SECTION III.--PLOTTING.

The transference of the measurements determined by the survey from the

field-book to the paper is termed _plotting_. The operations of plotting

are very simple, and the ability to perform them properly may be

acquired with a little practice. But their due performance demands the

same extreme care and attention as that of the operations in the field,

for it is obvious that the precautions taken to ensure accuracy in the

latter may be rendered nugatory by inaccurate plotting. The angular

instrument used in plotting is the protractor, and to ensure correct

results this instrument must be accurately divided. When, however, the

survey has been made without the aid of an angular instrument, the

protractor is not required in laying down the results. In such a case,

which frequently occurs in surveys of small extent, the lines, having

all been chained and registered in the field-book, are laid down

directly from the scale by means of an ordinary straight-edge and a pair

of compasses. The several methods of plotting and the various operations

involved have now to be considered.

_Reference Lines and Points._--The lines chained over in a survey and

recorded in the field-book are not usually the actual lines existing on

the ground, but imaginary straight lines chosen for the purpose of

referring other lines and points to them. They are, therefore,

appropriately termed _reference lines_, and all points situate in them

to which other lines are referred, in other words, all points in a

reference line in which other reference lines intersect it, are termed

_reference points_. Reference lines are generally made to form triangles

for facility of computation, and these triangles enclose the area to be

surveyed. But to determine the details included within them, it is

necessary to form other and smaller triangles within the larger ones

first laid down. The latter are, therefore, distinguished as Primary and

the former as Secondary triangles, and the lines of which they are

composed are called primary and secondary reference lines.

_Plotted Points._--In laying down a line of definite length upon paper,

the positions of its extremities are determined and marked by pencil

dots; such dots, or rather the points indicated by such dots, are termed

_plotted points_. The line is drawn by joining the plotted points.

_To Plot Reference Lines and Points._--To plot a reference line of a

given length when the position of neither of its extremities is given, a

light dot must be made upon the paper in a convenient part to indicate

the position of one extremity. The pencil-point mark should be as light

and well defined as possible, and hence it is essential that the pencil

used should be hard, and always kept pared to a fine conical point. The

scale must then be applied, in the direction of the line to be drawn,

with its zero point coincident with the plotted point. The scale should

be lightly but firmly held in this position with the left hand. The

distance of the other extremity of the line must then be found upon the

scale, and the eye placed directly over the line of the graduation; this

is necessary to the correct placing of the point, and it is well to

train the eye to trace accurately the prolongation of the line of

graduation upon the paper. A dot must be placed in the prolongation of

this line and close to the edge of the scale, to mark the position of

the other extremity. The reference line is then to be drawn between

these two plotted points with a sharp chisel-pointed pencil. Reference

lines, like reference points, should be well defined, but drawn as fine

and light as possible. The degree of fineness and lightness should be

such that when the detail is finely but firmly outlined, the reference

lines and points may not be visible, except on a close inspection of the

surface.

To plot secondary reference lines, as, for example, a number of offset

lines, apply the scale so that its edge may be parallel to and almost

over the pencil trace of the primary line and its zero point coincident

with the point at which the line begins. Care must always be taken to

place the zero of the scale at the beginning of the line, and not at the

end of it. At the distances recorded in the field-book as those at which

the offsets were taken, plot upon the line, in the manner described

above, the points indicating the extremities of the offset lines. All

other points, such as stations and intersection of fences, roads, and

streams, should be plotted at the same time. Around all stations, a

light, hand-drawn circle should be placed, and intersections marked by

small cross lines. This being done, place the offset scale so that the

zero may coincide with the plotted point in the reference line and the

edge be perpendicular to the line. To bring the edge into this position,

the end of the scale should be placed parallel to the reference line;

this is, of course, assuming the scale to be perfectly rectangular, as

it ought to be. The other extremities of the lines may then be plotted

in the same manner as those of the primary lines.

To illustrate the foregoing remarks, let it be required to plot the

following portion of a field-book.

+------+

{| 00 | 1346 | or 000 Line 1.

{| 75 | 1170 |

{| 96 | 1000 |

{| 105 | 650 |

{| 66 | 400 |

{| 00 | 000 |

+------+

Line 3. From | 1946 | last.

