CONSTRUCTION.

Ground was broken for work under the principal contract on July 9th,

1904, on which date the contractor began cutting asphalt for Trench No.

1 in 31st Street, and also began making a roadway from Ninth Avenue into

the pit just south of 32d Street.

_Excavation for Retaining Walls._--Two essentially different methods

were used in excavating for and building the retaining walls; one,

construction in trench, the other, construction on bench. In general,

the trench method was used wherever the rock on which the wall was to be

founded was 12 ft. or more below the surface of the street; or, what is

perhaps a more exact statement, as it includes the determining factor,

where the buildings adjoining the wall location were not founded on

rock.

In the trench method the base of the wall was staked out on the surface

of the ground, the required width being determined by the elevation of

the rock, as shown by the borings. The contractor then added as much

width as he desired for sheeting and working space, and excavated to a

depth of about 5 ft. before setting any timber. In some cases the depth

of 5 ft. was excavated before the cableway or derrick for the excavation

was erected, the wagons being driven directly into the excavation and

loaded by hand, but, usually, the cableway was first erected, and

buckets were used from the start. After the first 5 ft. had been

excavated, two sets of rangers and struts were set, the first in the

bottom of the excavation and the second at the level of the street

surface, supported by posts resting on the bottom rangers. The sheeting

was then set, and all voids back of it were filled with clean earth and

well tamped. The toe of the sheeting was kept level with the bottom of

the excavation until the ground-water was reached, after which it was

kept from 3 to 5 ft. ahead of the digging.

The sheeting used was 3-in., in variable widths; it was always tongued

and grooved on the side of the trench next to the buildings and in the

deeper excavations on both sides of the trench, and was driven by wooden

mauls above the ground-water level, but steam sheeting-drivers were used

below that elevation. Struts, rangers, and posts were generally 12 by

12-in.

Some exceedingly bad material was encountered in the deeper excavations,

beds of quicksand being passed through, varying in thickness from 1 to

18 ft., the latter, in 31st Street between Seventh and Eighth Avenues,

in the deepest excavation made. After encountering the fine sand in that

trench, no headway was made until a tight wooden cylinder was sunk

through the sand by excavating the material inside of it and heavily

weighting the shell with pig iron. When this cylinder had reached the

gravel, which lay below the sand, it was used as a sump, and the water

level was kept below the bottom of the excavation, which permitted good

progress. Sand continued to flow under the sheeting to such an extent,

however, that the front walls of four adjoining buildings were badly

cracked and had to be taken down and rebuilt. All the stoops along this

trench settled, and had to be repaired.

The bench method of excavating for the retaining wall was very simple,

and was used only where the rock lay near the surface and the adjoining

buildings were founded on it, the overlying material being in such case

dry, and consequently firm, little or no shoring was required. The

method was to extend the pit excavation to a width of 2 or 3 ft. beyond

the proposed back of the retaining wall, and to carry that width down to

the depth required for its base, below which the excavation was narrowed

to 1 ft. inside of the face of the wall and continued either before it

was built or subsequently.

_Retaining-Wall Construction._--The concrete walls were built in

sections 50 ft. in length, except where that spacing would bring an

expansion joint under a girder pocket or just on line with a tier of

struts, in which cases the section was shortened as required. Trenches

were never allowed to remain open at the full depth, the concreting

being started as soon after the necessary length of rock had been

uncovered as the forms and preliminary work for a section could be

prepared. Each section was a monolith, except in a few cases where

very heavy rains made it impossible to hold the laborers.

The various operations in building the concrete wall are shown on

Fig. 7. Guide-planks, "_a a_," Section "_A-A_," were securely spiked

to alternate tiers of struts for the length of the section, the face

of each guide-plank being set on line with the intended face of the

concrete wall, and 2-in. tongued-and-grooved spruce plank were laid

along the guide-plank to the height of the bottom strut and securely

braced from the front sheeting. A 4-in. brick wall was built

simultaneously on line with the back of the wall to the height of

the first step. Where the bottom strut was below that elevation, the

brickwork was left low at that immediate point and built up when the

strut was removed. The brick wall was then water-proofed on the side

toward the concrete, and loose laps of the water-proofing were allowed

to hang over the brickwork and at least 8 in. down the back. A 6-in.

vitrified pipe drain was then laid along the surface of the rock just

outside of the brick wall, the joints in the pipe being caulked with

oakum saturated in cement, and pointed with cement mortar above a line

1 in. below the horizontal diameter, the remainder of each joint being

left open. Cross-drains were laid from tees in the back drain to the

face of the wall at all low points in the rock and at least for every

25 ft. of wall length, the joints of these discharge pipes being caulked

and cemented throughout. The surface of the rock was then washed and

scraped clean, and was covered with about 1 in. of mortar, after which

the section was ready for concrete.

The building of monolithic sections in trenches required that the thrust

from one set of struts be taken by the concrete before the set above

could be removed, and necessarily caused slow progress, the rate at

which concrete was deposited being just sufficient to prevent one layer

from setting before the next layer above could be placed.

The concrete used was mixed in the proportions of 1 part of cement to

3 parts of sand and 6 parts of stone, in 2-bag batches, in ¾-yd. and

1-yd. Ransome portable mixers mounted with air-driven engines on the same

frame. These mixers were placed at the surface, and were charged with

barrows, the correct quantities of sand and stone for each batch being

measured in rectangular boxes previous to loading the barrows. The

concrete was discharged from the mixer into a hopper which divided into

two chutes, only one of which was used at a time, the concrete being

shoveled from the bottom of the chutes to its final position. Facing

mortar, 2 in. thick, was deposited simultaneously with the concrete, and

was kept separate from it by a steel diaphragm until both were in place,

when the diaphragm was removed and the two were spaded together. The

bottoms of the guide-planks were cut off just above the concrete as it

progressed, and, as soon as the wall had reached a strut at one end of

the section, that strut was removed, the form was built up to the next

strut, at front and back, and braced to the sheeting, so that, by the

time the entire length of the section had been carried up to the level

of the first line of struts, forms were ready at one end for the

succeeding layers. The layers of concrete never exceeded 8 in. in

height, and at times there were slight delays in the concreting while

the carpenters made ready the next lift of forms, but such delays were

rarely long enough to permit the concrete to take its initial set.

[Illustration:

Fig. 7.

SKETCH SHOWING FORMS FOR, AND METHOD OF, CONCRETING RETAINING WALLS

IN TRENCH.]

After a section of concrete had firmly set, both back and front forms

were removed, and the thrust from the sides of the trench was

transferred directly to the finished wall. The face of the wall was

rubbed with a cement brick to remove the marks of the plank, and was

then coated with a wash of thin cement grout. The water-proofing and

brick armor were then continued up the back of the wall, the spaces

between the lines of braces being first water-proofed and bricked, and

the braces transferred to the finished surface, after which the omitted

panels were completed. The water-proofing consisted of three layers of

Hydrex felt, of a brand known as Pennsylvania Special, and four layers

of coal-tar pitch. The pitch contained not less than 25% of carbon,

softened at 60° Fahr., and melted at a point between 96° and 106° Fahr.

The melting point was determined by placing 1 gramme of pitch on a lead

disk over a hole, 5/16-in. in diameter, and immersed in water which was

heated at the rate of 1° per min.; the temperature of the water at the

time the pitch ran through the hole was considered as the melting point.

In order to prevent the water-proofing from being torn at the joint

between sections when they contract from changes in temperature, a

vertical strip of felt, 6 in. wide, was pitched over each joint, lapping

3 in. on each concrete section. The back of this strip was not pitched,

but was covered with pulverized soapstone, so that the water-proofing

sheet was free from the wall for a distance of 3 in. on either side of

each joint.

