CHAPTER X.

FOOT-BRIDGES.

Very pleasing effects may be produced in public or private recreation

grounds by the constructional use of rustic work of good design.

[Illustration: Fig. 121.--Rustic Foot-bridge.]

[Illustration: Fig. 122.--Cross Section of Foot-bridge.]

[Illustration: Fig. 123.--Enlarged Section of Girders for Foot-bridge.]

[Illustration: Fig. 124.]

[Illustration: Fig. 125.]

[Illustration: Figs. 124 and 125.--Parts of Joint of Post and Girder.]

[Illustration: Fig. 126.--Detail of Middle Rail and Post of Foot-bridge.]

[Illustration: Figs. 127 and 128.--Joint of Strut to Post of Foot-bridge.]

[Illustration: Fig. 129.--Twig Hollowed to fit Rail of Foot-bridge.]

Fig. 121 is a perspective view of a rustic foot-bridge suitable for a

span of 8 ft. or 12 ft. The banks of the stream to be bridged are

excavated to allow of the building of a low rubble wall, on which the

sleepers rest, as shown in Fig. 122. The girders are formed of spruce or

larch spars. In the present instance, four are used; and they may be 8

in. or 10 in. in diameter, according to the length of the span. They are

roughly adzed down to sit on the sleepers, and each girder is also

worked down tolerably flat on the inner sides. The girders are then

bolted together in pairs with six 3/4-in. diameter coach bolts, as

shown by Fig. 123. The posts are tenoned and wedged to fit mortices in

the girders. Figs. 124 and 125 show the mortice and tenon joint.

[Illustration: Fig. 130.--Elevated Foot-bridge.]

The posts and top rails are 4-1/2 in. or 5-1/2 in. in diameter, and the

intermediate rails 3 in. in diameter. Fig. 126 indicates the method of

jointing the rails to the posts. The girder spars, with posts and rails

fitted, having been placed in position on the sleepers, and plumbed up

and stayed, the floor battens, 11 in. by 2-1/2 in., are fixed and the

struts are fitted and pinned or spiked to the posts and sleepers. The

joint for the struts is shown by Figs. 127 and 128.

[Illustration: Fig. 131.--Girder and Post of Elevated Foot-bridge Bolted

to Sleeper.]

[Illustration: Fig. 132.--Cross Section of Elevated Foot-bridge at Lower

Step (Fig. 130).]

If the bridge happens to be in a locality that is subject to periodical

flooding, it should be anchored to prevent its being unseated by flood

water. The anchoring can be best effected by driving four short piles

into the soil on the inside of both girders and near their ends. The

girders can be fastened to the piles with coach bolts. The tops of the

piles will be concealed by the end floor battens. The smaller twigs

forming the ornamentation are now fixed, and Fig. 129 shows the

vertical piece hollowed to fit the rails.

Fig. 130 gives a part view, in longitudinal section, of an elevated

bridge, suitable for a span of 12 ft. to 18 ft., and raised on piles to

enable small boats and canoes to pass under. Elm logs are suitable for

the pile foundation. An iron ring must be fitted over the tops of the

logs while they are being driven, and it will be necessary to use a

pile-driver. The logs, having been sufficiently driven, are cut off to

the required height from the ground line. Three piles on each side are

required to carry the sleepers. The bridge is 5 ft. 6 in. wide, and the

spars for girders are 12 in. in diameter. The sleepers are bolted to the

piles, and the girders are also bolted to the sleepers as shown by Fig.

131. A row of smaller piles is now driven, and a plank, 11 in. by 3 in.,

is housed to the top ends of these piles, and also connected to the

projecting ends of the girders. The treads of the steps rest upon the

tops of the smaller piles, and the outer side of the piles and planks is

covered with split saplings (see Fig. 130, and the cross-section, Fig.

132). The handrails and balustrades are fixed in similar manner to those

in Fig. 121.