+------+

| ↰ |

+------+

| 1946 | 00 |}

| 1420 | 88 |}

| 1200 | 144 |}

| 1000 | 110 |}

| 600 | 75 |}

| 520 | 50 |}

| 000 | 00 |}

+------+

Line 2. From | 2504 | last.

+------+

| ↙↑ |

+------+

| 2504 | 00 |}

| 2000 | 65 |}

| 1790 | 95 |}

| 1610 | 115 |}

| 1440 | 87 |}

| 1220 | 110 |}

| 1000 | |}

| 850 | 28 |}

| 420 | 100 |}

Line 1. | 000 | 00 or 1346

| | Line 3.

+------+

Begin at south corner and range N.

Having laid down in a convenient part of the paper the beginning of Line

1, place the edge of the scale so that the zero may coincide with the

plotted point and the edge be parallel to one of the meridians. Holding

the scale firmly in this position, plot the distance 2504 links, and

join the plotted points. Then, without removing the scale, plot upon

this reference line the distances at which the secondary or offset lines

were taken, that is at 420, 850, 1220, 1440, 1610, 1790, and 2000 links.

In this case we have nothing but offsets; had there been stations or

intersections of fences, roads, or streams, these would have had to be

plotted at the same time, and distinguished by an appropriate mark. Line

2 begins at the end of Line 1, and returns on the left at an acute

angle, as indicated by the arrow in the field-book. But as the magnitude

of this angle is not known, the survey having been taken with the chain

alone, the exact direction of Line 2 must be ascertained in the

following manner. Take the length of the line in the compasses, and with

this distance as a radius, strike an arc from the end of Line 1. Also

with the length of Line 3 as a radius, strike an arc from the beginning

of Line 1, at which point Line 3 closes, intersecting the former. The

point of intersection will be the end of Line 2. Join this point to the

end of Line 1, and plot the offset reference points upon this line in

the manner already described for Line 1. Line 3 begins at the end of

Line 2, and terminates at the beginning of Line 1; hence both

extremities being determined, we have only to join these points, and to

plot the offset reference points as before. Had a split line been taken

for the sake of accuracy from the angle A C B to the base Line 1, the

intersection of this line should have been plotted upon Line 1, and the

position of the end of Line 2 found by striking an arc from this point

also with a radius equal to the length of the split line. If the

distances have been correctly measured in the field and correctly taken

from the scale, the three arcs will intersect at the same point. If they

do not so intersect, the error must be noted in an error-sheet, and

corrected in the field before proceeding further. It may be remarked

here that on account of the irregularities of the surface chained over,

all measured lines are liable to be recorded a little too long. One link

in ten chains may be allowed for this source of error. Assuming,

however, that the primary reference lines “close” properly, the offset

lines may be plotted in the manner already described, and the detail or

boundary lines drawn in, which in the present instance are hedges. Fig.

82 shows the survey as laid down in the foregoing notes.

When the survey has been made with the aid of an angular instrument, the

method of plotting the primary reference lines differs somewhat from the

foregoing. In this case, the paper should be first covered with a number

of parallel straight lines ruled about an inch and a half apart to

represent magnetic meridians. The first station may then be marked upon

one of these meridians in a convenient part of the paper. To lay down

the first reference line, apply the protractor to this meridian with its

centre point coincident with the plotted point, and from the bearing

recorded in the field-book, lay off the given angle. Join the two

plotted points and produce the line indefinitely; and upon this line lay

off a distance equal to the length of the measured line. The second

reference line must be drawn in the same manner, from the end of the

first, by laying off from that point the recorded angle. But as the end

of the first line will probably not fall upon a meridian, the protractor

will have to be moved up to the point by means of a parallel ruler

adjusted to the nearest meridian. A more convenient and a more accurate

method, however, is to make the left of the drawing represent the north

while plotting, and to use the [T]-square instead of the parallel ruler.

All subsequent lines are plotted in the same way. Instead of covering

the paper with meridians before commencing to plot, it may, in some

cases, be found more convenient to draw with the set and [T] squares a

short meridian through the point as required.

