WM. R. WEBSTER.

"SPECIFICATIONS FOR STEEL RAILS.[E]

[Sidenote: Process of manufacture.]

"1. The entire process of manufacture shall be in accordance with

the best current state of the art.

"(_a_) Ingots shall be kept in a vertical position until ready to be

rolled, or until the metal in the interior has had time to solidify.

"(_b_) Bled ingots shall not be used.

[Sidenote: Chemical composition.]

"2. The chemical composition of the steel from which the rails are

rolled shall be within the following limits:

=================+============================+============================

| BESSEMER. | OPEN-HEARTH.

+-------------+--------------+-------------+--------------

|70 lbs. and | |70 lbs. and |

| over, but |85 to 100 lbs.| over, but |85 to 100 lbs.

|under 85 lbs.| inclusive. |under 85 lbs.| inclusive.

-----------------+-------------+--------------+-------------+--------------

Carbon |0.40 to 0.50 |0.45 to 0.55 |0.53 to 0.66 |0.63 to 0.76

Manganese |0.80 to 1.10 |0.80 to 1.10 |0.70 to 1.00 |0.70 to 1.00

Silicon |0.07 to 0.20 |0.07 to 0.20 |0.07 to 0.20 |0.07 to 0.20

Phosphorus, | | | |

not to exceed | 0.10 | 0.10 | 0.04 | 0.04

Sulphur, | | | |

not to exceed | 0.075| 0.075 | 0.06 | 0.06

=================+=============+==============+=============+==============

"3. When the average phosphorus content of the ingot metal used in

the Bessemer Process at any mill is below 0.08 and in the

Open-Hearth Process is below 0.03, the carbon shall be increased at

the rate of 0.035 for each 0.01 that the phosphorus content of the

ingot metal used averages below 0.08 for Bessemer steel, or 0.03 for

Open-Hearth steel.

"The percentage of carbon in an entire order of rails shall average

as high as the mean percentage between the upper and lower limits.

[Sidenote: Shearing.]

"4. The end of the bloom formed from the top of the ingot shall be

sheared until the entire face shows sound metal.

"All metal from the top of the ingot, whether made from the bloom or

the rail, is the top discard.

[Sidenote: Shrink]

"5. The number of passes and speed of train shall be so regulated

that, on leaving the rolls at the final pass, the temperature of the

rails will not exceed that which requires a shrinkage allowance at

the hot saws, for a 33-ft. rail of 100 lb. section, of 6-1/2 in. for

thick base sections and 6-3/4 in. for A. S. CC. E. sections, and 1/8

in. less for each ten pounds decrease of section, these allowances

to be decreased at the rate of 1-100 in. for each second of time

elapsed between the rail leaving the finishing rolls and being

sawed.

"The bars shall not be held for the purpose of reducing their

temperature, nor shall any artificial means of cooling them be used

between the leading and finishing passes, nor after they leave the

finishing pass.

[Sidenote: Section]

"6. The section of rail shall conform as accurately as possible to

the templet furnished by the Railroad Company. A variation in height

of 1-64 in. less or 1-32 in. greater than the specified height, and

1-16 in. in width of flange, will be permitted; but no variations

shall be allowed in the dimensions affecting the fit of splice bars.

[Sidenote: Weight]

"7. The weight of the rail shall be maintained as nearly as

possible, after complying with the preceding paragraph, to that

specified in the contract.

"A variation of one-half of one per cent. from the calculated weight

of section, as applied to an entire order, will be allowed.

"Rails will be accepted and paid for according to actual weight.

[Sidenote: Length]

"8. The standard length of rail shall be 33 ft.

"Ten per cent. of the entire order will be accepted in shorter

lengths varying by 1 ft. from 32 ft. to 25 ft.

"A variation of 1/4 in. from the specified lengths will be allowed.

"All No. 1 rails less than 33 ft. shall be painted green on both

ends.

[Sidenote: Finishing]

"9. Care shall be taken in hot-straightening rails, and it shall

result in their being left in such condition that they will not vary

throughout their entire length more than four (4) in. from a

straight line in any direction for thick base sections, and 5 in.

for A. S. C. E. sections when delivered to the cold-straightening

presses. Those which vary beyond that amount, or have short kinks,

shall be classed as second quality rails and be so marked.

"The distance between supports of rails in the straightening press

shall not be less than forty-two (42) in.; supports to have flat

surfaces and out of wind. Rails shall be straight in line and

surface and smooth on head when finished, final straightening being

done while cold.

"They shall be sawed square at ends, variations to be not more than

1-32 in., and prior to shipment shall have the burr caused by the

saw cutting removed and the ends made clean.

[Sidenote: Drilling]

"10. Circular holes for joint bolts shall be drilled in accordance

with specifications of the purchaser. They shall in every respect

conform accurately to drawing and dimensions furnished and shall be

free from burrs.

