TABLE 9.--LENGTH OF WATER MAINS.

=========================+=====================+=============

DIAMETER: | |

--------------+----------+ Length, in meters. | Number of

Centimeters. | Inches. | | gate-valves.

--------------+----------+---------------------+-------------

10.2 | 4 | 49,831.68 | 677

15.2 | 6 | 31,918.31 | 306

30.5 | 12 | 14,461.31 | 117

38.1 | 15 | 1,661.98 | 11

45.7 | 18 | 4,522.61 | 5

61.0 | 24 | 2,826.54 | 10

76.2 | 30 | 1,454.40 |

--------------+----------+---------------------+-------------

Totals | 106,676.83 | 1,126

=========================+=====================+=============

The pipes were all cast according to the British Standard Specification,

in 3.65-m. (12-ft.) lengths, and were supplied by Messrs. D. Y. Stewart

and Company, and Messrs. Dick, Kerr and Company, of Kilmarnock and

London. The valves were all of standard design, faced with gun-metal,

and were supplied by Messrs. Glenfield and Kennedy, Limited, of

Kilmarnock, Scotland.

In the distribution system it is proposed to provide 200 fire-hydrants,

by arrangement with the municipality, but only a few of these have been

placed. The general type is a double hydrant for two 63.5-mm.

(2-1/2-in.) streams. These are to be placed at the corner of every block

in the business portion of the city; single-way hydrants will be used in

the residential districts.

_Laying Cast-iron Pipes._--Table 10 has been prepared to show what can

be accomplished with Mexican labor in laying pipes. In this kind of work

the labor was particularly efficient; after the gangs were once drilled

into shape, the work proceeded systematically, and at very good speed.

All the pipes, after being laid, were tested to 150 lb. per sq. in. in

the presence of the Technical Inspector.

Table 11 gives the details of the excavation, the material, and the

average cost, of laying about 106.6 km. of pipes.

_House Connections._--The ordinary house connections, which are of

19-mm. (3/4-in.) galvanized-steel pipe, are connected to the mains by

lead goosenecks and brass corporation cocks. The Company's obligation

under the concession extended to the edge of the sidewalk, and at this

point curb-boxes, chiefly of the Hays pattern, were placed; but,

subsequently, owing to the metering of every house service in the city,

the control of the Company extended to the meter, which, as a rule, is

placed immediately inside of the house. Owing to the rapid deterioration

of the house service pipes in some districts of the northern part of the

city, where the soil is formed of decaying organic matter, it has been

decided to use lead pipe entirely from the main to the meter.

_Damage Due to Floods._--During the night of August 27th, the main

61-cm. pipe, under the river bed of Santa Catarina, at the point where

the main entered the city, was destroyed for a distance of 130 m., due

to the scouring away of a whole block of city property. The Venturi

meter register chart at the South Reservoir showed that the break

occurred a few minutes before midnight. The location of this pipe is

shown by Fig. 5; its broken end was in proximity to an old bridge pier.

Fortunately, at the time of the flood, the Obispado Reservoir works were

completed, and the whole city was supplied with water from San Geronimo

within 48 hours. As only about 1,500 services had then been connected,

this delay was not serious; in fact, in the lower part of the city, the

water in the mains was sufficient until the San Geronimo supply could be

connected. To make a temporary connection to conduct the high-pressure

water to the city, a 15-cm. steel pipe was placed above ground, on the

line of the main, for a distance of 100 m. This pipe was supported by a

cable, 30 mm. in diameter, and by timber trestles. By limiting the

supply district, this pipe was of sufficient capacity to serve until the

large main could be safely restored.

TABLE 10.--COST OF LAYING AND JOINTING CAST-IRON PIPES, EXCLUDING

LOWERING AND TESTING.

