CHAPTER IX

VITRIFIED BRICK ROADS

Vitrified brick roads consist of a foundation course of Portland

cement concrete, broken stone or slag macadam, or of brick laid flat,

the first named being by far the most generally used, and a wearing

course of vitrified brick.

=Vitrified Brick.=--Vitrified brick are made from clay of such a

character that when heated to the required temperature they will fuse

into a glassy texture. Brick roads are constructed on roads carrying

the severest of traffic and the brick must therefore be tough and of

high resistance to wear.

Not all of the clays from which brick may be manufactured will produce

a product suitable for road construction, and paving brick, even

though truly vitrified, are of different degrees of durability,

depending upon the nature of the clay and the care exercised in the

manufacture.

Paving brick are manufactured by the stiff mud process, which means

that the clay is molded into form in a relatively dry condition. To

accomplish this, considerable pressure is exerted in forcing the

column of clay through the dies, which form the prism from which the

brick are cut. If the clay is unsuitable in character or is not

properly ground and mixed, the brick will possess planes of weakness

between the various layers of clay which have been pressed together,

and these planes, called laminations, are a source of weakness if too

marked. It is usual to specify that the brick used for road surfaces

shall be free from marked laminations.

If the brick is not properly burned it will be only partly vitrified

and therefore not of maximum durability. It is customary to specify

that the brick shall show a glassy fracture indicating complete

vitrification.

Various defects of a minor nature occasionally develop in the brick

during the successive steps in the manufacturing process. Check cracks

resulting from the burning or from too rapid cooling are often

encountered, but unless these are deep, that is 3/16 inch or more,

they do not impair the wearing quality of the brick, nor indicate

structural weakness. Kiln marks are formed on some of the brick due to

the weight of the brick above in the kiln. These depressions are not

objectionable unless the brick are so distorted that they will not lie

evenly in the pavement.

Spacing lugs or raised letters are formed on one face of the brick to

insure sufficient space between the brick for the filler. These lugs

or letters are not less than 1/8 inch nor more than 1/4 inch high and

of such design that they will not obstruct the free flow of filler

into the joints between the brick.

Several varieties of paving brick are to be had, the difference being

principally in the design or size.

=Repressed Brick.=--In this type of brick the spacing lugs are formed

by pressing the green brick, after it has been cut to size, into a

mold on one face of which are recessed letters or other devices into

which the clay is pressed, thus forming the spacing lugs.

=Vertical Fiber Brick.=--These brick are designed to be laid with one

wire-cut face up and spacing is provided by two or more beads on the

side of the brick. Sometimes the vertical fiber brick has no spacing

lug, it being contended that the irregularities of the brick are such

as to provide all of the space required. In practice this does not

always work out, as the brick are so regular in shape that when laid

there is too little space between the brick to permit the introduction

of a suitable filler. The use of brick without spacing lugs is just

beginning and is not yet a generally accepted practice.

=Wire-cut-lug Brick.=--This is a type of non-repressed brick which has

spacing lugs provided by cutting one face in a special manner which

provided lugs for spacing. In this type the wire cut face is the one

between the brick as they are laid in the pavement.

=Tests for Quality.=--The standard test for quality of paving brick is

the rattler test. The brick rattler consists of a barrel of 14 sides

24 inches long, mounted so as to rotate at a speed between 29.5 and

30.5 revolutions per minute. The duration of a test is 1800

revolutions. Ten brick constitute a charge and these are placed in the

rattler along with 300 lbs. of cast iron spheres. The spheres are of

two sizes, the smaller being 1-7/8 inch in diameter when new, and the

larger 3-3/4 inches in diameter when new. Ten of the larger spheres

are used and the balance of the charge is made up of the small size.

When tested in the standard manner the loss allowable for the several

classes of service are as follows:

------------+---------------+----------------

| | Maximum Loss

Traffic | Average Loss | for any Brick

------------+---------------+----------------

Heavy | 20 per cent | 24 per cent

Medium | 22 per cent | 26 per cent

Light | 25 per cent | 28 per cent

------------+---------------+----------------

=Other Tests.=--Sometimes the absorption test is specified for paving

brick, but it is rarely a vitrified brick that will pass the rattler

tests which fails to pass a reasonable absorption test. Absorption of

water in an amount exceeding 4 per cent indicates incomplete

vitrification and failure of such brick is almost certain during the

rattler tests.

The cross breaking test is also sometimes employed, but generally

only to check the general quality of the brick. Failure in service

more frequently occurs from excessive wear than from any other cause

and the cross breaking test has little significance, except for brick

less than 3 inches thick, which are to be laid on a sand bedding

course.