[Illustration: FIG. 82.]

To lay down Fig. 82 in this manner, having fixed the first station A,

the length of the first primary reference line A B may be laid off upon

the meridian, because in this case the bearing being due north, the

reference line will be coincident with the meridian. This done, the

protractor is to be placed over the plotted point B and the second

bearing laid down. Having plotted the length of this line in the point

C, the third reference line C A will be determined both in length and

direction by the plotted points C A, which should be joined and the line

measured to ascertain whether its length corresponds with the measured

distance. If these do not correspond, the angle must be replotted and

the lengths laid off anew to discover the source of the error. Assuming,

however, that the lines close properly, the offsets and other secondary

points may be next plotted in the manner previously described.

Angles may be more accurately laid down by means of a table of _natural

sines_ and _cosines_ and a linear scale than by means of a protractor.

This is especially true when the angles are subtended by long lines, as,

for example, lines of 3, 4, and even 6 feet. In such cases, a protractor

is of little use. This mode of laying down angles is also convenient in

some cases where angles have been taken, but some of the sides not

measured. In using the table, it must be remembered that the radius of

the sines and cosines is taken as unity; therefore, to find the sine and

cosine for any other radius, the sine and cosine in the tables must be

multiplied by that radius. To lay down the angle A B C in Fig. 82, the

reduced cosine of the angle should be plotted from B in the point _a_,

according to some scale. The scale length of the reduced sine should

then be scribed from _a_, and the scale length of the radius scribed

from B. A line drawn from B through the point of intersection of the

scribes will lay down the angle corresponding to the sine and cosine in

the table. Suppose the radius chosen to be 5 chains, the angle being 32°

30′. The cosine of 32° 30′ is ·8434, which multiplied by 5, the assumed

radius, = 4·2170. Lay off this distance from B on the base A B. The sine

of 32° 30′ is ·5373, which multiplied by 5, = 2·6865. From the point

_a_, which is distant 4·2170 chains from B, with a radius equal to

2·6865 chains, describe an arc; and from the point B, with a radius

equal to 5 chains, describe another arc. From B draw a line through the

intersection of these arcs, and lay off upon it the measured length of

1946 links as recorded in the field-book.

If only the length of the base A B and the magnitudes of the angles

A B C and B A C were given, the lengths of the sides B C and A C would

have to be calculated by trigonometrical formulæ. This method of

calculating the lengths of the sides of triangles and plotting them with

the beam compasses, like chained triangles, is the most accurate for

laying down the great or primary triangles of a survey.

When it is required to plot according to this principle a solitary

angle, as, for example, that between a station line and the meridian, a

circle should be drawn with as large a radius as practicable round the

station at which the angle is to be laid down. The distance between the

points at which the two lines enclosing the angle cut that circle is

then found by multiplying the radius by the _chord_ of the angle, that

is, by twice the sine of half the angle.

It sometimes happens, particularly in extensive surveys, that all the

angular points of some triangles cannot be plotted upon the same sheet

of paper. In such cases, the plot of the outlying points and the sides

of the triangles may be laid down in the following manner. Plot the

intersected triangles independently and trace them on tracing paper.

Then, having drawn a fine line upon both sheets to represent the sheet

edge, lay the points on the trace corresponding to those already plotted

on the first sheet down upon, and make them to coincide with, the

latter. Secure the trace in this position and trace the sheet edge line

upon it. The intersected lines may now be plotted on the fair sheet with

a pricker at points outside the sheet edge line. Next apply the trace to

the second sheet and make the sheet edge lines coincide. Having secured

the trace in this position, the points and the intersected lines on this

second sheet may be plotted upon the fair paper by means of the pricker.

_To Plot Traverse Reference Lines._--In plotting a traverse survey in

which the angles have been measured from a fixed line of direction, the

magnetic meridian, the direction of the lines may be all laid down at

the first angular point. An example will best show the method employed

in this case. It is required to lay down the traverse shown in Fig. 83.

[Illustration: FIG. 83.]

In a convenient part of the paper draw the straight line N S to

represent the magnetic meridian, and plot upon it the first station A.