[Sidenote: Branding]

"11. The name of the manufacturer, the weight of the rail, and the

month and year of manufacture shall be rolled in raised letters and

figures on the side of the web. The number of the heat and a letter

indicating the portion of the ingot from which the rail was made

shall be plainly stamped on the web of each rail, where it will not

be covered by the splice bars. Rails to be lettered consecutively A,

B, C, etc., the rail from the top of the ingot being A. In case of a

top discard of twenty or more per cent. the letter A will be

omitted. Open-Hearth rails to be branded or stamped O. H. All

marking of rails shall be done so effectively that the marks may be

read as long as the rails are in service.

[Sidenote: Drop testing.]

"12. (_a_) Drop tests shall be made on pieces of rail rolled from

the top of the ingot, not less than four (4) ft. and not more than

six (6) ft. long, from each heat of steel. These test pieces shall

be cut from the rail bar next to either end of the top rail, as

selected by the Inspector.

"The temperature of the test pieces shall be between forty (40) and

one hundred (100) degrees Fahrenheit.

"The test pieces shall be placed head upward on solid supports, five

(5) in. top radius, three (3) ft. between centers, and subjected to

impact tests, the tup falling free from the following heights:

70 lb. rail 16 ft.

80, 85 and 90 lb. rail 18 ft.

100 lb. rail 20 ft.

"The test pieces which do not break under the first drop shall be

nicked and tested to destruction.

"(_b_) (It is proposed to prescribe, under this paragraph, the

requirements in regard to deflection, fixing maximum and minimum

limits, as soon as proper deflection limits have been decided upon.)

[Sidenote: Tests.]

"13. (A) Two pieces shall be tested from each heat of steel. If

either of these test pieces breaks, a third piece shall be tested.

If two of the test pieces break without showing physical defect, all

rails of the heat will be rejected absolutely. If two of the test

pieces do not break, all rails of the heat will be accepted as No. 1

or No. 2 classification (according as the deflection is less or

more, respectively, than the prescribed limit[A]).

"(B) If, however, any test piece broken under test A shows physical

defect, the top rail from each ingot of that heat shall be rejected.

"(C) Additional tests shall then be made of test pieces selected by

the Inspector from the top end of any second rails of the same heat.

If two out of three of these second test pieces break, the remainder

of the rails of the heat will also be rejected. If two out of three

of these second test pieces do not break, the remainder of the rails

of the heat will be accepted, provided they conform to the other

requirements of these specifications, as No. 1 or No. 2

classification (according as the deflection is less or more,

respectively, than the prescribed limit[F]).

"(D) If any test piece, test A, does not break, but when nicked and

tested to destruction shows interior defect, the top rails from each

ingot of that heat shall be rejected.

[Sidenote: Drop testing machine.]

"14. The drop-testing machine shall be the standard of the American

Railway Engineering and Maintenance of Way Association, and have a

tup of 2,000 lbs. weight, the striking face of which shall have a

radius of five (5) in.

"The anvil block shall be adequately supported and shall weigh

20,000 lbs.

"The supports shall be a part of or firmly secured to the anvil.

[Sidenote: No. 1 Rails.]

"15. No. 1 rails shall be free from injurious defects and flaws of

all kinds.

[Sidenote: No. 2 Rails.]

"16. Rails which, by reason of surface imperfections, are not

accepted as No. 1 rails, will be classed as No. 2 rails, but rails

containing physical defects which impair their strength, shall be

rejected.

"No. 2 rails to the extent of five (5) per cent. of the whole order

will be received. All rails accepted as No. 2 rails shall have the

ends painted white, and shall have two prick punch marks on the side

of the web near the heat number near the end of the rail, so placed

as not to be covered by the splice bars.

"Rails improperly drilled, straightened, or from which the burrs

have not been properly removed, shall be rejected, but may be

accepted after being properly finished.

"Different classes of rails shall be kept separate in shipment.

"All rails shall be loaded in the presence of the inspector.

[Sidenote: Inspection.]

"17. (_a_) Inspectors representing the purchaser shall have free

entry to the works of the Manufacturer at all times while the

contract is being executed, and shall have all reasonable facilities

afforded them by the Manufacturer to satisfy them that the rails

have been made in accordance with the terms of the specifications.

"(_b_) For Bessemer Steel the Manufacturer shall, before the rails

are shipped, furnish the Inspector daily with carbon determinations

for each heat, and two complete chemical analyses every twenty-four

hours representing the average of the other elements specified in

section 2 hereof contained in the steel, for each day and night turn

respectively. These analyses shall be made on drillings taken from

the ladle test ingot not less than 1/4 in. beneath the surface.

"For Open-Hearth Steel, the makers shall furnish the Inspectors with

a complete chemical analysis of the elements specified in section 2

hereof for each melt.

"(_c_) On request of the Inspector, the Manufacturer shall furnish

drillings from the test ingot for check analysis.

"(_d_) All tests and inspections shall be made at the place of

manufacture, prior to shipment, and shall be so conducted as not to

unnecessarily interfere with the operation of the mill."

Transactions of the American Society of Civil Engineers, Vol. LXX, Dec. 1910 Final Report of Special Committee on Rail Sections, Paper No. 1177 · 第 7 / 8 题