CHAPTER IX

REBUILDING A RAILROAD

RECONSTRUCTION NECESSARY IN MANY CASES--OLD GRADES TOO HEAVY--CURVES

STRAIGHTENED--TUNNELS AVOIDED--THESE IMPROVEMENTS REQUIRED ESPECIALLY

BY FREIGHT LINES.

To the operating heads of the great railroad systems, rebuilding a line is

to-day a far more important problem than the building of new routes. The

country has grown--grown in wealth, among other things. The causes that

demanded the very greatest economy in the building of early railroad lines

no longer exist. The hill that the early engineer carefully rounded with

his line is now pierced without a second thought. Grades that were once

deemed slight are now classed as impossible. The almost infinite

development in the operation of the railroad has seen the grade or the

curve, not as a slight matter, but as a matter which, however slight in a

single instance, becomes in the course of constant operation a heavy

operating expense. To-day the operating folk of the big railroads are

counting the pennies where they countlessly multiply in these fashions; it

is one of the greatest factors in the grinding operation competition

between the great railroad systems of the country.

It is all quite as it should be. The early builders did the best that they

might do with the opportunities that were theirs. They got the railroad

through. It developed wealth for itself, as well as for the territory it

served; and with that wealth it is enabled in these piping days of peace

and plenty to correct the alignment errors of the early builders.

Moreover, there are frequent cases where the steady increase of traffic

has rendered it necessary for a railroad to parallel its trunks with new

lines, quite aside from the consideration of grade and curve.

As far back as the early fifties this great work of rebuilding the

trunk-line railroads was begun. Certain serious errors in the original

alignment of the Baltimore & Ohio Railroad between Baltimore and the

Potomac River were corrected, even though at a considerable expense. As

time went on, other railroads continued this correction work. It is still

being prosecuted east and west of the Mississippi. Ten million dollars,

fifty million dollars, looks like a lot of money to the stockholders of

any company, when their president tells them that this is to be the cost

of this new relief line, this reconstruction, that cut-off; but what is

$1,000,000 when it is going to save more than $100,000 a year in the

operation of your railroad? It is the big sight of the big situation that

the railroads make nowadays at this reconstruction work.

Mr. Harriman, with his transcontinentals from the Mississippi watersheds

west, was almost the pioneer in this work of wholesale reconstruction. The

wholesale operating benefits that have resulted from it in the case of his

group of Pacifics have been largely responsible for his preëminence in the

railroad world. And yet, once his method was tried, it all seemed simpler

than A, B, C.

Take the case of the Lucin cut-off on his Southern Pacific. When the Union

Pacific was being pushed across the plains and threaded over the Rockies

and the Sierras, the Great Salt Lake of Utah lay directly in its path. The

railroad did the obvious thing and carefully made a detour around the

lake. When Mr. Harriman took over the Union Pacific, then in a state of

physical decadence, and linked it with his Southern Pacific, and surveyed

the situation carefully, he decreed that the Great Salt Lake should no

longer cause a trunk-line railroad to double in its path. He caused a line

to be surveyed direct across the marshy lake from Ogden to Lucin and when

that was done he had a line--on paper--103 miles long as against 147

miles by the old line. The engineer hesitated, but Harriman urged and they

courageously began the construction of miles and miles of embankment and

of trestle. Then new difficulties arose. Sink-holes developed. In a few

minutes structures that had been the work of long months silently

disappeared. The engineers in charge came to Harriman.

"It is not possible," they told him.

"You must carry it through whether it is possible or not," Harriman

replied.

Eventually they carried it through.

* * * * *

When it was done, the Union Pacific had not only shortened its

transcontinental line 44 miles, but it had eliminated more than 1,500 feet

of heavy grade and 3,919 degrees of curvature. An operating economy of

between $900,000 and $1,000,000 a year had been effected and the

stockholders of the company had a good investment for the $10,000,000 that

the Lucin cut-off had cost them.

Nor was that all on the Union Pacific. On other sections of its main line

similar reconstruction work has added to the economy of operation by

millions of dollars each year. For twenty miles west from Omaha, where the

old historic transcontinental formerly dipped south to avoid a series of

undulating hills, the new Lane cut-off cuts squarely across them--20 miles

of deep cuts and heavy fills--"heavy railroad," as the engineers like to

put it. And again, where the old line twisted and wound itself over the

Black Hills, and wobbled unsteadily through Wyoming, the reconstruction

engineers pressed their work.