Concreting was continued during the severest weather, one section being

placed when the thermometer was 5° above zero. When the thermometer was

below the freezing point both sand and stone were heated by wood fires

in large pipes under the supply piles; the temperature of the mix was

taken frequently, and was kept above 40 degrees. Numerous tests made

while the work was in progress showed that, while the temperature fell

slightly soon after the concrete was deposited, it was always from 2° to

5° higher at the end of 2 hours. The face and back of the concrete were

prevented from freezing by a liberal packing of salt hay just outside

the forms.

A vertical hog trough, 24 in. wide and 9 in. deep, was placed in one

end of each section, for its full height below the bridge seat, into

which the next section keyed, and, when the temperature at the time

of concreting was below 50° Fahr., a compression joint was formed by

placing a strip of heavy deadening felt, 2 ft. wide, on the end of the

completed section next to the face and covering the remainder of the

end with two ply of the felt and pitch water-proofing; the one ply of

deadening felt near the face was about the same thickness as the two ply

of water-proofing, and was used to prevent the pitch from being squeezed

out of the joint to the face of the wall.

The excavation for the retaining walls in 31st and 33d Streets were in

all cases made of sufficient width to receive the sewers, which were

laid as soon as the back-fill, carefully rammed and puddled, had reached

the proper elevations; the back-filling was then completed, and the gas

and water mains were afterward laid in separate trenches.

[Illustration:

Fig. 8.

SKETCH SHOWING FORMS AND BRACING FOR NINTH AVENUE WALL]

The sections of concrete built in trench varied in height from 13 to

59 ft. from the base to the top of the back wall. With the exception of

the Seventh Avenue wall, 50 ft. in height, and the Ninth Avenue wall,

62 ft. in height, none of those sections constructed by the bench

method was more than 14 ft. The forms and bracing for these walls were

substantially the same, except that the low walls were built in lengths

of approximately 50 ft., while the forms for the Seventh and Ninth

Avenue walls were only 20 ft. long.

The forms and bracing for the Ninth Avenue walls are shown on Fig. 8.

These forms were built in one piece and moved ahead from section to

section, and they were firmly braced from the bottom with raker braces

to a point 36 ft. above the base, the upper part being held in place by

¾-in. bolts passed through the forms and anchored by cables to bolts

grouted into the rock behind.

After the forms had been set and braced, an 8-in. brick wall was laid

up the face of the rock, containing a vertical line of three-cell hollow

tile block every 5 ft. of length, and laid to conform as nearly as

possible to the face of the rock, all voids being filled with broken

stone. Water-proofing, similar to that described for the walls in the

trench, was then applied to the brick and tile wall for the full height,

and firmly braced to the front forms, the braces being removed as the

concrete reached them. The concrete was mixed at the street level and

deposited through chutes, as described previously.

Tables 1, 2, and 3 show the quantity of cement used in each section of

retaining wall, and give figures by which the quantities of other

materials may be determined.

_Pit Excavation._--The pit excavation during the horse-and-truck period

was largely preparatory work done to get the excavation in good shape

for handling spoil trains after Pier No. 72 and the trestle approach

were finished. This required an open cut from Ninth to Seventh Avenues

at a sufficient depth below the sewers and other substructures in the

avenues to clear a locomotive, and wide enough for both running and

loading tracks, also the building of the cast-iron sewer in Eighth

Avenue across the entire excavation, with enough of the temporary

bridging to support it. The building of the trestle in Eighth Avenue

was essentially a part of the pit excavation, as the progress of one

depended greatly on that of the other.

Excavation was commenced on July 12th, 1904, for the crossing under

Ninth Avenue, and in the pit east of Ninth Avenue along 32d Street. The

line chosen for the opening cut was down the center of the pit, as it

was not safe to excavate near the bounding streets until after the

completion of the enclosing retaining wall. The excavation was started

by hand, but three 70-ton Bucyrus steam shovels were put to work as soon

as they could be delivered, the first on July 25th and the third on

September 12th. The excavated material was loaded by the shovels on

end-dump wagons, each having a capacity of 2 cu. yd., and was conveyed

in them to the dumping board at 35th Street. The average number of teams

was 135, 10% being snatch teams to pull the wagons out of the pit and to

assist them up the runway at the dumping board. The teams averaged only

seven trips per day of 10 hours, considerable delay being caused by the

trains of the New York Central Railroad at Eleventh Avenue. The number

of teams was not sufficient, therefore, to keep the three shovels busy

when they were all in good digging, but the dumping board was taxed to

accommodate that number, and little would have been gained by increasing

it. The digging was very good during this period, practically no rock

being encountered, and the building foundations were too light to

present any obstacle to such powerful shovels. The capacity of their

dippers was 3½ cu. yd., so that one dipperful meant one truck loaded and

running over. The output from August to November, inclusive, averaged

40,000 cu. yd. per month; one shift only was worked per day, and

although the quantity was not large for three such powerful shovels, it

was large to truck through the streets, and required that one team pass

a given point every 18 sec. At the end of November the opening up of

the pit had been accomplished, considerable rock had been stripped

near Ninth Avenue, and the streets had become so icy that the cost of

transportation was practically doubled; work in the pit, therefore, was

much curtailed, and amounted to continuous work for one shovel from that

time until the end of the period, May 22d, 1905, when Pier No. 72 was

put in service and transportation by train began. Figs. 2 and 3, Plate

LVI, show the condition of the pit east and west of Eighth Avenue,

respectively, on that date.

[Illustration:

Fig. 9.

SKETCH SHOWING TYPICAL BENT OF TRESTLE SUPPORTING EIGHTH AVENUE]

The work of excavating for and building the temporary street bridge,

a typical bent and bracing for which are shown on Fig. 9, and the

cast-iron sewer and water mains in Eighth Avenue, was commenced on

September 3d, 1904. The trestle was a double-decked structure of yellow

pine, with 10 by 10-in. posts and sills, 10 by 14-in. intermediate and

top caps, and 2 by 10-in. longitudinal and cross-braces. The trestle was

further stiffened longitudinally by four lines of 8 by 10-in. struts,

butted between the intermediate caps, and held in position by 2 by 8-in.

splice-plates resting on top of them. The intermediate caps were at an

elevation of 15 ft. below the surface of the street, and above that line

the longitudinal bracing was continuous, while below it the bents were

braced in pairs, the bracing being omitted from every second bay. Below

the intermediate cap the bents were uniform for the entire width of the

trestle, but the top cap was not continuous, being 5 ft. below the

surface under the trolley tracks, and only 18 in., the depth of

stringers and planking, beyond. The stringers under the trolley tracks

were 8 by 16-in. yellow pine, spaced three to a track, and those for the

driveway were 6 by 14-in., spaced 1 ft. 6 in. on centers, the planking

being 4-in. yellow pine.

The first step in the construction was to excavate a trench 15 ft. wide

on the west side of the street, the east side of the trench being 4 ft.

west of the westernmost trolley rail. While this work was in progress,

all vehicular traffic was turned to that part of the avenue east of the

westerly trolley rail. The trench was sheeted and timbered, and carried

to a depth sufficient to receive the intermediate cap. That portion of

the bent from the bottom of the intermediate cap to the bottom of the

top cap was then erected for the width of the trench, after which the

60-in. cast-iron sewer and the 48-in. water main were laid in position

and caulked. The top cap, stringers, and planking were then laid, for

the full width of the trestle west of the trolley tracks. This work was

finished and the sewage turned into the new sewer in April, 1905.

As the planking was laid west of the trolley tracks, traffic was turned

to that side of the street, and the material east of the tracks was

excavated to its natural slope. Trenches were then dug under the tracks

on the line of the bents, and the caps were set in position on blocking.

The material between these trenches was then removed, the tracks being

supported meanwhile by blocking at least every 6 ft., and the stringers

and planking were shoved into place. Excavation was next made between

the caps to a depth of about 5 ft. below them, needle-beams being placed

under the caps, one or two at a time, and supported on posts erected in

these excavations; the material on line of the bents was excavated to

the depth of the intermediate caps, which were then set, together

with the posts and bracing for the upper deck of the structure. This

operation was repeated for the lower deck, about 10 ft. being gained for

each change of posts, and three shifts, therefore, were required.