Set the protractor with its centre accurately placed over this point and

its 360th and 180th divisions coinciding with the meridian. Holding the

instrument securely in this position, lay off around it all the bearings

as entered in the field-book, numbering them in the order in which they

were taken. Against each of these numbers it is well to place the page

of the field-book on which the measurement of the angle and the survey

of the line are entered. The plotting must now be commenced by laying

down the first line through the first bearing and determining its

length from the recorded measurements. The direction of the second line

has next to be transferred from the first station A to the extremity of

the first line, or the second station B. This is accomplished by means

of the parallel ruler, by placing the edge of the ruler through the

plotted point and the point marked as bearing 2, and extending it till

the same edge intersects the point B. A line is then to be drawn from

this point and its length laid off from the field-book as before. The

direction of the third line will then be transferred from the first

angular point to the end of the second line, or station C, in the same

manner. This will be continued for all the lines in the traverse, and if

all the measurements have been correctly laid down, not only will the

last line pass through the point A, but it will be of the same length as

the chained line. Also the bearings taken from A to E and H will pass

through these latter stations. These proof line bearings should be laid

down at the same time as the reference line bearings, from which they

should be distinguished by some sign. The directions of the reference

lines should be consecutively transferred, and the length of each line

should be plotted in its proper place before the direction of the next

is transferred. To ensure the work closing properly, great care must be

taken to plot the points accurately and to draw the pencil lines fine.

[Illustration: FIG. 84.]

The degree of accuracy to be attained will depend in a great measure

upon the extent of the traverse. With long lines the difficulties

increase, and with a great number of angles the chances of error are

multiplied. If the angles are carefully taken, it is probable that

seconds have been read off in several instances, and these if neglected,

especially upon long chain lines, may lead to an error of some

importance. Also when the lines are long, the parallel ruler becomes

practically useless, and some other system has to be adopted. One way of

overcoming these difficulties is to draw a parallel to the first

meridian through every third or fourth angle; in such a case, great care

must be observed in drawing the parallels. A more easily practicable

method, however, is to use the [T]-square in the manner already

described. If the left-hand edge of the drawing board be made the north,

the blade will determine meridional lines, and by laying the straight

side of a semicircular protractor against the edge of the blade, its

zero will be adjusted to the fixed line of direction. The first bearing

having been laid down, the line is drawn and made the scale length of

the chain line; the blade of the square is then pushed to the station

thus found, and the next bearing set off. This operation is repeated

until all the lines have been laid down. If the work closes properly,

the plotting of the secondary lines may be proceeded with.

The most accurate method of plotting a traverse is by rectangular

co-ordinates, or, as it is usually termed, Northings, Southings,

Eastings, and Westings, because the position of each station is plotted

independently, and is not affected by the errors committed in plotting

previous stations. This method consists in assuming two fixed lines or

axes crossing each other at right angles at a fixed point, computing the

perpendicular distances or co-ordinates of each station from those two

axes, and plotting the position of each station by means of the [T] and

set squares and a linear scale. The meridian is usually made to

represent one of the axes, and in this case the co-ordinates parallel to

one axis will be the distances of the stations to the north or south of

the fixed point, and those parallel to the other axis will be their

distances to the east or west of the same point. Let N S, Fig. 84,

represent the meridian, and A B the first bearing taken, and the first

line measured. The angle in this case is N A B = θ. If θ is an acute

angle, the second station B is to the north of the first station A; if

it is an obtuse angle, B is to the south of A. If the angle θ lies to

the right of the meridian, B is to the east of A; if to the left, to the

west. Thus it will be seen that if the northernly and easternly

directions are considered positive, the southernly and westernly

directions will be negative. From the foregoing it is manifest that the

co-ordinates of B are as follows:--

Northing A _a_ = _b_ B (or if negative, southing) = A B × cos. θ.

Easting A _b_ = _a_ B (or if negative, westing) = A B × sin. θ.