[Illustration: WHERE HARRIMAN STRETCHED THE SOUTHERN PACIFIC IN A STRAIGHT

LINE ACROSS THE GREAT SALT LAKE]

[Illustration: LINE REVISION ON THE NEW YORK CENTRAL--TUNNELLING THROUGH

THE BASES OF THESE JUTTING PEAKS ALONG THE HUDSON RIVER DOES AWAY WITH

SHARP AND DANGEROUS CURVES]

[Illustration: IMPRESSIVE GRADE REVISION ON THE UNION PACIFIC IN THE BLACK

HILLS OF WYOMING. THE DISCARDED LINE MAY BE SEEN AT THE RIGHT]

It is not generally understood that the summit of the Union Pacific is in

the Black Hills, which are the first foothill range of the Rockies, rather

than in the mountain crest beyond. The Black Hills have always been a

baffling proposition, with their short, steep slopes. The engineers

wrinkled their brows at the thought of correcting the old line through

there, but Harriman simply said that they must, that the board--which

meant E. H. Harriman himself--had directed that 247 feet be cut from the

road's crest there; and 247 feet, almost to the inch, was cut. It took

giant fills and embankments and an army of men but the grades were brought

to a minimum for a Rocky Mountain stretch. Wooden trestles, old and

affording a constant fire-risk, were swallowed up in embankments; a single

slice through a hill-top, a quarter of a mile long and eighty feet deep,

did its part in reducing the grades; antiquated cars disappeared before

equipment of the modern class; dilapidated shanties were supplanted by

fine, permanent railroad stations. The new Union Pacific is a monument to

the reconstruction engineer--and to E. H. Harriman.

The Canadian Pacific Railway, while traversing but one small northeastern

corner of the United States, is essentially an American railroad, both in

equipment and in operation. It forms an important half of that all-British

Red Line encircling the globe, of which any Englishman is so very proud.

When the Canadian Pacific Railway was completing its last link in this

unbroken line of rails from St. John, N. B., and Montreal, to Vancouver,

the question of grades was indeed a secondary one. The vital thing was to

cut the line through, and to that end great sacrifices of grade efficiency

were made. So that when the line was through, and the first Imperial

Limited was making its way from the Atlantic to the Pacific over a single

railroad system, it was indeed a line with structural defects. At one

point--the famous Big Hill, near Field, Alta.--in order to overcome the

steep Rocky Mountain climbs, it was necessary to use from four to six

engines for comparatively light freight and passenger trains. And at that,

it was difficult to attain a speed of more than four or five miles an

hour.

Within the last three years, this fearful grade has been corrected by the

very first spiral tunnels ever built upon the American continent. Spiral

tunnel construction of this kind is not new. It has been used with

remarkable success by the railroads of Continental Europe, in piercing the

High-Alpine boundaries between France, Germany, Austria, and Italy.

Coming from the east on the Canadian Pacific Railway, the train first

enters the spiral tunnel--they call it the "corkscrew" out in

Alberta--under Cathedral Mountain. This first bore is some 3,200 feet in

length. Emerging from it, the train runs back east across the Kicking

Horse River, then enters the eastern spiral tunnel, and after describing

an elliptic curve, emerges, and again crosses the Kicking Horse westward.

This whole thing is a perfect maze--the railroad doubling back upon itself

twice, tunnelling under two mountains, and crossing the river twice in

order to cut down the grade. The work cost $1,500,000. The mere cost of

the explosives came to over $250,000. It was one of the really great

tunnel jobs of the world. Yet despite the complicated work caused by the

spiral shape of the tunnels, they met exactly. The worth of the thing to

the Canadian Pacific is shown in the fact that those same trains that

formerly required four to six engines, are now handled easily over this

Big-Hill grade with but two engines, and at a speed of about twenty-five

miles an hour.

Other railroads by the dozen, whose lines traverse mountainous or even

hilly country, are engaged in this proposition of lowering their grades.

F. D. Underwood, president of the Erie, and known as one of the ablest

operating heads in this country, has been engaged in cutting off some of

the heavy hill-climbs on that old-time route from the seaboard to the

lakes. Underwood has already seen Erie's hopes of success in developing

the property as essentially a freighter and for the immediate improvement

of that portion of its facilities he has built three new relief lines, a

small stretch near Chautauqua Lake in western New York, and then through

the upper Genesee Valley, the third and most important eastward from a

point near Port Jervis and piercing the summit of the Shawangunk

Mountains.

The line through the Genesee Valley extends from Hunts, on the Buffalo

division, about 20 miles west of Hornell, to Hinsdale on the main line,

and is 33 miles long. It cuts off a heavy grade between Hornell and

Hinsdale on the main line--a little over one per cent--for both east-bound

and west-bound freight. At that particular point, Erie's west-bound

freight approximates 75 per cent of the east-bound, and so the new line

recognizes that fact by establishing the west-bound maximum grade at 3-10

of one per cent, as against a maximum of 2-10 of one per cent in the other

direction. Brought to a plain understanding, a single locomotive has no

difficulty in handling 80 cars, each bearing 40 tons of coal, over this

new low-grade line. To take one-half that load over the old main line

required a pusher.