At the beginning of the train-transportation period, May 22d, 1905, two

shifts of 10 hours each were inaugurated, and the earth was handled at

the rate of from 85,000 to 90,000 cu. yd. per month; but, by the end of

August, when a little more than 60% of the total earth had been disposed

of, the rock began to interfere very greatly with the progress. The

strike of the rock was almost directly north and south, and its surface

formed broken ridges running in that direction, with deep valleys

between. The dip was almost vertical near Ninth Avenue, and about 70°

toward the west near Seventh Avenue. This condition made it necessary to

turn the shovels parallel to the ridges in order to strip the rock for

drilling; and, as the ridges were very broken, the shovels continued to

bump into them on all occasions, making it necessary to move back and

start other cuts or stand and wait for the rock to be drilled and

blasted. One small Vulcan steam shovel, with vertical boiler and ¾-cu.

yd. dipper, had been brought on the work to be used in stripping rock,

and was moved from place to place so much more easily than the large

ones that an Ohio shovel of the same general type was purchased in

October, and thereafter the stripping was done largely by the two small

shovels and by hand, the large shovels being used almost exclusively in

handling rock.

The drilling necessary to remove the rock was very large in amount and

also per yard excavated. In order not to damage the retaining walls and

the rock underlying them, holes spaced at 5-in. centers were drilled

1 ft. away from the face of the walls and on the same batter. These

breaking holes alone amounted to a total of 210,000 lin. ft., or 1 ft.

of hole for each 3½ cu. yd. of rock excavated; and the regulations of

the Bureau of Combustibles, which prevented springing, caused the

blasting holes to be placed very close together and required a total of

about 420,000 lin. ft., making 630,000 ft. If to this is added the block

holes, for some of the rock broke very large, it will show at least

1 ft. of drill hole for each cubic yard of rock excavated, about ten

times the average on general railroad work.

[Transcriber's Note:

The three numbered Tables were originally printed at full width, with

columns (1)-(13) displayed in a single row.]

TABLE 1a.--Record of Retaining-Wall Sections, Terminal Station.

West Thirty-first Street from Seventh Avenue to Ninth Avenue.

(1) Section No.

(2) Stations.

(3) Contents of section, in cubic yards.

(4) Barrels of cement used for facing.

(5) Cubic yards of facing mortar equivalent.

(6) Barrels of cement used for bed mortar.

(7) Cubic yards of bed mortar equivalent.

(8) Cubic yards of embedded stone.

(1) (2) (3) (4) (5) (6) (7) (8)