=Foundation.=--The foundation for brick roads is usually of Portland

cement concrete, the thickness varying with the nature of the traffic

and the kind of soil upon which the pavement is built. For well

drained soils and normal highway traffic, 5 inches is the ordinary

thickness of foundation. Under favorable conditions such as locations

with sandy soils or in semi-arid or arid regions where the soil is

always stable, the foundation may be four inches thick, and a

considerable mileage of brick road has been built with concrete

foundations less than four inches thick.

In other locations the soil and traffic conditions require a base six

inches or more in thickness, and the proper thickness can be

determined only after all of the factors involved are known and have

been analyzed. It is impractical to adopt a standard thickness of

foundation that will be equally economical for all locations and all

kinds of traffic. As the brick pavement is essentially a heavy traffic

type of surface, the design cannot be varied greatly with similar

foundation conditions because the weight of individual loads is the

significant factor and this does not vary so much as the volume of

traffic. A variation in volume of traffic may be compensated for by a

variation in the quality of the brick as already set forth.

The mixtures for the concrete foundation vary widely because of the

variation in the aggregates employed. If the fine and coarse aggregate

for the concrete are of good quality a mixture of one part cement, two

and one-half parts sand and five parts of coarse aggregate would

insure concrete of adequate strength. A somewhat leaner mixture is

sometimes employed and would be satisfactory if the aggregates were of

exceptional concrete making quality. Mixtures of sand and pebbles

(unscreened gravel) may also be used if care is exercised to secure a

mixture of adequate strength. The proportion will of necessity vary

with each particular material and the discussion of the various

considerations involved may be obtained from various standard works on

concrete and concrete materials.

Broken stone macadam is sometimes utilized for the foundation course

of the brick pavement and such foundations are constructed as

water-bound, which is described in a previous chapter. The thickness,

like that of the concrete foundation, varies with the soil conditions

and the weight of the loads that are expected to use the road. The

macadam is placed in a single layer and is rolled and bonded with

screenings as described in the chapter dealing with water-bound

macadam. Six inches is a common thickness for the macadam base. This

type of foundation should be employed only where the soil is quite

stable and where material costs are such as to insure that the macadam

base is materially cheaper than one of concrete. This would usually be

in locations where the cost of cement is high because of long hauls

and where suitable macadam materials may be obtained close at hand.

Old macadam roads are sometimes utilized for the foundation for the

brick surface, but the instances where this is permissible are

comparatively few in number. When an old macadam is to be used it is

reshaped to the proper cross section and re-rolled and bonded so as to

afford a stable foundation of the proper cross slope.

BEDDING COURSE FOR BRICK SURFACES

In order to equalize the variations in size and shape of the brick,

they are laid on a bedding course composed of material into which the

brick may be forced by rolling. In this way the upper surfaces of all

brick can be brought to the proper elevation to insure smoothness and

easy riding qualities. Several kinds of bedding course are now

employed.

=Sand Bedding Course.=--The sand bedding course has been referred to

as a sand cushion, but as a matter of experience the cushion effect is

slight, although sometimes pavements have become uneven because the

brick have pushed down into the sand after the pavement was used for a

time. The sand for the bedding course should preferably be fine

grained, all particles passing the eight mesh sieve, but ordinary

concrete sand is satisfactory. The sand need not be clean, as a

comparatively large percentage of silt or clay does not impair the

usefulness of the material.

[Illustration: Fig. 19.--Cross Sections for Brick Highways]

=Sand Mortar Bedding Course.=--In order to eliminate the tendency for

the straight sand bedding course to shift because of the impact of

traffic on the brick, a lean cement mortar is sometimes employed

rather than the straight sand. Sand and cement in the ratio of one

part cement to four or five parts of sand are mixed dry, and after the

brick have been rolled, is moistened to furnish water to hydrate the

cement. The sand employed is ordinary clean concrete sand.

=Green Concrete Bedding Course.=--In the monolithic type of brick

road construction, the brick are laid directly on the green concrete

base before the concrete has taken a set and the irregularities of the

brick are taken up by rolling them until bedded in concrete.

FILLERS FOR BRICK SURFACES

The spaces between the brick are filled with some material that will

prevent the brick from being displaced and prevent water getting to

the bedding course. A suitable filler must adhere to the brick and

fill completely the spaces between them. It must withstand traffic so

as to remain intact in the joints and when in place it must be rigid

enough to prevent displacement of the brick.

=Cement Grout Filler.=--One of the most commonly used fillers for

brick pavements consists of a grout composed of Portland cement and

fine sand. When properly mixed and applied the grout filler meets all

requirements for a filler except that it is non-elastic and some means

must be adopted for caring for pavement expansion.