On the east end of the line, where Erie's engineers built their greatest

low-grade cut-off, the coal rolls down to the seaboard in such quantities

as to make the west-bound tonnage only a quarter of the east-bound; so the

reconstruction engineers were satisfied with a maximum west-bound grade at

6-10 of one per cent as against the maximum of 2-10 east-bound, in the

direction of the heavy traffic. The cut-off, which is double-tracked and

is 42-1/2 miles long, increases the distance from New York to Chicago 8

miles; but this is not an essential fact, for, like the Genesee Valley

Road it is built exclusively for freight service, and not only almost

triples the hauling capacity of a locomotive but actually permits of

faster running time for the freight trains between Jersey City and Port

Jervis. To build the cut-off required a really great expenditure, for like

all these new lines it was "heavy work," embracing a tunnel nearly a mile

long under the crest of the Shawangunk Ridge, and a steel trestle over the

Moodna Valley, 3,200 feet in length and 190 feet high. Still President

Underwood can contemplate his locomotives hauling three times their old

loads over it. The economy of such a proposition becomes apparent upon the

face of it.

The Baltimore & Ohio, the Southern, and the Norfolk & Western have

recently lowered their grades and straightened their curves in similar

fashion; the Lehigh Valley, by the erection of a great new bridge at

Towanda, Pa., has taken a bad link out of its main line; the Chicago &

Alton, when the engineers told it that it must abandon miles upon miles of

its main line (for long years its pride) and build anew, told those

engineers to go ahead. Stretch by stretch the old road was revamped to

meet in every way modern conditions. A steel bridge across the Missouri,

which was the first steel bridge built in America, and which cost

$500,000, was sent to the scrap-heap while the old-timers groaned. "That

which yesterday was a railroad marvel becomes a curiosity to-morrow,"

observes Frank H. Spearman, in speaking of this very thing.

The rebuilding of the Chicago & Alton was a clean-cut affair. The 70-pound

rails were torn from the main line and sent to sidings and branch lines in

favor of the 80-pound rails; for while men were tearing at the tracks, the

shops were working overtime; 55-ton freight engines that could haul 30

cars were to give way to 165-ton motive power, capable of picking up and

carrying a hundred cars with ease. That was why the old bridge had to go

in favor of one which cost an even million dollars. And when the Alton

built heavy new bridges at dozens of other points besides the Missouri, it

built them after the new fashion, with solid rock ballast floor, affording

additional comfort and safety to its patrons.

In a flat State like Illinois there were no very serious grade defects to

be corrected, but through the gentle undulations of rolling country the

line twisted and turned like a lazy brook. The rebuilders stopped that.

When they were done there was a single section of 40 miles, straight as

the arrow flies, and many tangents of from 15 to 29 miles. In some cases

when the trains were transferred to the completed line, the old, spindly,

wobbly affair could be seen for miles in roadbed, to the one side or the

other of the new. In some cases, this abandoned right-of-way was sold to

interurban electric railroads; in one particular case one of the abandoned

bridges was included in the sale.

* * * * *

The Delaware, Lackawanna, & Western is one of the old time Eastern Roads

that have waxed immensely prosperous with the years. Originally built as

an anthracite coal carrier from the Eastern Pennsylvania Mountains to the

seaboard, it has developed into a through freight and passenger carrier of

importance. The old-time engineer knew how to plan good railroads; the

Pennsylvania to-day is building its new low-grade freight line on the very

surveys made by its pioneer surveyors three-quarters of a century ago;

but, as we have already intimated, those railroads were financially weak.

Early annual reports of the Pennsylvania tell how its stock was peddled in

Philadelphia from house to house--up one street and down another--and how

sometimes two houses joined together to buy a single share. Money was not

plentiful in the middle of the last century.

So the Lackawanna engineers were compelled to build their road in

semi-mountainous districts, along the lines of least resistance, rather

than by the most direct routes. As it came east from Scranton over the

Pocono Mountains it found its way in a roundabout course to the middle of

Northern New Jersey. The road wound south and then wound north again, its

grades were steep, some of its curves were short, and it dipped through

two tunnels--one at Oxford Furnace, the other at Manunka Chunk.