_____________________________________________________________________

| 1 {165 + 05.8} | | | | | | |

| {165 + 66.0} | 617.48 | 17.50 | 5.95 | ... | ... | ... |

| 2 {165 + 66.0} | | | | | | |

| {165 + 95.4} | 233.96 | 10.25 | 3.49 | ... | ... | ... |

| 3 {165 + 95.4} | | | | | | |

| {166 + 41.2} | 355.20 | 24.50 | 8.34 | ... | ... | ... |

| 4 {171 + 03.4} | | | | | | |

| {171 + 53.4} | 309.29 | 67.50 | 23.00 | ... | ... | ... |

| 5 {177 + 44.0} | | | | | | |

| {177 + 94.0} | 109.62 | 30.25 | 10.30 | ... | ... | ... |

| 6 {171 + 53.4} | | | | | | |

| {171 + 83.0} | 246.35 | 27.75 | 9.44 | ... | ... | ... |

| 7 {166 + 41.2} | | | | | | |

| {166 + 79.0} | 644.12 | 77.50 | 26.37 | ... | ... | ... |

| 8 {171 + 83.0} | | | | | | |

| {172 + 12.0} | 394.43 | 63.75 | 21.69 | ... | ... | ... |

| 9 {166 + 79.0} | | | | | | |

| {167 + 20.5} | 974.58 |103.75 | 35.30 | 2.50 | 0.85 | 7.96 |

| 10 {170 + 16.6} | | | | | | |

| {170 + 58.6} | 767.34 | 92.50 | 31.48 | 2.75 | 0.94 | ... |

| 11 {170 + 58.6} | | | | | | |

| {171 + 03.4} | 599.17 | 77.00 | 26.20 | 10.25 | 3.49 | ... |

| 12 {167 + 20.5} | | | | | | |

| {167 + 43.9} | 535.28 | 50.50 | 17.18 | 2.00 | 0.68 | 4.00 |

| 13 {175 + 18.5} | | | | | | |

| {175 + 61.8} | 553.04 | 62.00 | 21.10 | 5.25 | 1.79 | ... |

| 14 {177 + 02.9} | | | | | | |

| {177 + 44.0} | 305.12 | 49.25 | 16.76 | 4.50 | 1.53 | ... |

| 15 {175 + 61.8} | | | | | | |

| {176 + 91.7} | 429.88 | 50.00 | 17.01 | 1.50 | 0.51 | ... |

| 16 {176 + 62.5} | | | | | | |

| {177 + 02.9} | 675.64 | 77.50 | 26.37 | 6.25 | 2.13 | ... |

| 17 {174 + 04.5} | | | | | | |

| {174 + 29.6} | 162.98 | 29.00 | 9.87 | 3.50 | 1.19 | ... |

| 18 {175 + 91.7} | | | | | | |

| {176 + 21.5} | 698.88 | 46.25 | 15.72 | 4.50 | 1.53 | 15.86 |

| 19 {176 + 21.5} | | | | | | |

| {176 + 62.5} | 1,166.79 | 81.50 | 27.73 | 4.00 | 1.36 | 34.96 |

| 20 {167 + 43.9} | | | | | | |

| {167 + 92.6} | 975.53 | 95.75 | 32.58 | 3.25 | 1.11 | 36.99 |

| 21 {172 + 12.0} | | | | | | |

| {172 + 45.2} | 271.48 | 31.75 | 10.80 | 2.50 | 0.85 | 8.65 |

| 22 {168 + 41.3} | | | | | | |

| {168 + 72.6} | 316.30 | 44.00 | 14.97 | 5.25 | 1.79 | 7.18 |

| 23 {173 + 63.6} | | | | | | |

| {174 + 04.5} | 529.33 | 54.75 | 18.63 | 4.75 | 1.62 | 1.25 |

| 24 {167 + 92.6} | | | | | | |

| {168 + 41.3} | 1,010.64 | 66.00 | 22.46 | 5.50 | 1.87 | 10.16 |

| 25 {173 + 21.2} | | | | | | |

| {173 + 63.6} | 675.21 | 77.75 | 26.46 | 2.50 | 0.85 | 12.00 |

| 26 {164 + 72.5} | | | | | | |

| {165 + 05.8} | 458.22 | 40.00 | 13.61 | 5.50 | 1.87 | 22.37 |

| 27 {172 + 81.9} | | | | | | |

| {173 + 21.2} | 409.43 | 35.00 | 11.91 | 9.75 | 3.31 | 4.64 |

| 28 {164 + 27.6} | | | | | | |

| {164 + 72.5} | 658.46 | 72.00 | 24.50 | 1.50 | 0.51 | 16.40 |

| 29 {172 + 45.2} | | | | | | |

| {172 + 81.9} | 345.89 | 30.25 | 10.29 | 5.00 | 1.70 | 1.62 |

| 31 {174 + 78.0} | | | | | | |

| {175 + 18.5} | 507.50 | 35.75 | 12.17 | 3.00 | 1.02 | 17.09 |

| 32 {174 + 29.6} | | | | | | |

| {174 + 78.0} | 396.99 | 43.75 | 14.89 | 1.75 | 0.60 | 6.50 |

| 43 {177 + 94.0} | | | | | | |

| {178 + 44.1} | 194.07 | 30.00 | 10.21 | 2.00 | 0.68 | 8.35 |

| Pier {168 + 72.6} | | | | | | |

| {168 + 81.1} | 106.52 | ... | ... | ... | ... | ... |

| 76 {178 + 44.1} | | | | | | |

| {178 + 94.1} | 136.32 | 12.75 | 4.34 | 4.75 | 1.62 | ... |

| 79 {178 + 94.1} | | | | | | |

| {179 + 44.1} | 118.07 | 9.00 | 3.06 | 8.50 | 1.19 | ... |

| 82 {179 + 44.1} | | | | | | |

| {179 + 93.7} | 126.12 | 6.50 | 2.21 | 2.50 | 0.85 | ... |

| 84 {179 + 93.7} | | | | | | |

| {180 + 44.2} | 126.77 | 6.75 | 2.30 | 2.25 | 0.77 | ... |

| 86 {180 + 44.2} | | | | | | |

| {180 + 93.6} | 162.48 | 8.00 | 2.72 | 2.75 | 0.94 | ... |

| 90 {180 + 93.6} | | | | | | |

| {181 + 17.9} | 92.52 | 4.00 | 1.36 | 1.00 | 0.34 | ... |

|___________________|__________|_______|_______|_______|______|_______|

TABLE 1b.--Record of Retaining-Wall Sections, Terminal Station.

West Thirty-first Street from Seventh Avenue to Ninth Avenue.

(1) Section No.

(2) Stations.

(9) Cubic yards of concrete in section (net).

(10) Barrels of cement used in concrete.