=Bituminous Fillers.=--Asphaltic materials and tars are widely used as

fillers for brick pavements. Such fillers are of high melting point

and consequently solid at ordinary temperature. They are poured into

the joints hot and when they cool are firm enough to comply with the

requirements for a filler. In addition, they have enough ductility to

accommodate the expansion of the pavement due to temperature changes.

=Mastic Fillers.=--Mastic consists of a mixture of about equal volumes

of fine sand and a solid bituminous material. The mixture is prepared

at high temperature and is worked into the joints between the brick

while hot. When cool it resembles the straight bituminous filler

except that the mastic is somewhat more resistant to wear than the

straight bituminous filler.

EXPANSION JOINTS

It is recognized that brick will expand and contract with changes in

temperature. When a bituminous or mastic filler is employed there is

sufficient yield to the filler to accommodate the change in dimension

in the brick, but when the grout filler is used either the expansion

joint must be provided or the pavement must be designed to withstand

the compression due to expansion of the brick. Expansion joints may

consist of a sheet of bituminous mastic prepared for the purpose and

set in place in the pavement. The sheet of joint material is simply

inserted between courses of brick at the proper place.

Another method of forming an expansion joint consists in placing a

strip of wood between courses of brick at the place where a joint is

required. After the pavement has been grouted, the wooden strip is

pulled out and the joint is filled with a suitable bituminous filler.

=Marginal Curb.=--If the sand bedding course is employed, it is

necessary to provide curbing along the sides of the brick to hold the

bedding course in place. The curb is usually constructed integral with

the base and of concrete of the same mixture as the base. The width of

the curb is usually six inches and the top of the curb is at the same

elevation as the edge of brick surface.

CONSTRUCTION OF THE SURFACE

Before the construction of a brick surface should be undertaken on a

road, the drainage should be provided for even more completely than

for a less costly type of surface since it does not pay to jeopardize

the stability of the pavement by failure to provide adequately for the

stability of the supporting soil. Grades should also be reduced to the

economical limit.

The earth subgrade is brought to the proper elevation and cross

section and is thoroughly rolled. If there are places where the soil

will not compact properly under rolling, these places are corrected by

taking out the material and back filling with new material that will

properly compact under the roller.

The aggregates for the concrete may be distributed along on the

prepared subgrade or may be stored in stock piles or bins at

convenient points. If stored on the subgrade, a traction mixer is

employed which is drawn along the road as the work progresses, the

materials being placed directly in the mixer. If stored at a central

point, they may be transported to the mixer on the road and dumped

directly into the mixer, or the mixer may be set up at the storage

piles and the concrete hauled in trucks to the road where it is

deposited and shaped.

The concrete is spread to the proper thickness and tamped either by

hand or by machinery. If the marginal curb is to be employed, it is

constructed immediately after the concrete for the base has been

finished but before the cement begins to set.

After the foundation concrete has set, the bedding course is spread

and struck off to the proper thickness. When the bedding course

consists of sand-cement mortar, the sand and cement are mixed dry and

spread to prescribed thickness. It is considered to be desirable to

roll the sand bedding course with a light hand roller before the brick

are placed, but the sand-cement bedding course is not rolled. The

bedding course must be carefully shaped by means of a templet or

strike board before the brick are placed.

The brick are laid in straight courses across the pavement, with the

spacing lugs all in the same direction if brick with spacing lugs are

employed, and with the lugs in contact with the brick of adjoining

courses. If brick without spacing lugs are used they are laid loosely

so that there will be room for the filler between the brick of

adjoining courses.

After the brick have been laid they are rolled to bed them in the sand

or sand-mortar bedding course and thus secure a smooth surface. For

this purpose a light, power driven, tandem roller is used and the

rolling is continued until the brick are thoroughly bedded. Any

defective brick that are noted are removed and replaced with good

brick and after this culling has been completed the surface is once

more thoroughly rolled. If a cement-sand bedding course is employed,

the surface is sprinkled just after the final rolling so that water

will flow down between the brick and moisten the bedding course

sufficiently to cause the cement to set. In some cases, the

sand-cement bedding course is sprinkled just before the brick are laid

but in warm weather the setting would take place before the brick

could be rolled if that were done. In cool weather the setting is

sufficiently slow to permit rolling before the bedding course hardens.

The filler is applied to the surface after the rolling. If the

bituminous type of filler is employed, the hot filler is poured onto

the surface and worked into the joints by means of squeegees, with

comparatively little material left on the surface. In some instances

cone-shaped pouring pots are employed and the material is poured

directly into the joints.

The cement grout filler is applied in the same general manner as the

bituminous filler. The grout, consisting of equal parts of sand and

cement, is mixed to a thin consistency and poured onto the surface and

is then worked into the joints with squeegees. Two or more

applications are usually required to effect a complete filling of the

joints. The surface should be covered with sand and be kept moist

until the cement grout has set.