To iron out those time-taking dips, the sharp curves, the grades, and the

tunnel, the Lackawanna cut-off--the "heaviest" bit of railroad in the

world--was begun three years ago. A new route 28-1/2 miles long was

surveyed diagonally across from Port Morris on the main line in New Jersey

to the main line again at the Delaware Water Gap. Despite the fact that it

must cross the watersheds diagonally--the watersheds formed by deep

valleys and high rocky ridges--the line as surveyed and built is only

three miles longer than an absolute air-line. It shortens the Lackawanna's

main stem from New York to Buffalo--already the shortest route between

these two cities--by 15 miles, and brings that busy lake port a trifle

within 400 miles from the seaboard.

To cross those watersheds at a sharp diagonal meant "heavy work"; and the

engineers, to run their straight-cut, low-grade line, found that they

would have to make tremendous cuts and fills--these last alone totalling

14,600,00 cubic yards. The Lackawanna's engineers will give you a faint

idea of the stupendous size of these embankments. To build them up of

stone and earth at the rate of a cartload a minute for each working-day of

the year would require 81 years for the job. To do it in less than three

years has meant the employment of whole trains of dump-cars, the purchase

of 600-acre farms for single borrow-pits, the energy and administration of

real engineers.

There have been cuts through solid rock, 65 bridges and culverts to be

wrought of concrete, a single embankment (at the Pequest River) three

miles in length, 110 feet high, and 300 feet wide at its base. The

traveller who rides over the completed double-track road will have but a

faint idea of the human labor and the human energy that have gone to

construct it.

* * * * *

The great railroad that traverses the State of Pennsylvania is another

monument to the engineer. The Pennsylvania Railroad was no wobbly affair

at any time. Its grades and curves, considering the character of the

country through which its trunk rests, are not excessive. It has been a

good standard railroad for a good many years past. But in 1902, the

Pennsylvania found that its troubles rested in the volume of traffic that

was being offered it. Over its middle division from Harrisburg to

Pittsburgh it was handling as much tonnage as J. J. Hill's entire Great

Northern system. The heavy tonnage business began to clog the road's fast

passenger traffic (its especial pride) and the fast freight traffic (the

mainstay of its shippers), and appeal was made to the reconstruction

engineers.

It was no slight appeal at that. Pittsburgh, handling 400,000 freight cars

a month, was clogged, congested with such streams as had never before

tried to crowd through that narrow neck of the Pennsylvania's bottle and

the orders that went forth for relief were emphatic. Vice-presidents,

general managers, superintendents and general superintendents, and

engineers of every sort crowded into the president's office in Broad

Street Station, and out of that conference the plans for an exclusively

low-grade freight line from New York to Pittsburgh and for the traffic

relief of Pittsburgh itself were born.

Every large city has become, in a sense, a bottle-neck for the important

railroads that pierce it. In some cases like Chicago or St. Louis or

Kansas City or Indianapolis, the situation has been solved by the creation

of belt-line freight railroads partly or entirely encircling the town. At

Buffalo, the New York Central lines have built a connecting line to enable

through traffic to escape the congestion of city yards and terminals,

while at New Haven, the road of the same name has recently spent several

million dollars in enlarging its narrow throat in the middle of the town.

But nowhere else did the situation approach that at Pittsburgh. Through

the Pennsylvania's passenger station there poured not only an abnormally

heavy passenger traffic, owing to a heavy suburban service, but every

pound of freight bound between the parent company and its two great

subsidiaries, the Panhandle and the Fort Wayne. There were further

complications right at the station, owing to the proximity of two of the

very worst grade-crossings in America, where Penn and Liberty Avenues

swept their busy tides of city traffic all day long over the Fort Wayne's

main line tracks. It was a problem that called for the best in engineering

skill--and received it.

The Pennsylvania dug deep into its pocket-book and solved the problem

magnificently. It began by going back to the vicinity of its great

Pitcairn freight-yards at the east of the city, and from them building two

connecting laterals (the one to the south and across the Monongahela River

to connect with the Panhandle tracks, the other to the north--known as the

Brilliant cut-off) across the Alleghany and connecting with the tracks of

the West Penn Railroad, which in turn connected with those of the Fort

Wayne in the one-time city of Allegheny. That sounds simple, but it was in

reality a fearfully expensive undertaking. The mile of Brilliant cut-off,

"heavy work" every inch of it, cost $5,500,000, and is to-day the most

expensive mile of railroad track in the world.

But the gripping hand was off the traffic throat of Pittsburgh and

commercial Pittsburgh breathed more easily once again. The Union Station

and its approach tracks were restored to passenger uses; and in the course

of things the Pennsylvania tore down the old station, built a new one, and

wiped out the two wicked city crossings, as with the stroke of an

Aladdin's hand.