(11) Barrels of cement per cubic yard of concrete.

(12) Concrete started.

(13) Concrete finished.

(1) (2) (9) (10) (11) (12) (13)

______________________________________________________________________

| 1 {165 + 05.8} | | | | | |

| {165 + 66.0} | 611.53 | 731.50 | 1.20 | 11/4/04 | 11/20/04 |

| 2 {165 + 66.0} | | | | | |

| {165 + 95.4} | 230.47 | 277.25 | 1.20 | 11/21/04 | 11/27/04 |

| 3 {165 + 95.4} | | | | | |

| {166 + 41.2} | 346.86 | 398.25 | 1.15 | 11/26/04 | 12/3/04 |

| 4 {171 + 03.4} | | | | | |

| {171 + 53.4} | 286.29 | 360.50 | 1.26 | 12/2/04 | 12/10/04 |

| 5 {177 + 44.0} | | | | | |

| {177 + 94.0} | 99.32 | 120.75 | 1.22 | 12/28/04 | 12/30/04 |

| 6 {171 + 53.4} | | | | | |

| {171 + 83.0} | 236.91 | 292.50 | 1.23 | 1/2/05 | 1/11/05 |

| 7 {166 + 41.2} | | | | | |

| {166 + 79.0} | 617.75 | 737.00 | 1.19 | 1/13/05 | 2/4/05 |

| 8 {171 + 83.0} | | | | | |

| {172 + 12.0} | 372.74 | 420.75 | 1.13 | 1/14/05 | 1/28/05 |

| 9 {166 + 79.0} | | | | | |

| {167 + 20.5} | 930.47 | 1,066.25 | 1.14 | 2/18/05 | 3/13/05 |

| 10 {170 + 16.6} | | | | | |

| {170 + 58.6} | 734.92 | 852.50 | 1.16 | 1/31/05 | 2/25/05 |

| 11 {170 + 58.6} | | | | | |

| {171 + 03.4} | 569.48 | 689.75 | 1.21 | 3/11/05 | 3/23/05 |

| 12 {167 + 20.5} | | | | | |

| {167 + 43.9} | 513.42 | 611.75 | 1.19 | 3/9/05 | 3/26/05 |

| 13 {175 + 18.5} | | | | | |

| {175 + 61.8} | 530.15 | 630.50 | 1.19 | 3/15/05 | 3/29/05 |

| 14 {177 + 02.9} | | | | | |

| {177 + 44.0} | 286.83 | 340.25 | 1.19 | 3/26/05 | 3/31/05 |

| 15 {175 + 61.8} | | | | | |

| {176 + 91.7} | 412.36 | 472.50 | 1.15 | 3/28/05 | 4/14/05 |

| 16 {176 + 62.5} | | | | | |

| {177 + 02.9} | 647.14 | 788.00 | 1.22 | 4/1/05 | 4/17/05 |

| 17 {174 + 04.5} | | | | | |

| {174 + 29.6} | 151.92 | 182.50 | 1.20 | 5/3/05 | 5/6/05 |

| 18 {175 + 91.7} | | | | | |

| {176 + 21.5} | 665.77 | 801.00 | 1.20 | 5/9/05 | 5/19/05 |

| 19 {176 + 21.5} | | | | | |

| {176 + 62.5} | 1,102.74 | 1,354.50 | 1.23 | 5/15/05 | 5/28/05 |

| 20 {167 + 43.9} | | | | | |

| {167 + 92.6} | 904.85 | 1,012.75 | 1.12 | 5/25/05 | 6/3/05 |

| 21 {172 + 12.0} | | | | | |

| {172 + 45.2} | 251.18 | 311.50 | 1.24 | 5/29/05 | 6/3/05 |

| 22 {168 + 41.3} | | | | | |

| {168 + 72.6} | 292.36 | 338.75 | 1.16 | 6/5/05 | 6/10/05 |

| 23 {173 + 63.6} | | | | | |

| {174 + 04.5} | 507.83 | 587.25 | 1.16 | 6/5/05 | 6/13/05 |

| 24 {167 + 92.6} | | | | | |

| {168 + 41.3} | 976.15 | 1,038.75 | 1.07 | 6/8/05 | 6/21/05 |

| 25 {173 + 21.2} | | | | | |

| {173 + 63.6} | 635.90 | 776.25 | 1.22 | 6/16/05 | 6/24/05 |

| 26 {164 + 72.5} | | | | | |

| {165 + 05.8} | 420.37 | 532.00 | 1.26 | 6/23/05 | 6/28/05 |

| 27 {172 + 81.9} | | | | | |

| {173 + 21.2} | 389.57 | 450.00 | 1.16 | 6/27/05 | 7/7/05 |

| 28 {164 + 27.6} | | | | | |

| {164 + 72.5} | 617.05 | 726.25 | 1.18 | 6/29/05 | 7/7/05 |

| 29 {172 + 45.2} | | | | | |

| {172 + 81.9} | 332.28 | 384.00 | 1.16 | 7/11/05 | 7/19/05 |

| 31 {174 + 78.0} | | | | | |

| {175 + 18.5} | 477.22 | 567.50 | 1.19 | 7/29/05 | 8/6/05 |

| 32 {174 + 29.6} | | | | | |

| {174 + 78.0} | 375.00 | 434.25 | 1.16 | 8/5/05 | 8/12/05 |

| 43 {177 + 94.0} | | | | | |

| {178 + 44.1} | 174.83 | 219.75 | 1.26 | 11/9/05 | 11/12/05 |

| Pier {168 + 72.6} | | | | | |

| {168 + 81.1} | 106.52 | 144.00 | 1.35 | 12/6/06 | 12/8/06 |

| 76 {178 + 44.1} | | | | | |

| {178 + 94.1} | 130.36 | 142.50 | 1.09 | 7/8/07 | 7/10/07 |

| 79 {178 + 94.1} | | | | | |

| {179 + 44.1} | 113.82 | 129.50 | 1.14 | 7/15/07 | 7/16/07 |

| 82 {179 + 44.1} | | | | | |

| {179 + 93.7} | 123.06 | 131.75 | 1.07 | 7/22/07 | 7/23/07 |

| 84 {179 + 93.7} | | | | | |

| {180 + 44.2} | 123.70 | 133.50 | 1.08 | 7/26/07 | 7/27/07 |

| 86 {180 + 44.2} | | | | | |

| {180 + 93.6} | 158.82 | 167.00 | 1.05 | 7/30/07 | 7/31/07 |

| 90 {180 + 93.6} | | | | | |

| {181 + 17.9} | 90.82 | 115.00 | 1.27 | 8/18/08 | 8/18/08 |

|___________________|__________|__________|______|__________|__________|

NOTE.--The number of cubic yards of crushed stone used in any section

can be found by multiplying the figure for that section in Column 10 by

0.7778.

