test holes were drilled above this heading and to the sides. The

results indicated that there was sufficient rock cover of fair quality

to enable the Twin Tunnel to be driven without great risk. The new plan

(continuing the Twin Tunnel westward at a lower grade) was adopted in

March, 1907, and work was immediately resumed at Fifth Avenue.

The relation between the cross-sections under the old and new plans at

that point is shown by Fig. 3. Before the new section was excavated it

was necessary to support the timber work in the old headings. The plan

adopted is also shown by Fig. 3. The rock was excavated under the center

heading, as shown in cross-section, for a length of about 3 ft. A girder

composed of two 18-in. I-beams was then put in position over each line

and supported on the sides by posts. The ends at the center lines

between the tunnels were supported on short posts bearing on the rock

bench. The support of the timbering in the headings was then transferred

to the girders by additional posts. Blocking was also inserted between

the tops of the beams and the rock walls between the headings. Fig. 2,

Plate LIX, gives a good idea of the timber work in the top headings

above the I-beams. When the roof had been made secure, the removal of

the bench was begun. As the work advanced it was necessary to replace

the short posts at the center of the tunnel by others of full height,

and there was considerable settlement in the I-beams during this

operation. When the bench had been removed to a point 61 ft. west of

Fifth Avenue, settlement was detected in the street surface above. Bench

excavation was suspended and a section of the permanent lining, 35 ft.

long, was placed. The space between the lining and the beams and between

the beams and the roof was filled with rubble masonry. Grout pipes were

built into the masonry and later all voids were filled with grout. Fig.

3, Plate LIX, shows the first section of the concrete lining completed

and part of the rubble in place; and Fig. 4, Plate LIX, shows details of

the work above the tunnels. A second section of bench was next removed

and more lining was placed. Work was continued in this way until all the

roof at the old three-track headings had been secured. In this portion

of the work the posts were embedded in the concrete.

Between Fifth and Sixth Avenues there were two more sections of bad rock

where it was necessary to support the roof with steel beams. At these

latter points there were no complications with the excavation for the

Three-Track Tunnel, and the work was much simpler. To avoid leaving the

center posts in the permanent work, two rows of temporary posts were

placed, as shown by Fig. 1, Plate LX, the center wall and skewback were

built, and the posts were removed, as shown by Fig. 2, Plate LX, before

placing the remainder of the lining.

In 32d Street the normal progress of the excavation was frequently

interrupted by encountering soft and unsound rock. In the excavation

between the East River and the Intermediate Shafts it was possible to

overcome these conditions by temporarily narrowing the excavation on one

side and supporting the roof on 16 by 16-in. transverse timbers caught

in niches in the rock at the sides, leaving sufficient room for the

steam shovel to work through. In order to save time, the height of the

excavation was not increased before placing these timbers, so that,

previous to the concreting, they all required to be raised to clear the

masonry lining and were then supported on posts on the center line

between the tunnels. This permitted the remainder of the excavation to

be made, and such additional timbering as was required was placed. At

most of these sections a brick arch and water-proofing were used, on

account of the presence of water. In certain places the center line

posts were buried in the core-wall, and, in order to permit the placing

of the water-proofing, were then cut off one by one flush with its top

as the load was transferred to the completed masonry. In other cases the

load was transferred to posts clear of the masonry and the center line

posts were entirely removed. Under such conditions the normal concrete

methods, to be described later, could not be used, and special forms

were substituted.

[Illustration: FIG. 3. CONSTRUCTION OF TWIN TUNNELS, THROUGH EXCAVATION

STARTED FOR THREE-TRACK TUNNEL IN 33D STREET NEAR 5TH AVENUE]

In this section of the work the most serious difficulties were

encountered near Fourth Avenue a short distance east of the Intermediate

Shaft, and beneath the site of the old pond shown on General Viele's

map. The rock cover was known from the boring to be very thin, and the

presence of the subway overhead caused some anxiety. The excavation was

at first taken out to practically full width and timbered, but the rock

became so treacherous that the heading was narrowed to a width

sufficient for one tunnel only. With this span the rock in the roof held

without timbering. As the masonry lining approached, sufficient trimming

was done to permit the placing of the core-wall and one arch. Above the

completed core-wall and brick arch the voids were filled solid with

rubble masonry to give an unyielding support to the roof. The excavation

of the remaining width of tunnel was then undertaken. Near the west side

of Fourth Avenue, the excavation broke out of rock at the top, and fine

sand and gravel with a large quantity of water were encountered. The

work of excavation was arduous, and proceeded very slowly, on account of

the care with which it was executed. Only a small amount of sand entered

the tunnel, but the lining was placed as soon as the excavation was

completed. Rubble masonry packing and grout ejected through pipes built

into the arch were used to fill the voids above the roof. As a further

precaution against the settlement of the subway, 2-in. pipes were washed

down from the street above the point where soft ground was exposed in

the roof of the tunnel, and through them grout was forced into the

ground at various depths. Careful levels show that no settlement of the

subway has taken place.

West of the Intermediate Shaft the tunnel was excavated for full width

until bad rock was encountered about 60 ft. west of Madison Avenue. (See

General Viele's map, Plate IX.) Timbering was used for a short distance,

and then the heading and bench were narrowed to 18 ft., and steam-shovel

excavation was abandoned. As the heading advanced the rock grew steadily

softer, the difficult conditions in this locality culminating when a

slushy disintegrated feldspar was met, requiring poling and breasting.

Thereafter the rock improved markedly, but near the east side of Fifth

Avenue its thickness above the roof was found to be only 1-1/2 ft.,

and the advance was stopped, pending a decision as to a change of plan.

[Illustration: PLATE LX, FIG. 1.--DOUBLE ROW OF POSTS UNDER I-BEAMS,

SUPPORTING ROOF IN BAD ROCK SECTION.]

[Illustration: PLATE LX, FIG. 2.--CENTER WALL AND SKEWBACK UNDER I-BEAMS,

AFTER REMOVAL OF DOUBLE ROW OF POSTS.]

[Illustration: PLATE LX, FIG. 3.--TIMBERING IN FULL-WIDTH HEADING OF

THREE-TRACK TUNNEL.]

[Illustration: PLATE LX, FIG. 4.--UNDERPINNING WALLS IN OPEN-CUT

SECTION.]

After some delay, an exploration drift, similar to the one already

described, was driven through to Sixth Avenue, and a change in plan was

made, substantially the same as for the 33d Street tunnels. Enlargement

to full size was at once started, but, for 400 ft. the rock was very

soft and poor, and required extremely careful handling. The exploration

drift was widened out to the full Twin-Tunnel width, and I-beams were

placed and supported, in much the same manner as in 33d Street. The rock

was so soft that it was frequently necessary to drive poling boards

ahead as the face was mined out with picks and shovels. The load was

very heavy, and the work the most difficult encountered in the tunnels.

After this stage of the enlargement was reached, the excavation of the

bench and the placing of the lining proceeded alternately, with the

I-beams temporarily supported on long posts while the concrete core-wall

was being built. Considerable settlement took place while shifting the

posts, and eventually showed on the street surface and in the adjacent

sidewalk vaults, but no damage was done to the structural portions of

the buildings.

While the above work had been going on westward from Fifth Avenue, the

excavation of the Twin Tunnel eastward from the end of the open-cut

section at Sixth Avenue had been proceeding rapidly, and, toward the end

of the difficult Fifth Avenue work, it was being attacked from both

directions.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The Cross-Town Tunnels. Paper No. 1158 · 第 8 / 16 题