BRICKWORK

=4.= In estimating the brickwork, openings have been deducted, thus

practically giving “kiln count,” so that the analyses of prices given

heretofore will apply. If openings had not been deducted, the prices

would be 15 per cent. lower.

PRESSED BRICK

_Quantities_ NO.

BRICK

Facing exterior walls, same length as stone

lintel course, 125' × 8' = 1,000 sq. ft. at

7½ bricks per square foot 7,500

SQUARE

Deduct for Openings: FEET

Nine windows, total width 32' X 6' 6" high 208.0

Two casement windows, total width

7' 4" × 8' high 58.7

One lavatory window, total width 2' X 6"

× 5' 6" 13.8

Main door, 5' 5" × 8' 9" 47.4

-----

Total deductions 327.9

327.9 × 7½ = 2,459

-----

Number of brick 5,041

Add 5 per cent. for waste 252

-----

Total pressed brick 5,293

_Cost_

The cost of pressed brickwork is based on the analysis given in

Estimating and Calculating Quantities, Part 1, and is $53.71 per

thousand.

_Summary_

From the preceding estimate of quantities, the

number of pressed brick laid is 5,041, which,

at $53.71 per M, will cost $270.75

Pressed brick, not laid, 252, at $30 per M 7.56

-------

Total cost of pressed brickwork $278.31

COMMON BRICK

_Quantities_ NO.

BRICK

Backing exterior pressed-brick walls, 8½ in. thick,

5,041 × 2 = 10,082

Backing behind lintel course,

9" X 125' × 8" at 15 brick per sq. ft. 1,406

Interior cellar walls, 28' 4" × 8' = 226.7 sq. ft.

(17-inch wall) at 30 brick per square foot 6,801

Deduct for three openings, 12' 3" total width

× 6' 6" height = 79.6 sq. ft. at 30 brick

per square foot 2,388

----- 4,413

Interior wall, 8½" thick, 43' 9" × 8', 350 sq. ft.

at 15 brick per square foot 5,250

Chimney, principal (flues figured solid), approximately

920 cu. ft., at 22½ brick per cubic foot 20,700

Chimney, rear, approximately 245 cu. ft., at 22½ brick

per cubic foot 5,513

Trap pits, 46 sq. ft., at 7½ brick per square foot 345

------

46,303

Add 5 per cent. for waste 2,315

------

Total common brick 48,618

_Cost_

The cost of the common brickwork is based on the analysis given in

_Estimating and Calculating Quantities_, Part 1, and is $16.68 per

thousand for lime-cement mortar.

_Summary_

According to the estimate of quantities, the

number of common brick laid is 46,303, which,

at $16.68, will cost $ 772.33

Common bricks, not laid, 2,315, at $8 18.52

Molded brick and terra-cotta cap for rear chimney 10.00

--------

Total cost of common brickwork $ 800.85

_Recapitulation of Cost of Brickwork_

Pressed brickwork $ 278.31

Common brickwork 800.85

---------

Total cost of brickwork $1,079.16