The number of cubic yards of sand used in any section can be found by

multiplying: the sum of the figures for that section in Columns 4, 6,

and 10 by 0.3889.

REMARKS.--Section No. 4. Amount of sand cut down on a part of this

section on account of dust in stone.

Section No. 8. O'Rourke stone used on this section, large and full of

dust.

Section No. 9. Stone crushed on the work used on this section, large

and full of dust.

Section No. 21. 1:3:5 mix was used in part of this section on account

of stone being large.

Section No. 24. Different sized stone was shipped on barge and mixed

on the board for this section.

Section No. 25. 1:3:5 mix used in a small part of this section on

account of stone being large.

Sections Nos. 76, 82, 84, and 86. Stone contained large amount of

dust.

TABLE 2a.--Record of Retaining-wall Sections, Terminal Station.

West Thirty-third Street from Seventh Avenue to Ninth Avenue.

(1) Section No.

(2) Stations.

(3) Contents of section, in cubic yards.

(4) Barrels of cement used for facing.

(5) Cubic yards of facing mortar equivalent.

(6) Barrels of cement used for bed mortar.

(7) Cubic yards of bed mortar equivalent.

(8) Cubic yards of embedded stone.

(1) (2) (3) (4) (5) (6) (7) (8)

___________________________________________________________________

| 30 {170 + 73.2} | | | | | | |

| {171 + 16.1} | 364.72 | 42.50 | 14.46 | 4.00 | 1.36 | ... |

| 33 {178 + 48.7} | | | | | | |

| {178 + 84.1} | 180.40 | 29.50 | 10.04 | 3.50 | 1.19 | ... |

| 34 {R 2 + 75.5} | | | | | | |

| {170 + 03.5} | 214.12 | 38.00 | 12.93 | 1.00 | 0.34 | 1.50 |

| 35 {171 + 16.1} | | | | | | |

| {171 + 42.5} | 381.56 | 40.25 | 13.70 | 1.00 | 0.34 | 14.37 |

| 36 {170 + 03.6} | | | | | | |

| {170 + 25.0} | 150.16 | 20.50 | 6.98 | ... | ... | 6.25 |

| 37 {171 + 42.5} | | | | | | |

| {171 + 91.3} | 869.40 | 59.50 | 20.25 | 4.50 | 1.53 | 44.96 |

| 38 {171 + 91.3} | | | | | | |

| {172 + 19.2} | 233.49 | 22.75 | 7.74 | 2.75 | 0.94 | 14.45 |

| 39 {179 + 27.2} | | | | | | |

| {179 + 64.2} | 255.39 | 32.00 | 10.89 | 3.00 | 1.02 | 9.05 |

| 40 {170 + 25.0} | | | | | | |

| {170 + 73.2} | 500.73 | 44.25 | 15.06 | 1.00 | 0.34 | 29.64 |

| 41 {169 + 50.8} | | | | | | |

| {R 2 + 75.5} | 215.93 | 28.25 | 9.61 | 2.00 | 0.68 | ... |

| 42 {178 + 84.1} | | | | | | |

| {179 + 27.2} | 177.62 | 23.00 | 7.83 | 1.50 | 0.51 | 7.06 |

| 44 {180 + 05.5} | | | | | | |

| {180 + 44.2} | 936.15 | 58.75 | 19.99 | 10.50 | 3.47 | 73.84 |

| 45 {180 + 44.2} | | | | | | |

| {180 + 74.9} | 1,133.59 | 60.00 | 20.42 | 5.00 | 1.70 | 60.71 |

| 46 {179 + 64.2} | | | | | | |

| {180 + 05.5} | 477.14 | 35.00 | 11.91 | 3.75 | 1.28 | 24.58 |

| 47 {169 + 00.1} | | | | | | |

| {169 + 50.8} | 136.19 | 14.25 | 4.85 | 3.50 | 1.19 | 2.00 |

| 48 {178 + 24.1} | | | | | | |

| {178 + 48.7} | 192.78 | 21.25 | 7.23 | 2.00 | 0.68 | ... |

| 49 {177 + 81.1} | | | | | | |

| {178 + 24.1} | 241.51 | 25.25 | 8.59 | 2.50 | 0.85 | 1.33 |

| 50 {168 + 03.6} | | | | | | |

| {168 + 45.6} | 405.61 | 25.50 | 8.68 | 4.00 | 1.36 | 36.10 |

| 51 {177 + 38.4} | | | | | | |

| {177 + 81.1} | 100.54 | 12.75 | 4.34 | 3.00 | 1.02 | 0.78 |

| 52 {168 + 45.6} | | | | | | |

| {168 + 80.1} | 181.96 | 19.00 | 6.47 | 1.00 | 0.34 | 9.03 |

| 53 {168 + 80.1} | | | | | | |

| {169 + 00.1} | 41.32 | 3.50 | 1.19 | ... | ... | ... |

| 55 {176 + 90.0} | | | | | | |

| {177 + 38.4} | 92.41 | 11.25 | 3.83 | 2.50 | 0.85 | 3.68 |

| 56 {167 + 62.1} | | | | | | |

| {168 + 03.6} | 383.67 | 33.75 | 11.48 | 3.25 | 1.11 | 36.62 |

| 59 {175 + 67.3} | | | | | | |

| {175 + 98.9} | 175.61 | 15.50 | 5.27 | 2.50 | 0.85 | 9.37 |

| 60 {176 + 49.0} | | | | | | |

| {176 + 90.0} | 69.97 | 8.25 | 2.81 | 3.00 | 1.02 | 1.58 |

| 61 {175 + 98.9} | | | | | | |

| {176 + 49.0} | 104.56 | 8.00 | 2.72 | 3.50 | 1.19 | 3.72 |

| 64 {175 + 30.3} | | | | | | |

| {175 + 67.3} | 140.15 | 14.75 | 5.02 | 2.75 | 0.94 | ... |

| 65 {174 + 85.4} | | | | | | |

| {175 + 30.3} | 80.66 | 9.00 | 3.06 | 2.50 | 0.85 | ... |

| 66 {174 + 47.9} | | | | | | |

| {174 + 85.4} | 68.89 | 5.50 | 1.87 | 3.25 | 1.11 | ... |

| 67 {174 + 21.1} | | | | | | |

| {174 + 47.9} | 60.14 | 3.00 | 1.02 | 2.00 | 0.68 | 0.92 |

| 68 {167 + 12.3} | | | | | | |

| {167 + 62.1} | 379.94 | 23.50 | 8.00 | 5.00 | 1.70 | 19.34 |

| 69 {173 + 85.6} | | | | | | |

| {174 + 21.1} | 77.43 | 6.50 | 2.21 | 3.00 | 1.02 | ... |

| 70 {166 + 75.6} | | | | | | |

| {167 + 12.3} | 408.81 | 33.75 | 11.48 | 3.75 | 1.28 | ... |

| 71 {173 + 46.5} | | | | | | |

| {173 + 85.6} | 85.92 | 8.25 | 2.81 | 1.75 | 0.60 | ... |

| 74 {172 + 19.2} | | | | | | |

| {172 + 73.0} | 449.28 | 22.75 | 7.74 | 6.25 | 2.13 | ... |

| 75 {172 + 73.0} | | | | | | |

| {173 + 24.0} | 502.20 | 27.25 | 9.27 | 7.00 | 2.38 | ... |

| 77 {164 + 77.0} | | | | | | |

| {165 + 27.1} | 141.38 | 9.00 | 3.06 | 7.25 | 2.47 | ... |

| 78 {168 + 83.4} | | | | | | |

| {169 + 18.3} | 63.35 | 3.00 | 1.02 | 1.50 | 0.51 | ... |

| 80 {165 + 27.1} | | | | | | |

| {165 + 76.6} | 108.86 | 11.75 | 4.00 | 3.00 | 1.02 | ... |

| 81 {168 + 45.6} | | | | | | |

| {168 + 83.4} | 210.97 | 13.00 | 4.42 | 6.25 | 2.13 | ... |

| 83 {165 + 76.6} | | | | | | |

| {166 + 20.5} | 108.06 | 8.00 | 2.72 | 3.75 | 1.28 | ... |

| 85 {166 + 20.5} | | | | | | |

| {166 + 64.6} | 107.52 | 9.00 | 3.06 | 2.25 | 0.76 | ... |

| 87 {166 + 64.6} | | | | | | |

| {166 + 75.6} | 23.44 | 1.00 | 0.34 | 2.25 | 0.42 | ... |

| 88 {164 + 26.3} | | | | | | |

| {164 + 77.0} | 317.72 | 24.00 | 8.17 | 2.25 | 0.76 | ... |

| 89 {173 + 20.8} | | | | | | |

| {173 + 46.5} | 93.51 | 5.60 | 1.70 | 1.50 | 0.51 | ... |

| 91 {180 + 74.9} | | | | | | |

| {180 + 92.7} | 141.40 | 17.50 | 5.96 | ... | ... | ... |

| 92 {180 + 92.7} | | | | | | |

| {181 + 28.8} | 118.93 | 19.00 | 6.46 | ... | ... | ... |

|_________________|__________|_______|_______|_______|______|_______|

TABLE 2b.--Record of Retaining-wall Sections, Terminal Station.

West Thirty-third Street from Seventh Avenue to Ninth Avenue.

(1) Section No.

(2) Stations.

(9) Cubic yards of concrete in section (net).

(10) Barrels of cement used in concrete.

(11) Barrels of cement per cubic yard of concrete.

(12) Concrete started.

(13) Concrete finished.

(1) (2) (9) (10) (11) (12) (13)