To plot the point B, draw through the point A, with the aid of the

[T]-square, a horizontal line. Multiply the chained length of the line

A B by the sine of the angle N A B as entered in the field-book, and set

off this distance along the horizontal line. From the point thus

determined, erect, with the aid of the set square, a perpendicular,

which will be parallel to the meridian. Multiply the chained length of

A B by the cosine of the angle N A B, and set off this distance along

the perpendicular line. The point thus determined will be the position

of the second station B, which may then be joined to A by a straight

line.

[Illustration: FIG. 85.]

The mode of laying down the survey in Fig. 85 will now be obvious.

Having determined the position of the second station B in the manner

just described, draw a horizontal line through B and determine the third

station C in the same way. The fourth station D being to the left of the

meridian passing through C, _c d_ is a westing and is to be considered

as negative. Therefore the horizontal line through C must be drawn to

the left of that station, and the station D determined in the same

manner as the preceding stations.

The results of all these calculations should be entered in a book, in

four columns, for northings, southings, eastings and westings

respectively. Also in four other columns should be entered the total

northing or southing, and easting or westing, of each station from the

first station, computed by adding all the successive northings and

subtracting the southings made in traversing to the station, the result

being a northing if positive, and a southing if negative. The same

treatment is applied to the eastings and westings. This affords a means

of testing the accuracy of the work. It is also obvious that the

position of the last or any station may be determined by this means

without plotting the intermediate stations.

Let it be observed that both θ and sin. θ are positive or negative

according as that angle lies to the east or to the west of the meridian;

and that the cosines of obtuse angles are negative.

_To Plot Detail._--By “detail” is meant outlines or objects whether

natural or artificial, such as fences, walls, rivers, canals, roads,

lakes, water margins, beach marks, seas, or imaginary boundary lines. In

plotting from the entries of measurements for detail, these measurements

should be laid down upon the paper in the order and manner indicated in

the field-book. The mode of plotting the perpendicular reference lines

by means of which the position of the detail is fixed has already been

fully described and illustrated. The proper connections for detail, as

shown by the field-book, should be made by drawing a firm pencil line

through the detail points with the aid of an offset scale adjusted

successively to the adjacent points. All such connections should be

clearly and elegantly made. When all boundaries, roads, and streams have

been drawn and inked in, tracings should be taken in small portions of

all that has been laid down for the use of the “examiner.” The duties of

the examiner are to make on the ground the necessary corrections for

omissions and detail in error; to give, in position and character,

woods, water, marsh, commons, vegetable and geological features, and

permanent artificial structures; and to furnish the descriptive names of

places and things, or any other desirable information. The topographical

character of mountains, marshes, bogs, rough pasture, woods and water,

should be drawn in character on trace and tinted. If required, hill

sketching should also be supplied on the examiner’s trace. On being

returned to the office, the plotter should replot from the field notes

the detail corrected, and transfer the details from the trace to the

map.

_To Plot Contours._--The student who has made himself familiar with the

methods of laying down angles, and plotting reference lines and points,

will find no difficulty in laying down contour traces. When the contour

points have been surveyed with the chain, the contour is obtained by

drawing a free line of feature through the plotted points. But when the

contour points have been surveyed by measuring magnetic angles to known

points, such angles must be laid down at these points, and produced to

meet in the contour point. The drawing of contours differs from the

drawing of ordinary detail insomuch as each contour point is shown by a

small dot, and each carrying point by a similar dot surrounded by a

small hand-drawn circle to distinguish it. The former should be so

plotted as to be distinguishable in the trace or contour line, which

should be readily traceable, but not conspicuous. The line joining

adjacent points should be true lines of feature. Colour is usually

employed for these lines, and it is well to give them a broken or

somewhat undefined character. When the French system is adopted, contour

lines are drawn continuous, a broad but faint line of colour.

_To Plot Sounded Points in Submerged Districts._--When the angles have

been measured on dry land with the theodolite, these angles should be

laid down at the dry-land points, and the lines produced to meet in the

sounded point. But when the angles have been measured on the water with

a sextant, a station pointer is required. The arcs of the pointer should

be adjusted to read the measured angles, and the instrument applied to

the plotted points of the observed objects so as to bring the hair lines

accurately to their respective object points. The sounded point may then

be correctly plotted through the centre of the pointer. If the angles

have been measured by the magnetic compass, that is, if the angles are

those made with the magnetic meridian, the angles should be laid down at

the plotted points of the observed land objects, and the lines produced

to meet in the sounded point. Instead of the station pointer, a piece of

tracing paper may be used in the following manner. Draw three straight

lines radiating from one point so as to make with each other angles

equal to the measured angles. Lay the paper on the plan and move it

about till the three lines traverse the observed objects. The point from

which they diverge will then mark the position of the sounded point,

which may be plotted by being pricked off.