+--------------+----------+----------------------------------------+

| | | 76 CM. (30 IN.) |

| | +-------+------------+--------+----------+

| Employees. | Rate for | Total | Total cost | No. of | Cost per |

| | 10-hour | No. | of labor. | pipes | linear |

| | day. | men. | Pesos. | laid. | meter. |

| | Pesos. | | | | Pesos. |

+--------------+----------+-------+------------+--------+----------+

| Foreman | 4.50 | 1 | 4.50 | ... | ... |

| Caulkers | 3.00 | 4 | 12.00 | ... | ... |

| Lead pourers | 2.00 | 2 | 4.00 | ... | ... |

| Lead melter | 1.50 | 1 | 1.50 | 20 | 0.498 |

| Pipe cutter | 2.00 | 1 | 2.00 | ... | ... |

| Peons | 1.00 | 12 | 12.00 | ... | ... |

| Water boy | 0.50 | 1 | 0.50 | ... | ... |

| | | | | | |

| | ... | 22 | 36.50 | ... | ... |

+--------------+----------+-------+------------+--------+----------+

| | | 61 CM. (24 IN.) |

| | +-------+------------+--------+----------+

| Employees. | Rate for | Total | Total cost | No. of | Cost per |

| | 10-hour | No. | of labor. | pipes | linear |

| | day. | men. | Pesos. | laid. | meter. |

| | Pesos. | | | | Pesos. |

+--------------+----------+-------+------------+--------+----------+

| Foreman | 4.50 | 1 | 4.50 | ... | ... |

| Caulkers | 3.00 | 5 | 15.00 | ... | ... |

| Lead pourers | 2.00 | 2 | 4.00 | ... | ... |

| Lead melter | 1.50 | 1 | 1.50 | 25 | 0.410 |

| Pipe cutter | 2.00 | 1 | 2.00 | ... | ... |

| Peons | 1.00 | 10 | 10.00 | ... | ... |

| Water boy | 0.50 | 1 | 0.50 | ... | ... |

| | | | | | |

| | ... | 21 | 37.50 | ... | ... |

+--------------+----------+-------+------------+--------+----------+

| | | 50 CM. (20 IN.) |

| | +-------+------------+--------+----------+

| | Rate for | Total | Total cost | No. of | Cost per |

| Employees. | 10-hour | No. | of labor. | pipes | linear |

| | day. | men. | Pesos. | laid. | meter. |

| | Pesos. | | | | Pesos. |

+--------------+----------+-------+------------+--------+----------+

| Foreman | 4.50 | 1 | 4.50 | ... | ... |

| Caulkers | 3.00 | 4 | 12.00 | ... | ... |

| Lead pourers | 2.00 | 2 | 4.00 | ... | ... |

| Lead melter | 1.50 | 1 | 1.50 | 35 | 0.287 |

| Pipe cutter | 2.00 | 1 | 2.00 | ... | ... |

| Peons | 1.00 | 12 | 12.00 | ... | ... |

| Water boy | 0.50 | 1 | 0.50 | ... | ... |

| | | | | | |

| | | 22 | 36.50 | ... | ... |

+--------------+----------+-------+------------+--------+----------+

| | | 45.7 CM. (18 IN.) |

| | +-------+------------+--------+----------+

| | Rate for | Total | Total cost | No. of | Cost per |

| Employees. | 10-hour | No. | of labor. | pipes | linear |

| | day. | men. | Pesos. | laid. | meter. |

| | Pesos. | | | | Pesos. |

+--------------+----------+-------+------------+--------+----------+

| Foreman | 4.50 | 1 | 4.50 | ... | ... |

| Caulkers | 3.00 | 4 | 12.00 | ... | ... |

| Lead pourers | 2.00 | 2 | 4.00 | ... | ... |

| Lead melter | 1.50 | 1 | 1.50 | 40 | 0.221 |

| Pipe cutter | 2.00 | 1 | 2.00 | ... | ... |

| Peons | 1.00 | 8 | 8.00 | ... | ... |

| Water boy | 0.50 | 1 | 0.50 | ... | ... |

| | | | | | |

| | | 18 | 32.50 | ... | ... |

+--------------+----------+-------+------------+--------+----------+

| | | 38 CM. (15 IN.) |