___________________________________________________________________

|30 {170 + 73.2} | | | | | |

| {171 + 16.1} | 348.90 | 391.00 | 1.12 | 7/20/05 | 7/26/05 |

|33 {178 + 48.7} | | | | | |

| {178 + 84.1} | 169.17 | 188.00 | 1.11 | 8/7/05 | 8/11/05 |

|34 {R 2 + 75.5} | | | | | |

| {170 + 03.5} | 199.35 | 217.25 | 1.09 | 8/14/05 | 8/19/05 |

|35 {171 + 16.1} | | | | | |

| {171 + 42.5} | 353.15 | 400.25 | 1.13 | 8/16/05 | 8/22/05 |

|36 {170 + 03.6} | | | | | |

| {170 + 25.0} | 136.93 | 133.75 | 0.98 | 8/19/05 | 8/22/05 |

|37 {171 + 42.5} | | | | | |

| {171 + 91.3} | 802.66 | 909.00 | 1.13 | 8/22/05 | 9/6/05 |

|38 {171 + 91.3} | | | | | |

| {172 + 19.2} | 210.36 | 238.50 | 1.13 | 8/24/05 | 8/27/05 |

|39 {179 + 27.2} | | | | | |

| {179 + 64.2} | 234.43 | 270.25 | 1.15 | 8/29/05 | 9/2/05 |

|40 {170 + 25.0} | | | | | |

| {170 + 73.2} | 455.69 | 525.75 | 1.15 | 9/11/05 | 9/15/05 |

|41 {169 + 50.8} | | | | | |

| {R 2 + 75.5} | 205.64 | 236.50 | 1.15 | 10/3/05 | 10/6/05 |

|42 {178 + 84.1} | | | | | |

| {179 + 27.2} | 162.22 | 194.75 | 1.20 | 10/9/05 | 10/11/05 |

|44 {180 + 05.5} | | | | | |

| {180 + 44.2} | 838.85 | 987.00 | 1.18 | 11/17/05 | 11/27/05 |

|45 {180 + 44.2} | | | | | |

| {180 + 74.9} | 1,050.86 | 1,206.00 | 1.15 | 12/13/05 | 12/23/05 |

|46 {179 + 64.2} | | | | | |

| {180 + 05.5} | 439.37 | 535.00 | 1.22 | 1/15/06 | 1/19/06 |

|47 {169 + 00.1} | | | | | |

| {169 + 50.8} | 128.15 | 150.50 | 1.17 | 4/4/06 | 4/6/06 |

|48 {178 + 24.1} | | | | | |

| {178 + 48.7} | 184.87 | 226.00 | 1.22 | 4/24/06 | 4/30/06 |

|49 {177 + 81.1} | | | | | |

| {178 + 24.1} | 230.74 | 274.00 | 1.19 | 5/21/06 | 5/24/06 |

|50 {168 + 03.6} | | | | | |

| {168 + 45.6} | 359.47 | 406.00 | 1.13 | 6/13/06 | 6/18/06 |

|51 {177 + 38.4} | | | | | |

| {177 + 81.1} | 94.40 | 112.00 | 1.19 | 6/20/06 | 6/21/06 |

|52 {168 + 45.6} | | | | | |

| {168 + 80.1} | 166.12 | 190.00 | 1.14 | 6/25/06 | 6/28/06 |

|53 {168 + 80.1} | | | | | |

| {169 + 00.1} | 40.13 | 44.50 | 1.11 | 6/29/06 | 6/29/06 |

|55 {176 + 90.0} | | | | | |

| {177 + 38.4} | 84.05 | 98.25 | 1.17 | 8/17/06 | 8/18/06 |

|56 {167 + 62.1} | | | | | |

| {168 + 03.6} | 334.46 | 383.50 | 1.14 | 8/28/06 | 9/1/06 |

|59 {175 + 67.3} | | | | | |

| {175 + 98.9} | 160.12 | 186.00 | 1.16 | 10/15/06 | 10/16/06 |

|60 {176 + 49.0} | | | | | |

| {176 + 90.0} | 64.56 | 75.00 | 1.16 | 10/17/06 | 10/18/06 |

|61 {175 + 98.9} | | | | | |

| {176 + 49.0} | 96.93 | 108.00 | 1.11 | 10/19/06 | 10/20/06 |

|64 {175 + 30.3} | | | | | |

| {175 + 67.3} | 134.19 | 161.50 | 1.20 | 11/21/06 | 11/22/06 |

|65 {174 + 85.4} | | | | | |

| {175 + 30.3} | 76.75 | 92.75 | 1.21 | 12/14/06 | 12/15/06 |

|66 {174 + 47.9} | | | | | |

| {174 + 85.4} | 65.91 | 83.50 | 1.27 | 12/18/06 | 12/18/06 |

|67 {174 + 21.1} | | | | | |

| {174 + 47.9} | 57.52 | 67.50 | 1.17 | 12/21/06 | 12/21/06 |

|68 {167 + 12.3} | | | | | |

| {167 + 62.1} | 350.90 | 412.50 | 1.17 | 1/2/07 | 1/6/07 |

|69 {173 + 85.6} | | | | | |

| {174 + 21.1} | 74.20 | 91.00 | 1.23 | 1/29/07 | 1/30/07 |

|70 {166 + 75.6} | | | | | |

| {167 + 12.3} | 396.05 | 468.50 | 1.18 | 4/2/07 | 4/10/07 |

|71 {173 + 46.5} | | | | | |

| {173 + 85.6} | 82.51 | 95.75 | 1.16 | 4/17/07 | 4/19/07 |

|74 {172 + 19.2} | | | | | |

| {172 + 73.0} | 439.41 | 506.00 | 1.15 | 6/20/07 | 6/24/07 |

|75 {172 + 73.0} | | | | | |

| {173 + 24.0} | 490.55 | 579.00 | 1.18 | 7/8/07 | 8/25/07 |

|77 {164 + 77.0} | | | | | |

| {165 + 27.1} | 135.85 | 161.50 | 1.19 | 7/13/07 | 7/15/07 |

|78 {168 + 83.4} | | | | | |

| {169 + 18.3} | 61.82 | 73.00 | 1.18 | 7/13/07 | 7/14/07 |

|80 {165 + 27.1} | | | | | |

| {165 + 76.6} | 103.84 | 133.50 | 1.28 | 7/18/07 | 7/19/07 |

|81 {168 + 45.6} | | | | | |

| {168 + 83.4} | 204.42 | 255.75 | 1.25 | 7/20/07 | 7/23/07 |

|83 {165 + 76.6} | | | | | |

| {166 + 20.5} | 104.06 | 128.50 | 1.23 | 7/25/07 | 7/27/07 |

|85 {166 + 20.5} | | | | | |

| {166 + 64.6} | 103.70 | 144.50 | 1.39 | 7/29/07 | 7/30/07 |

|87 {166 + 64.6} | | | | | |

| {166 + 75.6} | 22.68 | 30.00 | 1.32 | 7/31/07 | 7/31/07 |

|88 {164 + 26.3} | | | | | |

| {164 + 77.0} | 308.79 | 370.00 | 1.20 | 8/8/07 | 8/11/07 |

|89 {173 + 20.8} | | | | | |

| {173 + 46.5} | 91.30 | 121.75 | 1.33 | 9/7/07 | 9/8/07 |

|91 {180 + 74.9} | | | | | |

| {180 + 92.7} | 135.44 | 203.50 | 1.50 | 11/18/07 | 11/20/0 |

|92 {180 + 92.7} | | | | | |

| {181 + 28.8} | 112.47 | 190.00 | 1.69 | 12/1/08 | 12/2/08 |

|________________|__________|__________|______|__________|__________|

NOTE.--The number of cubic yards of crushed stone used in any section

can be found by multiplying the figure for that section in Column 10 by

0.7778.

The number of cubic yards of sand used in any section can be found by

multiplying the sum of the figures for that section in Columns 4, 6, and

10 by 0.3889.

REMARKS.--Section No. 47. Part of this section was removed on account

of damage done by blasting and was replaced by Section No. 78.

Section No. 52. All of this section was removed on account of damage

done by blasting and was replaced by Section No. 81.

Section No. 53. All of this section was removed on account of damage

done by blasting and was replaced by Sections Nos. 78 and 81.

TABLE 3a.--Record of Retaining Wall Sections.

(1) Section No.

(2) Stations.

(3) Contents of section, in cubic yards.

(4) Barrels of cement used for facing.

(5) Cubic yards of facing mortar equivalent.

(6) Barrels of cement used for bed mortar.

(7) Cubic yards of bed mortar equivalent.

(8) Cubic yards of embedded stone.

Power-House.

(1) (2) (3) (4) (5) (6) (7) (8)

________________________________________________________________

| A {L 2 + 75.3} | | | | | | |

| {L 3 + 25.3} | 463.28 | 58.25 | 19.82 | 5.50 | 1.87 | 11.50 |

| B {L 3 + 25.3} | | | | | | |

| {L 3 + 74.9} | 114.78 | 23.00 | 7.83 | 1.75 | 0.60 | 1.50 |

| C {169 + 30.8} | | | | | | |

| {169 + 74.8} | 179.19 | 34.25 | 11.66 | 1.00 | 0.34 | 3.60 |

| D {169 + 74.8} | | | | | | |

| {170 + 28.8} | 114.38 | 27.25 | 9.27 | 0.25 | 0.09 | 0.07 |

| E {168 + 83.6} | | | | | | |

| {169 + 30.8} | 101.20 | 22.00 | 7.49 | 1.50 | 0.51 | 0.65 |

| F {L 2 + 78.2} | | | | | | |

| {L 3 + 19.6} | 358.80 | 39.50 | 13.44 | 0.75 | 0.26 | 9.50 |

| G {L 3 + 19.6} | | | | | | |

| {L 3 + 56.9} | 237.33 | 23.00 | 7.83 | 1.00 | 0.34 | 0.74 |

| H {L 3 + 56.9} | | | | | | |

| {168 + 83.5} | 25.55 | 6.25 | 2.13 | 0.75 | 0.26 | ... |

|_________________|________|_______|_______|______|______|_______|

Seventh Avenue.

________________________________________________________________

| 54 {164 + 27.6} | | | | | | |

| {L 2 + 32.0} | 764.48 | 69.75 | 23.74 | 3.00 | 1.02 | ... |

| 57 {L 2 + 10.3} | | | | | | |

| {L 2 + 32.0} | 533.06 | 34.00 | 11.57 | 2.25 | 0.77 | ... |

| 58 {L 1 + 87.1} | | | | | | |

| {L 2 + 10.3} | 544.54 | 32.25 | 10.97 | 2.00 | 0.68 | 9.80 |

| 62 {L 1 + 87.1} | | | | | | |

| {L 1 + 64.4} | 575.67 | 30.00 | 10.21 | 3.00 | 1.02 | 6.20 |

| 63 {L 1 + 42.4} | | | | | | |

| {L 1 + 64.4} | 607.01 | 30.50 | 10.38 | 2.50 | 0.85 | 3.79 |

| 72 {L 1 + 42.4} | | | | | | |

| {L 1 + 19.6} | 631.97 | 30.00 | 10.21 | 1.75 | 0.60 | 1.18 |

| 73 {L 1 + 19.6} | | | | | | |

| {L 0 + 97.0} | 573.33 | 25.25 | 8.59 | 0.25 | 0.08 | 2.48 |

|_________________|________|_______|_______|______|______|_______|

TABLE 3b.--Record of Retaining Wall Sections.

(1) Section No.

(2) Stations.

(9) Cubic yards of concrete in section (net).

(10) Barrels of cement used in concrete.

(11) Barrels of cement per cubic yard of concrete.

(12) Concrete started.

(13) Concrete finished.

Power-House.

(1) (2) (9) (10) (11) (12) (13)

________________________________________________________________

| A {L 2 + 75.3} | | | | | |

| {L 3 + 25.3} | 430.09 | 482.75 | 1.12 | 5/18/05 | 5/25/05 |

| B {L 3 + 25.3} | | | | | |

| {L 3 + 74.9} | 104.85 | 125.50 | 1.20 | 6/14/05 | 6/16/05 |

| C {169 + 30.8} | | | | | |

| {169 + 74.8} | 163.59 | 183.00 | 1.12 | 7/10/05 | 7/13/05 |

| D {169 + 74.8} | | | | | |

| {170 + 28.8} | 104.95 | 119.25 | 1.14 | 7/14/05 | 7/19/05 |

| E {168 + 83.6} | | | | | |

| {169 + 30.8} | 92.55 | 107.25 | 1.16 | 7/26/05 | 7/28/05 |

| F {L 2 + 78.2} | | | | | |

| {L 3 + 19.6} | 335.60 | 397.75 | 1.18 | 9/19/05 | 9/24/05 |

| G {L 3 + 19.6} | | | | | |

| {L 3 + 56.9} | 228.42 | 278.00 | 1.22 | 9/26/05 | 9/29/05 |

| H {L 3 + 56.9} | | | | | |

| {168 + 83.5} | 23.16 | 28.00 | 1.21 | 9/29/05 | 9/29/05 |

|_________________|________|________|______|__________|__________|

Seventh Avenue.

