2. Plane off the groove edge of one piece of ceiling and nail it on the
back of the frame even with the end. 3. Nail the rest of the ceiling on
the back. Be sure that each joint matches tightly.
[Illustration: _Fig._ 35.--Frame of cabinet nailed together]
Shelves:
1. Make four strips (3/4" × 3/4" × 16-1/2") and nail two of them inside,
across each end, 15" and 24" from the bottom. These strips hold the
shelves.
2. From a 1" × 12" piece cut two pieces 32-1/2" long; fit and
nail them in for the upper shelf.
3. Make the bottom shelf of two pieces, one 10-1/4" wide and the other
8" wide. When these boards are nailed in place, the shelf is narrow
enough to allow the doors, with pockets on, to close.
4. Make two strips; one 13-16" × 1" × 16-1/2" and the other 13-16" ×
1-3/4" × 20-1/2", and nail them to the top shelf for drawer guides.
Top: