TABLE 6.--COST OF 55.9-CM. CONCRETE PIPES.

========================================+===============================

| FOR 1,126 PIPES 63.5 CM.

| IN DIAMETER.

Materials. +-------------+-----------------

| Quantities. | Cost.

----------------------------------------+-------------+-----------------

Portland cement, at 8.00 pesos per | |

bbl., delivered at pipe-making yard. | 401 bbl. | 3,208.00 pesos.

Sand, at 2.65 pesos per cu. m. | 85 cu. m.| 225.25 "

Crushed rock, 19-mm. (3/4-in.), at 2.65 | |

pesos per cu. m. | 62 cu. m.| 164.30 "

No. 6 galvanized-wire hoops. 4 rings | |

to each pipe. | 4,504 | 203.00 "

----------------------------------------+-------------+-----------------

Totals. | ... | 3,800.55 pesos.

----------------------------------------+-------------+-----------------

Cost per pipe. | ... | 3.37 pesos.

========================================+=============+=================

========================================+==============================

| FOR 1,095 PIPES 55.9 CM.

| IN DIAMETER.

Materials. +-------------+----------------

| Quantities. | Cost.

----------------------------------------+-------------+----------------

Portland cement, at 8.00 pesos per | |

bbl., delivered at pipe-making yard. | 303 bbl. | 2,424.00 pesos.

Sand, at 2.65 pesos per cu. m. | 68 cu. m.| 180.20 "

Crushed rock, 19-mm. (3/4-in.), at 2.65 | |

pesos per cu. m. | 50 cu. m.| 132.15 "

No. 6 galvanized-wire hoops. 4 rings | |

to each pipe. | 4,380 | 183.00 "

----------------------------------------+-------------+----------------

Totals. | ... | 2,919.45 pesos.

----------------------------------------+-------------+----------------

Cost per pipe. | ... | 2.66 pesos.

========================================+=============+================

_Excavation for Pipe Line and Siphons._--The excavation for the pipe

line and for bridge works, etc., was let by contract to Messrs. Scott

and Lee, of Monterrey, under three classifications:

(1) "All material which in the judgment of the Engineer can

be economically loosened with picks and handled with

shovels."

(2) "Indurated earth or gravel, shale or rock which can be

loosened without blasting, and 'sillar', locally so-called,

whether pure or mixed with other substances, and whether it

requires blasting or not."

(3) "All rock not included in the above which requires

drilling or blasting."

Locally, this classification is well understood, particularly No. 2, as

it covers the sillar soils which are common in the neighborhood of

Monterrey. The contract prices were: No. 1, 50 cents; No. 2, 1.50

pesos; and No. 3, 2.50 pesos per cu. m. These prices were over and above

the clearing and grubbing of the line, which was paid for at the rate of

100 pesos per hectare.

The route of the pipe line being along broken country, at some points

difficult of access, service roadways, about 3 m. wide, for hauling

material were constructed, and, for about 7 km., a roadway was made

along the line of the trench.

The prices for the roadway, under the above classification, were: For

No. 1, 35 cents; No. 2, 1.50 pesos; and No. 3, 2.50 pesos per cu. m.

The trenches were excavated 5 cm. below the required finishing depth, to

allow for grading the pipes in selected material, and were taken out to

an average width of 40 cm. greater than the outside diameter of the

pipe, to allow for their proper jointing, and also to give sufficient

room to roll the pipes in the trenches.

The final quantities of excavation were:

TRENCH: No. 1 11,115 cu. m.

No. 2 18,096 " "

No. 3 6,650 " "

--------------

Total 35,861 cu. m.

ROADWAYS: No. 1 4,165 cu. m.

No. 2 1,999 " "

No. 3 30 " "

-------------

Total 6,194 cu. m.

The route of the pipe line was laid out so as to obtain an average fill

of not more than 1 m. over the tops of the pipes, but in some cases the

cuts, for short lengths, were 3 m. deep. The excavation for this work

began in June, 1907.

_Hauling Pipes._--The pipes were hauled to the site of the work with

ox-carts and mule teams. The cost of hauling varied from 25 cents per

pipe at the lower end, to 1 peso per pipe at the upper and,

comparatively speaking, inaccessible portion of the line. The weight of

each 55.9-cm. pipe was about 182 kg.; that of each 63.5-cm. pipe was

about 216 kg.