| | +-------+------------+--------+----------+

| | Rate for | Total | Total cost | No. of | Cost per |

| Employees. | 10-hour | No. | of labor. | pipes | linear |

| | day. | men. | Pesos. | laid. | meter. |

| | Pesos. | | | | Pesos. |

+--------------+----------+-------+------------+--------+----------+

| Foreman | 4.50 | 1 | 4.50 | ... | ... |

| Caulkers | 3.00 | 4 | 12.00 | ... | ... |

| Lead pourers | 2.00 | 2 | 4.00 | ... | ... |

| Lead melter | 1.50 | 1 | 1.50 | 45 | 0.196 |

| Pipe cutter | 2.00 | 1 | 2.00 | ... | ... |

| Peons | 1.00 | 8 | 8.00 | ... | ... |

| Water boy | 0.50 | 1 | 0.50 | ... | ... |

| | | | | | |

| | | 18 | 32.50 | ... | ... |

+--------------+----------+-------+------------+-------------------+

| | | 30.5 CM. (12 IN.) |

| | +-------+------------+--------+----------+

| | Rate for | Total | Total cost | No. of | Cost per |

| Employees. | 10-hour | No. | of labor. | pipes | linear |

| | day. | men. | Pesos. | laid. | meter. |

| | Pesos. | | | | Pesos. |

+--------------+----------+-------+------------+--------+----------+

| Foreman | 4.50 | 1 | 4.50 | ... | ... |

| Caulkers | 3.00 | 4 | 12.00 | ... | ... |

| Lead pourers | 2.00 | 2 | 4.00 | ... | ... |

| Lead melter | 1.50 | 1 | 1.50 | 60 | 0.147 |

| Pipe cutter | 2.00 | 1 | 2.00 | ... | ... |

| Peons | 1.00 | 8 | 8.00 | ... | ... |

| Water boy | 0.50 | 1 | 0.50 | ... | ... |

| | | | | | |

| | | 18 | 32.50 | ... | ... |

+--------------+----------+-------+------------+--------+----------+

| | | 15 CM. (6 IN.) |

| | +-------+------------+--------+----------+

| Employees. | Rate for | Total | Total cost | No. of | Cost per |

| | 10-hour | No. | of labor. | pipes | linear |

| | day. | men. | Pesos. | laid. | meter. |

| | Pesos. | | | | Pesos. |

+--------------+----------+-------+------------+--------+----------+

| Foreman | 4.50 | 1 | 4.50 | ... | ... |

| Caulkers | 3.00 | 4 | 12.00 | ... | ... |

| Lead pourers | 2.00 | 2 | 4.00 | ... | ... |

| Lead melter | 1.50 | 1 | 1.50 | 100 | 0.082 |

| Pipe cutter | 2.00 | 1 | 2.00 | ... | ... |

| Peons | 1.00 | 6 | 6.00 | ... | ... |

| Water boy | 0.50 | 1 | 0.50 | ... | ... |

| | | | | | |

| | | 16 | 30.50 | ... | ... |

+--------------+----------+-------+------------+--------+----------+

| | | 10 CM. (4 IN.) |

| | +-------+------------+--------+----------+

| Employees. | Rate for | Total | Total cost | No. of | Cost per |

| | 10-hour | No. | of labor. | pipes | linear |

| | day. | men. | Pesos. | laid. | meter. |

| | Pesos. | | | | Pesos. |

+--------------+----------+-------+------------+--------+----------+

| Foreman | 4.50 | 1 | 4.50 | ... | ... |

| Caulkers | 3.00 | 4 | 12.00 | ... | ... |

| Lead pourers | 2.00 | 2 | 4.00 | ... | ... |

| Lead melter | 1.50 | 1 | 1.50 | 150 | 0.0574 |

| Pipe cutter | 2.00 | 1 | 2.00 | ... | ... |

| Peons | 1.00 | 6 | 6.00 | ... | ... |

| Water boy | 0.50 | 1 | 0.50 | ... | ... |

| | | | | | |

| | | 16 | 30.50 | ... | ... |

+--------------+----------+-------+------------+--------+----------+

TABLE 11.--CAST-IRON WATER PIPES.--COST

OF MATERIALS AND LAYING AT MONTERREY.

ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911. · 第 28 / 48 题