________________________________________________________________

| 54 {164 + 27.6} | | | | | |

| {L 2 + 32.0} | 739.72 | 907.50 | 1.23 | 8/6/06 | 8/15/06 |

| 57 {L 2 + 10.3} | | | | | |

| {L 2 + 32.0} | 520.72 | 610.75 | 1.17 | 9/10/06 | 9/15/06 |

| 58 {L 1 + 87.1} | | | | | |

| {L 2 + 10.3} | 523.09 | 588.25 | 1.12 | 9/24/06 | 9/28/06 |

| 62 {L 1 + 87.1} | | | | | |

| {L 1 + 64.4} | 538.24 | 639.50 | 1.19 | 10/24/06 | 10/29/06 |

| 63 {L 1 + 42.4} | | | | | |

| {L 1 + 64.4} | 581.99 | 678.50 | 1.17 | 11/5/06 | 11/11/06 |

| 72 {L 1 + 42.4} | | | | | |

| {L 1 + 19.6} | 619.98 | 719.50 | 1.16 | 4/25/07 | 4/30/07 |

| 73 {L 1 + 19.6} | | | | | |

| {L 0 + 97.0} | 562.18 | 685.75 | 1.22 | 5/13/07 | 5/18/07 |

|_________________|________|________|______|__________|__________|

NOTE.--The number of cubic yards of crushed stone used in any section

can be found by multiplying the figure for that section in Column 10 by

0.7778. The number of cubic yards of sand used in any section can be

found by multiplying the sum of the figures for that section in Columns

4, 6, and 10 by 0.3889.

Channeling with a 10-ft quarry bar, carrying a No. 4 Ingersoll-Rand

drill with Z-bits, was attempted in place of the close drilling below

the walls, but, as the rock stood so nearly vertical and was full of

soft seams, very little could be accomplished, the average cut per day

of 10 hours, counting the time of moving and setting up, was only 4 sq.

ft., and, after a thorough trial, the bars were abandoned.

_Disposal._--The excavated material was hauled from the shovels to the

pier in 10-car trains. The cars were of three classes: 4-yd. Western

dump-cars, flat cars without skips, and flats carrying specially

designed steel skips having a capacity of 4 cu. yd. each. As far as

practicable, earth, and rock containing 1 cu. yd. or less, was loaded

on dumpers, medium-sized rock on the skips, and large rock on the bare

flats. As a steam shovel must pick up what is nearest to it first,

however, this classification could not always be adhered to, and many

large rocks were loaded into dumpers. Cars of this class which contained

no material too large to dump were run at once to the hoppers, and were

dumped and returned to the pit; others, together with the flat and skip

cars, were run down the incline to the derricks and telphers, where the

flats and skips were entirely unloaded, and the large rocks ware removed

from the dumpers, after which they were run to the hoppers and emptied.

The total quantity of excavated material handled at this pier from May

22d, 1905, to December 31st, 1908, amounted to 673,800 cu. yd. of earth

and 1,488,000 cu. yd. of rock, place measurement, equal to 3,203,400 cu.

yd., scow measurement; in addition to which 175,000 cu. yd. of crushed

stone and sand and 6,000 car loads of miscellaneous building material

were transferred from scows and lighters to small cars for delivery to

the Terminal work.

All the earth and 570,000 cu. yd. of the rock, place measurement, were

handled through the chutes, and the remainder of the rock, 918,000 cu.

yd., and all the incoming material by the derricks and telphers. In

capacity to handle material, one telpher was about equal to one derrick.

A train, therefore, could be emptied or a boat loaded under the bank of

eight telphers in one-fourth the time required by the derricks, of which

only two could work on one boat. The telphers, therefore, were of great

advantage where track room and scow berths were limited.

As noted in the list of contracts under which the work was executed,

the scows at both the 35th Street dumping board and Pier No. 72 were

furnished, towed, and the material finally disposed of, by Henry Steers,

Incorporated. During the same period, this contractor disposed of the

material excavated from both the Cross-town Tunnels, constructed by the

United Engineering and Contracting Company, and the tunnels under the

East River, constructed by S. Pearson and Son, Incorporated. As stated

in other papers of this series relating to the construction of those

tunnels, the material excavated by the United Engineering and

Contracting Company was delivered to barges at 35th Street and East

River and that by S. Pearson and Son, Incorporated, at two points, one

in Long Island City and the other at 33d Street and East River,

Manhattan.

The total number of cubic yards of material disposed of amounted to:

Place measurement. Total barge

Earth. Rock. measurement.

35th Street and North River 242,800 22,800 281,500

Pier No. 72, North River 673,800 1,488,000 3,203,400

From Cross-town Tunnels 570,400

From Under-river Tunnels 402,500

-----------

Total 4,457,800

===========

The material was delivered as follows:

To the freight terminal of the Pennsylvania Railroad

Company at Greenville, N.J. 3,454,800

To the Meadows Division of the Tunnel Line between

Harrison, N.J., and the North River Portals 711,900

To other points selected by the contractors 291,100

---------

Total 4,457,800

=========

The handling of this large quantity of material required the loading of

from 10 to 20 scows per day (and for more than two years the average was

14), and, as the average time spent in one round trip was 3 1/3 days, a

fleet of more than 50 scows was required to keep all points supplied and

allow for a few to be out of service undergoing repairs.

All loaded scows were towed from the docks, with the ebb tide, to a

stake boat anchored in the bay about one mile off shore at Greenville;

and were taken from there to the different unloading points, as

required, by smaller tugs which also returned the empty scows to the

stake.

The unloading plants were similar at the different points, although that

at Greenville was much larger than the others. It included five land

dredges and eight traveling derricks of two types, one floating and the

other mounted on wheels and traveling on a track of 16-ft. gauge. The

derricks handled the large rock, which was loaded at Pier No. 72 by

derricks and telphers. They were of the ordinary A-frame type, and were

designed to handle 20 tons. They were operated by 9 by 10-in. Lidgerwood

double-drum and swinging-gear engines. The large rock was deposited by

the derricks either in the channels along which they worked or in the

fill along shore, without the use of cars. The land dredges were

equipped with a 60-ft. boom and a 2½-yd. Hayward bucket operated by a

14 by 18-in. double-drum Lidgerwood dredging engine. They loaded into

9-yd., standard-gauge, side-dump cars, built by the contractor, and

unloaded the scows to within about 1 ft. of the deck, a Hayward bucket

being unsuitable for closer work without greatly damaging the scows.

The material remaining was loaded by hand into skips which were handled

to the cars by small derricks, one of which was located at the rear of

each dredge. The cars were taken to the dump and returned by 25-ton,

standard-gauge, engines which had previously done service on the

Manhattan Elevated Railroad, but were spotted for loading by the engine

on the dredge.

In order to keep a record of the fleet of scows, which would show the

available supply at a glance, a board, 10 by 15 in., and covered with a

heavy sheet of ruled paper, was arranged as shown by Fig. 10. It was

divided into 12 vertical columns, the first of which was headed "Scows,"

and contained the name or number of each scow in service. The next four

columns denoted loading points, and were headed "Pier No. 72,"

"Thirty-third Street, East River," "Thirty-fifth Street, East River,"

and "Long Island City," respectively; the sixth column was headed

"Greenville," the seventh "Hackensack," the eighth "Passaic," and the

ninth "Governors Island," being unloading points, the tenth and

eleventh, "Stake Boat" and "Dry Dock," respectively, while the twelfth

was for "Extra pins," not in use. To indicate the condition of the

scows, small pins with colored heads were used; white indicated empty;

blue, working; black, loaded; red, being repaired; and a pearl-colored

pin, missing. Thus a white-headed pin opposite the number 6 in the

column headed Pier No. 72 indicated that scow No. 6 was lying at that

pier waiting to be placed in position for loading, whereas a

black-headed pin at the same point meant that the scow had received

its load and was ready to be towed.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The Site of the Terminal Station. Paper No. 1157 · 第 10 / 12 题