The breakages in all the pipes cast at the pipe yard amounted to about

1%, due chiefly to unloading them carelessly near the pipe line.

_Pipe Laying._--The pipe-laying gang was composed of 7 Mexicans under

the direction of an American foreman, who was in charge of several

gangs. One gang could lay daily from 60 to 73 m. (from 100 to 120

pipes). The following was the ordinary pay-roll for one gang:

1 Foreman at 8 pesos (proportion). 2.00 pesos.

1 Pipe layer at 3 pesos. 3.00 "

1 Pipe layer's assistant at 2 pesos. 2.00 "

1 Cement mixer at 2 pesos. 2.00 "

2 Outside plasterers at 2.50 pesos. 5.00 "

2 Inside plasterers at 2.25 pesos. 4.50 "

1 Water boy at 0.50 peso. 0.50 "

-----------

Total. 20.00 pesos.

This brings the average cost of laying the pipes to 32.8 cents per lin.

m.

The pipes were jointed with 1:2 cement mortar, the outer joint being

rounded over both pipes for a width of 12-1/2 cm. (5 in.) and a height

of about 19 mm. (3/4 in.). In making these joints the pipe layers wore

rubber gloves. The joints were kept moist, and the trench was

back-filled with fine, screened material to a depth of 10 cm. above the

top of the pipe. Inside, the joints were carefully caulked with cement

and rendered smooth, the plasterers working continuously along with the

pipe layers, doing from 20 to 35 m. at a time. Water had to be conveyed

to the trenches by barrels on burros, and during the dry season it was

sometimes carried 5 or 6 km.

[Illustration: PLATE IV, FIG. 1.--TYPICAL REINFORCED CONCRETE GIRDER

BRIDGE, ESTANZUELA AQUEDUCT.]

[Illustration: PLATE IV, FIG. 2.--ELLIPTICAL ARCH BRIDGE CARRYING

ESTANZUELA AQUEDUCT.]

_Bridges._--The line as laid out passed over many gulches and dry

arroyos, and these were crossed with reinforced concrete bridges of

varying spans and heights, two being shown on Plate IV.

These bridges were formed of continuous horizontal girders, 1.10 m. deep

and 1 m. wide, with a cantilever overhang at the abutments, varying in

length from 1 to 2 m., so as to avoid settlement between the pipes and

the bridges. The bottom reinforcement consisted of from 2 to 6 twisted

bars of mild steel, varying in different spans from 12.7 to 19 mm. (1/2

to 3/4 in.) in diameter. The turned up bars were 28-1/2 mm. (1-1/8 in.)

in diameter; they were placed on either side, carried over the upper

part of the beams, and continued along the end for the overhanging part

of the girder. These bars, when not obtainable of the full length, were

spliced with a lap of 1.2 m. with No. 6 galvanized-steel wire. The

vertical stirrups were 4.7 by 25.4 mm. (3/16 by 1 in.), of mild steel;

they were equally spaced 30.5 cm. (12 in.) apart, and carried all around

the girders, lapping at the center about 15 cm. (6 in.), all the steel

being carefully wired together before placing the concrete.

The general type of the piers and abutments is shown by Fig. 1, Plate

IV, and varies in height with practically every bridge, the foundations

in every case resting on hard rock. The concrete for the girders was a

1:2-1/2:3-1/2 mixture, the crushed stone used having all passed a mesh

of 19 mm. (3/4 in.). The piers were of 1:3-1/2:5-1/2 concrete, and heavy

"displacers" were embedded within them.

The concrete was placed after the pipes had been laid through the form

by the pipe contractor, the joints being kept clear of the bottom to the

required distance by small moulded concrete blocks. The tops of the

girders were moulded to a slightly segmental form. The bridges were all

kept watered for about 15 days, and the forms were not struck for 28

days after placing. At Station 13.4 the pipes were carried over a

picturesque arroyo on an elliptical arched bridge (Fig. 2, Plate IV) of

11 m. clear span.

The abutments of all bridges were protected by rubble walls in cement

mortar carried up 60 cm. above the tops of the girders.

The contract price for the concrete work of these bridges, the Company

furnishing the steel and cement, was 14 pesos per cu. m., and for

placing reinforcing steel 35 pesos per metric ton (2,204 lb.).

