TABLE 15.--RATES OF WAGES

+-----------------------------------+-------------------+

| | Pesos per day. |

+-----------------------------------+-------------------+

| General foreman | 8.00 to 10.00 |

| Foreman | 6.00 " 8.00 |

| Cabos | 2.00 " 4.00 |

| Masons | 3.00 " 4.00 |

| Bricklayers | 3.00 " 4.00 |

| Masons and bricklayers helpers | 1.50 |

| Cast-iron pipe jointers (foreman) | 4.50 |

| " " caulkers | 3.00 |

| " " helpers | 1.50 to 2.00 |

| Fire-clay pipe layers | 1.75 |

| " " helpers | 1.25 to 1.50 |

| Drillers | 1.25 " 1.50 |

| Carpenters | 2.00 " 2.50 |

| Blacksmiths | 2.50 |

| Crane men | 6.00 |

| Peons (laborers) | 1.00 to 1.25 |

| Boys (watering concrete) | 0.37-1/2 to 0.50 |

| Watchman | 1.00 |

| Timekeepers | 22.00 per week. |

+-----------------------------------+-------------------+

ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911. · 第 38 / 48 题