Or, as a total for the entire streets and roads of London,--

Relaying 400 miles of granite-built £

streets, at 11,000_l._ per mile 4,400,000

Relaying 1350 miles of macadamized

streets, at 4400_l._ per mile 5,940,000

Relaying five miles of wood-built

streets, at 9680_l._ 48,400

-----------

£10,388,400

But the above refers only to the road, and besides this, there is, as

a gentleman to whom I am much indebted for valuable information on

the subject, reminds me, the foot paving, granite curb, and granite

channel not included. The usual price for _paving_ is 8_d._ per foot

superficial, when laid--granite curb 1_s._ 7_d._ per foot run, and

granite channel 12_s._ per square yard.

“Now, presuming that three-fourths of the roads,” says my informant,

“have paved footpaths on each side at an average width of six feet

exclusive of curb, and that one-half of the macadamized roads have

granite channels on each side, and that one-third of all the roads

have granite curb on each side; these items for 400 miles of granite

road, 1350 macadamized, and 5 miles of wood--together 1755 miles--will

therefore amount to

£ _s._ _d._

Three-fourths of 1755 miles of

streets paved on each side,

six feet wide, at 8_d._ per foot

superficial 2,779,392 0 0

One-half of 1350 miles of macadamized

roads with one foot

of granite channel on each

side, at 12_s._ per yard square 458,537 4 5

One-third of 1755 miles of road

with granite curb on each

side, at 1_s._ 7_d._ per foot run 489,060 0 0

---------------------

3,726,989 4 5

Cost of constructing 1755 miles

of roadway 10,388,400 0 0

----------------------

Total cost of constructing the

streets of London £14,115,389 4 5

“Accordingly the original cost of the metropolitan pavements exceeds

fourteen millions sterling, and, calculating that this requires

renewal every five years, the gross annual expenditure will be at the

rate of 2,500,000_l._ per annum, which, added to 1,822,500_l._, gives

4,322,500_l._, or upwards of four millions and a quarter sterling for

the entire annual cost of the London roadways.

“From rather extensive experience,” adds my informant, “in building

operations, and consequently in making and paying for roads, I am of

opinion that the amount I have shown is under rather than above the

actual cost.

“In a great many parts of the metropolis the roads are made by the

servants of a body of Commissioners appointed for the purpose; and

from dear-bought experience I can say they are a public nuisance, and

would earnestly caution speculating builders against taking building

ground or erecting houses in any place where the roads are under

their control. The Commissioners are generally old retired tradesmen,

and have very little to occupy their attention, and are often quite

ignorant of their duties; I have reason to believe, too, that some of

them even use their little authority to gratify their dislike to some

poor builder in their district, by meddling and quibbling, and while

that is going on the houses which have been erected can neither be let

nor sold; so that as the bills given for the materials keep running,

the builder, when they fall due, is ruined, for his creditors will not

take his unlet houses for their debts, and no one else will purchase

them until let, for none will rent them without proper accesses.

I feel certain that in those parts where the roads are made by

Commissioners three times more builders, in proportion to their number,

get into difficulties than in the districts where they are permitted to

make the roads themselves.”

The paved ways and roads of London, then, it appears, cost in round

numbers 10,000,000_l._ sterling, and require nearly 2,000,000_l._ to be

expended upon them annually for repairs.

But this is not the sole expense attendant upon the construction of

the streets of the metropolis. Frequently, in the formation of new

lines of thoroughfare, large masses of property have to be bought up,

removed, and new buildings erected at considerable cost. In a return

made pursuant to an order of the Court of Common Council, dated 23rd

October, 1851, for “An account of all moneys which have been raised

for public works executed, buildings erected, or street improvements

effected, out of the Coal Duties receivable by the Corporation of

London in the character of trustees for administration or otherwise,

since the same were made chargeable by Parliament for such purposes in

the year 1766,” the following items are given relating to the cost of

the formation of new streets and improvements of old ones:--

_Street Improvements forming New Thoroughfares._

Amount raised

for Public

Works, &c.