So much for Pittsburgh. Now consider the great new freight line leading to

the east from there. Not all of that railroad has yet been built, but the

greater part of it is already completed, and every part of the old road

that was under tension because of freight congestion has already been

relieved.

To build this new double-track railroad across 350 miles of a mountainous

State, the engineers studied two points--grade and curvature. Distance

was no object, for speed is the very last attainment of heavy tonnage

movement. The new route consisted in part of the enlargement of the old

routes, and in part of the construction of brand new line. It started east

from Pittsburgh, where the great Brilliant cut-off had been built to

relieve the tremendous terminal freight congestion, and followed up the

valley of the Alleghany River on the route of the West Penn Road, a

Pennsylvania property. The main line of the Pennsylvania comes east from

Pittsburgh up the valley of the Monongahela for a distance, and then

across country to Blairsville Intersection, 50 miles east of Pittsburgh,

where it is intercepted by the low-grade freight route.

From Blairsville to Gallitzin, the road winds through the narrow and

forbidding Conemaugh Valley most of the way. It twists itself through the

slender defile of Packsaddle. A dozen years ago or more, when the

Pennsylvania's engineers were ordered to four-track the original

double-track through that narrow defile in God's great world, they shook

their heads dubiously; then--after the fashion of engineers--they went

ahead and did it. When the order came for two more tracks in the same

narrow pass, they placed them there, although they had literally to blast

out a shelf on the side of the fearfully steep mountainsides for the

low-grade line.

Just beyond Gallitzin, where the Pennsylvania pierces with two great

tunnels the very summit of the Alleghanies, the low-grade line takes its

own course once more, breaking farther and farther away from the main

line, and for long sections following the trail of the long-since

abandoned Portage Railroad. The day is coming when Gallitzin Tunnels are

to be left high in the air. The Pennsylvania's officers tell you that

frankly.

"We have plans for a six-mile tunnel, to be handled by electric

motive-power already made," said one of them, just the other day, "and

every year we wait, that tunnel grows longer, the approaching grades less

and less. It will cost money--money into millions of dollars--and it will

earn 10 per cent on the investment."

From Gallitzin, the low-grade line delves far south to Hollidaysburgh and

then follows the tracks of a former branch line up to Petersburg on the

main line, which it parallels to the Susquehanna. Where the main line

crosses the Susquehanna at Rockville, the low-grade freight route diverges

once again and follows the west bank of the river for a number of miles,

completely avoiding in that way Harrisburg and the steel-making towns to

the south of it with all of their conditions of congestion. The freight

route crosses the broad Susquehanna at Shock's Mills, eight miles north of

Columbia, and follows the east bank of the river for twenty miles to

Shenks Ferry, where it turns abruptly eastward through the rugged hills of

Lancaster County to a connection with the main line at Parkesburg. From

thence it follows the main line nearly all the way to Glen Loch, crossing

and re-crossing it but at all times retaining its nominal grades. At Glen

Loch it makes a wide detour around Philadelphia and its suburbs and

reaches with a long straight "short cut" over to the main line at

Morrisville near Trenton.

So much for the location of this great line of reconstruction. In grades

and in curvatures it has achieved real triumphs. The great tonnage here is

also always east-bound--coal and iron coming to the seaboard. Its grades

also are chiefly consequential then to the east-bound movement. To that

movement the heavy grades are again at the almost incredible figure of

3-10 of one per cent--some seventeen feet to the mile. That will mean more

when it is understood that that figure is equal to the pull that is

required of an engine to start a heavy freight train upon an absolutely

level track. With such a pull, grades become as nothing, and the

Pennsylvania's operating department is enabled to run 75 trains an hour

over this low-grade line; hour after hour upon a 15 minutes' interval.

Ask a Pennsylvania officer what he would do with such traffic on his old

main line to-day, and he will tell you that he would rather resign than

tackle the proposition. The same thing is true on the New York Central

lines. Like the Pennsylvania, that railroad thought a little time ago that

with its four tracks it might move all civilization. Its acquisition of

the bankrupt West Shore Railroad in the eighties gave it two extra tracks

across New York State that for a long time were carried on the company's

books as deadwood. Now they are filled with freight operation and bringing

in a healthy return to their owners. The growing land is always catching

up to its new railroad facilities, no matter how rapidly they may be

constructed.

To-morrow?

The railroad operator does not like to think of that. He meets to-day and

he plans as best he may against that to-morrow. To meet the great unknown

he bids the engineers--those who construct and those who reconstruct--to

him, and begs that they exercise their best wits to help him to see a

little way into the dim and shadowy future.

The Modern Railroad · 第 9 / 27 章