TABLE 16.--PRINCIPAL ITEMS OF EXPENDITURE.

+---------------------------------------------+--------------------+

| | Pesos, |

| | Mexican currency. |

+---------------------------------------------+--------------------+

| ESTANZUELA SUPPLY : | |

| Aqueduct and dam | 502,000 |

| South Reservoir | 429,000 |

| | ------- 931,000 |

| | |

| SAN GERONIMO GRAVITY SUPPLY : | |

| Aqueduct, tunnel, and infiltration gallery | 223,000 |

| Obispado Reservoir | 436,000 |

| | ------- 659,000 |

| | |

| SAN GERONIMO PROVISIONAL SUPPLY , | |

| including boring operations, etc. | 130,000 |

| | |

| CITY WATER DISTRIBUTION SYSTEM | 1,195,700 |

| | |

| CITY SEWER SYSTEM | 1,036,000 |

| | |

| OUTFALL : | |

| Main outfall sewer | 425,000 |

| Sewage purification works | 75,000 |

| | ------- 500,000 |

+---------------------------------------------+--------------------+

| Total 4,451,700 |

+---------------------------------------------+--------------------+

As a general statement, the actual cost of labor is about 33-1/3% of the

total cost of the construction work, including materials. Fig. 20 shows in

graphic form the amount of the labor pay-rolls and the progress of the

work during the whole construction period from 1906 to 1909, inclusive,

comprising also that done under contract.

[Illustration: FIG. 20.--PROGRESS DIAGRAM SHOWING MONTHLY LABOR PAY-ROLLS

DURING THE CONSTRUCTION PERIOD.]

ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911. · 第 40 / 48 题