There are 49 single-span bridges, the larger spans being 9.10 m.; 8

two-span, and 11 three-span bridges, their total length, including the

overhang, amounting to 870.50 m., or 4-1/2% of the whole length of

aqueduct.

_Concrete Aprons._--At 76 points there were small depressions which did

not necessitate the construction of bridges, and at these places the

pipes were encased in blocks of concrete carried up the hillside in the

form of an apron having small abutment walls from 1 to 2 m. apart. This

also served to protect the pipes from scouring action during rainstorms.

At the upper end of the line, near the intake, the pipe had to be

protected by concrete continuously for a distance of about 300 m., in

order to prevent damage from falling rocks.

[Illustration: PLATE V, FIG. 1.--VENTILATING COLUMN AND ENTRANCE

MANHOLE, ESTANZUELA AQUEDUCT.]

_Ventilators and Manholes._--Along the route of the concrete pipe there

are 27 ventilators, one of which, together with an entrance manhole, is

shown by Fig. 1, Plate V. They consisted of simple concrete columns,

3.35 m. high, above the ground line, the interior of the shafts being

formed of fire-clay pipes, 15 cm. (6 in.) in diameter. At each

ventilator the pipe was cut and a block of concrete, the width of the

trench, filled in as a foundation. Entrance manholes were also placed at

49 points, at 27 of which they immediately adjoined the ventilating

columns.

_Estanzuela Tunnel._--At 1,560 m. from the intake at Estanzuela, the

conduit is laid through a tunnel 281 m. long. The tunnel was driven

through hard calcareous strata from the open cuttings at each end. The

inner dimensions were trimmed to approximately 2 m. high and 1-1/2 m.

wide. At the ends of the tunnel the rock was moderately easy to take

out, but the inner section was very hard and difficult to blast.

Ordinary hand drilling was adopted, and the actual cost of driving

varied from 28 pesos per lin. m. at the ends to 50 pesos in the center.

The pipes were laid through the tunnel in the ordinary way, and

back-filled from the center, so as to give a cover of about 45 cm. above

to protect them from falling pieces of shale.

[Illustration: PLATE V, FIG. 2.--PLACING CONCRETE PIPES IN FORMS FOR

BRIDGE CROSSING AT NORTH END OF TUNNEL, ESTANZUELA AQUEDUCT.]

_Siphons._--It has already been mentioned that there are 6 cast-iron

pipe siphons. The head on these varies between 10 and 38 m. All are

provided with special inlets and outlets, forming combined overflow and

ventilating chambers, and have wooden hand-sluices to divert the water

when necessary. The bottoms of all siphons are provided with 20-cm.

cast-iron scour-out pipes, fitted with valves, and carried down to a

lower point to obtain a free outlet. The valve-boxes are protected by

being placed in heavy concrete chambers carried up above the level of

ordinary floods.

The siphons are formed of cast-iron socket pipes, 3.65 m. (12 ft.) long,

caulked in the ordinary way with lead joints. The thickness of the

45.7-cm. (18-in.) pipes is 19 mm.; that of the 50.8-cm. pipes is 21 mm.

On the steep hillsides the pipes are anchored securely to the rock in

concrete blocks reinforced with heavy iron chains. In some cases these

siphons were difficult of access, but ox-teams hauled the pipes in a

very efficient and satisfactory manner.

_Overflow Chambers._--The ordinary overflows, of which there are 14, are

similar in design to the siphon inlets.

_Testing, etc._--When the line was completed it was tested for

water-tightness, and the loss was found to be about 5%, part of which

was probably due to absorption. At a later date it was found that the

waters of the Estanzuela River, which contain 150 parts of calcium

carbonate (CaCO_{3}) per million, deposited a very fine film of lime on the

interior of the pipes, completely filling any pores there might have

been. At the present time there is no measurable leakage, thus proving

that the character of the work is very satisfactory.

The water was turned into the conduit on June 11th, 1908, and delivered

to the city on the following day through a by-pass, before the reservoir

was completed.

The pipe line is patrolled daily by an inspector with the authority of a

gendarme, so as to prevent the unlawful abstraction of water, a very

necessary precaution in so dry a country.

ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911. · 第 20 / 48 题