Building the bridge across the river £. _s._ _d._

Thames, from Blackfriars, in the city

of London, to Upper Ground-street, in

the county of Surrey, now called

Blackfriars Bridge, and forming the

avenues thereto, and embanking the

north abutment of the said bridge--(Entrusted

to the Corporation of the

city of London) 210,000 0 0

Making a new line of streets from Moorfields,

opposite Chiswell-street, towards

the east into Bishopsgate-street

(now Crown-street and Sun-street),

also from the east end of Chiswell-street

westward into Barbican--(Corporation

of the city of London) 16,500 0 0

Making a new street from Crispin-street,

near Spitalfields Church, into Bishopsgate-street

(now called Union-street),

in the city of London and in the

county of Middlesex--(Commissioners

named in Act 18, George III., c. 78) 9,000 0 0

Opening communications between Wapping-street

and Ratcliffe-highway, and

between Old Gravel-lane and Virginia-street,

all in the county of Middlesex--(Commissioners

appointed under Act 17, Geo. III., c. 22) 1,000 0 0

Formation of Farringdon-street, removal

of Fleet-market, and erection of Farringdon-market,

in the city of London--(Corporation

of the city of London) 250,000 0 0

Formation of a new street from the end

of Coventry-street to the junction of

Newport-street and Long-acre (Cranbourn-street),

continuing the line of street from Waterloo

Bridge, already completed to Bow-street (Upper

Wellington-street), and thence northward into

Broad-street, Holborn, and thence

to Charlotte-street, Bloomsbury, extending

Oxford-street in a direct line

through St. Giles’s, so as to communicate

with Holborn at or near Southampton-street

(New Oxford-street); also widening the northern

and southern extremities of Leman-street,

Goodman’s-fields, and forming a new

street from the northern side of

Whitechapel to the front of Spitalfields

Church (Commercial-street),

and forming a new street from Rosemary-lane

to East Smithfield, near to

the entrance of the London-docks;

also formation of a street from the

neighbourhood of the Houses of Parliament

towards Buckingham Palace,

in the city of Westminster (Victoria-street),

all in the county of Middlesex;

also formation of a line of new street

between Southwark and Westminster

Bridges, in the county of Surrey--(Her

Majesty’s Commissioners of

Woods, Forests, and Land Revenues) 665,000 0 0

NOTE.--The Commissioners of Her

Majesty’s Woods have been authorised

to raise further moneys on the

credit of the duty of 1_d._ per ton for

further improvements in the neighbourhood

of Spitalfields, but the

Chamberlain is not officially cognizant

of the amount.

