GAS-FITTING

=12.= Following is given the cost of buying and installing the

various gas fixtures and pipes that are used in the building under

consideration:

FIXTURES

_Quantities and Cost_

Cellar:

2 brackets, 1 burner, each at 50 cents $ 1.00

First floor:

Parlor, 1 chandelier, 4 burners 50.00

2 brackets, stiff, 2 burners, each at $10 20.00

Dining room, 1 chandelier, 5 burners 45.00

2 brackets, stiff, 1 burner, each at $5 10.00

Hall, 1 chandelier, 4 burners 30.00

Library, 1 chandelier, 6 burners 50.00

2 brackets, stiff, 2 burners, each at $10 20.00

Lavatory, 1 bracket, 1 burner, stiff 2.50

Kitchen, 1 center fixture, 2 burners 4.00

1 side light, stiff, 1 burner 1.00

Butler’s pantry, 1 drop light, 2 burners 4.00

Pantry, 1 side light, stiff, 1 burner 1.00

Cellar stairs, 1-bracket light, 1 burner .50

Second floor:

Bedrooms, 11 double-swing brackets, 1 burner, at $5 55.00

Dressing room, 1 double-swing, plain, 1 burner 2.00

Hall, 1 stiff bracket, 2 burners 6.00

Stair landing, 2 stiff brackets, 1 burner, each at $4 8.00

Bathroom, 1 bracket, double swing, plain, 1 burner 3.00

Attic rooms, 5 stiff brackets, 1 burner, each at $.75 3.75

-------

Total $316.75

PIPE AND FITTINGS

_Quantities and Cost_

54 ft. 1½-inch pipe, at 10 cents $ 5.40

30 ft. ¾-inch pipe, at 6 cents 1.80

30 ft. ½-inch pipe, at 4 cents 1.20

205 ft. ⅜-inch pipe, at 3 cents 6.15

Fittings 4.00

-------

Total $ 18.55

LABOR

Labor, assumed to be one-seventh the cost of materials

(fixtures, pipes, etc.) = $335.30 ÷ 7 = $ 47.90

_Summary_

Fixtures $316.75

Pipe and fittings 18.55

Labor 47.90

-------

Total cost of gas-fitting $383.20