Forming a new street from the northern

end of Victoria-street, Holborn (formed

by the Corporation to Clerkenwell-green,

all in the county of Middlesex)--(Clerkenwell

Improvement Commissioners) 25,000 0 0

Formation of a new line of streets from

King William-street, London Bridge,

to the south side of St. Paul’s Cathedral,

by widening and improving

Cannon-street, making a new street

from Cannon-street, near Bridge-row,

to Queen-street, and another street

from the west side of Queen-street, in

a direct line to St. Paul’s-churchyard,

and widening Queen-street, from the

junction of the said new street to

Southwark Bridge; also improving

Holborn Bridge and Field-lane, and

effecting an improvement in Gracechurch-street

and Ship Tavern-passage,

all in the city of London--(Corporation

of the city of London) 500,000 0 0

Finishing the new street left incomplete

by the Clerkenwell Improvement Commissioners,

from the end of Victoria-street,

Farringdon-street, to Coppice-row,

Clerkenwell, all in the county of

Middlesex--(Corporation of the City

of London) 88,000 0 0

-------------------

Total cost of forming the above-mentioned

new thoroughfares 1,764,500 0 0

_Improving existing Thoroughfares._

Improving existing approaches, and

forming new approaches to new London

Bridge, viz., in High-street,

Tooley-street, Montague-close, Pepper-alley,

Whitehorse-court, Chequer-court,

Chaingate, Churchyard-passage,

St. Saviour’s churchyard, Carter-lane,

Boar’s-head-place, Fryingpan-alley,

Green Dragon-court, Joyner-street,

Red Lion-street, Counter-street, Three

Crown-court, and the east front of

the Town Hall, all in the Borough of

Southwark; also ground and premises

at the north-west foot of London

Bridge, Upper Thames-street, Red-cross-wharf,

Mault’s-wharf, High

Timber-street and Broken-wharf,

Swan-passage, Churchyard-alley, site

of Fishmonger’s Hall, Great Eastcheap,

Little Eastcheap, Star-court,

Fish-street-hill, Little Tower-street,

Idol-lane, St. Mary-at-hill, Crooked-lane,

Miles-lane, Three Tun-alley,

Warren-court, Cannon-street, Gracechurch-street,

Bell-yard, Martin’s-lane,

Nicholas-lane, Clement’s-lane, Abchurch-lane,

Sherborne-lane, Swithin’s-lane,

Cornhill, Lombard-street,

Dove-court, Fox Ordinary-court, Old

Post Office Chambers, Mansion-house-street,

Princes-street, Coleman-street,

Coleman-street-buildings, Moorgate-street,

London Wall, Lothbury,

Tokenhouse-yard, King’s Arms-yard,

Great Bell-alley, Packer’s-court,

White’s-alley, Great Swan-alley,

Crown-court, George-yard, Red Lion-court,

Cateaton-street, Gresham-street,

Milk-street, Wood-street, King-street,

Basinghall-street, Houndsditch, Lad-lane,

Threadneedle-street, Aldgate

High-street, and Maiden-lane, all in

the City of London--(Corporation of

the City of London) 1,016,421 18 1

Widening and improving the entrance

into London near Temple-bar, improving

the Strand and Fleet-street,

and formation of Pickett-street, and

for making a new street from the

east end of Snow-hill to the bottom of

Holborn-hill, now called Skinner-street--(Corporation

of the City of London) 246,300 0 0

Widening and improving Dirty-lane and

part of Brick-lane, leading from Whitechapel

to Spitalfields, and for paving

Dirty-lane, Petticoat-lane, Wentworth-street,

Old Montague-street,

Chapel-street, Princes-row, &c., all in

the county of Middlesex--(Commissioners

appointed by the Act 18, Geo.

III., c. 80) 1,500 0 0

Widening the avenues from the Minories,

through Goodman’s-yard into

Prescott-street, and through Swan-street

and Swan-alley into Mansell-street,

and from Whitechapel through

Somerset-street into Great Mansell-street,

all in the county of Middlesex--(Commissioners

named in Act 18,

George III., c. 50) 1,500 0 0

-------------------

Total cost of improving the above-mentioned

thoroughfares 1,265,721 13 1

_Paving._

Paving the road from Aldersgate Bars to

turnpike in Goswell-street, in the

county of Middlesex--(Commissioners

Sewers, &c., of the City of London) 5,500 0 0

Completing the paving of the town

borough of Southwark and certain

parts adjacent--(Commissioners for

executing Act 6, George III., for paving

town and borough of Southwark) 4,000 0 0

---------------

Total cost of paving the above-mentioned

thoroughfares 9,500 0 0

Hence the aggregate expense of the preceding improvements has been

upwards of 3,000,000_l._ sterling.

I have now, in order to complete this account of the cost of paving

and cleansing the thoroughfares of the metropolis, only to add the

following statement as to the traffic of the principal thoroughfares in

the city of London, for which I am indebted to Mr. Haywood, the City

Surveyor.

By the subjoined Return it will be seen that there are two tides as

it were in the daily current of locomotion in the City--the one being

at its flood at 11 o’clock A.M., after which it falls gradually till

2 o’clock, when it is at its lowest ebb, and then begins to rise,

gradually till 5 o’clock, when it reaches its second flood, and then

begins to decline once more. The point of greatest traffic in the

City is London-bridge, where the conveyances passing and repassing

amount to 13,099 in the course of twelve hours[31]. Of these it would

appear, that 9351 consist of one-horse vehicles and equestrians, 3389

of two-horse conveyances, and only 359 of vehicles drawn by more than

two horses. The one-horse vehicles would seem to be between two and

three times as many as the two-horse, which form about one-fourth of

the whole, while those drawn by more than two horses constitute about

one-sixtieth of the entire number.

The Return does not mention the state of the weather on the several

days and hours at which the observations were made, nor does it

tell us whether there was any public event occurring on those days

which was likely to swell or diminish the traffic beyond its usual

proportions. The table, moreover, it should be remembered, is confined

to the observations of only one day in each locality, so that we must

be guarded in receiving that which records a mere accidental set of

circumstances as an example of the general course of events. It would

have been curious to have extended the observations throughout the

night, and so have ascertained the difference in the traffic; and also

to have noted the decrease in the number of vehicles passing during a

continuously wet as well as a showery day. The observations should be

further carried out to different seasons, in order to be rendered of

the highest value. Mr. Haywood and the City authorities would really be

conferring a great boon on the public by so doing.