The sounded point determined by angles measured with the sextant may

also be plotted by describing circles on the land-object lines as

chords, to contain segmental angles equal to the measured angles. Such

circles will intersect in the common land-object point and the sounded

point. To plot the sounded point in this manner, requires the solution

by construction of the problem, “to describe on a given line a segment

of a circle that shall contain a given angle.” But this method is

generally found too tedious in practice.

_Errors and Error-sheets._--There is a tendency, as we have previously

remarked, for the measured lengths of lines to be a little too long, by

reason of the irregularities of the surface. It is usual to allow for

this source of error 1 in 1000 in fair open country, and 1¹⁄₂ in 1000 in

close country. When the measurements differ by an amount exceeding these

limits, the pencil trace should not be drawn between the reference

points, but the line should be entered on an “office error-sheet.” The

error-sheet should show the number of the plot-sheet, the triangle, the

book and page in which the measurements are entered, and the scale and

measured lengths of the line. To ascertain the source of the error,

other lines referenced to the reference point or points of the line in

error should be plotted, and the apparent source should be entered on

the error-sheet. If the lines referred to the same point be found to

plot to another point in the reference line, the scale measurement of

this point should also be entered. And if the reference point in error

be not directly surveyed in the survey of their respective lines, the

measurements for reference and the arithmetical reductions will have to

be examined. Besides the office error-sheet, there should be a field

error-sheet for each book and triangle, upon which should be entered the

book, the page, and the line in error, and some indication of the source

of the error. This sheet will be forwarded with the field-book to the

surveyor for correction. The following are examples of a common and very

good form of error-sheet, but it may be varied in many ways if thought

desirable:--

OFFICE ERROR-SHEET.

_Plotter’s Name_____________ _Date_ ____________

-----+------+--------+---------+--------+----------+------------------

Book.|Lines.| Scale |Reference|Apparent|Triangles.| Observations.

-----+ |Measure-| Points | Correc-| |

Page.| | ment. |of Lines.| tions. | |

-----+------+--------+----+----+--------+----------+------------------

200 | | |1118|1551| 1651 | |Examine reference

-----+ 1953 | 1907 +----+----+--------+ |point and line.

23 | | |2094|4020| 4020 | |

| | | | | | |

200 | | |2814|1308| | [Illus- |

-----+ 3000 | 3056 +----+----| 3056 | tra- |Examine line.

28 | | |4020|3082| | tion] |

| | | | | | |

200 | | |1551| 85 | 1651 | |Examine reference

-----+ 1314 | 1323 +----+----+--------+ |point and line.

42 | | |4020|3028| 4020 | |

-----+------+--------+----+----+--------+----------+------------------

FIELD ERROR-SHEET.

_To A. B., Surveyor._ _Date_ ____________

-----+------+----------+----------------------------------------------

Book.|Lines.|Triangles.| Observations.

-----+ | |

Page.| | |

-----+------+----------+----------------------------------------------

| | |_Examine reference points and line._

200 | | |1651

-----+ 1953 | |---- Reference point (August 10th, 1874).

23 | | |4020

| | |

200 | | [Illus- |

-----+ 3000 | tra- |_Examine line._ Line 3056 (August 10th, 1874).

28 | | tion] |

| | |_Examine reference points and line._

200 | | |1651

-----+ 1314 | |---- (August 12th, 1874).

42 | | |4020

| | | Corrected in the field, A. B.

-----+------+----------+----------------------------------------------

_To Plot Vertical Sections._--In plotting a vertical section, a fine and

firm horizontal line is first drawn to represent the _datum line_. The

reference points are then plotted upon this line from the level-book by

means of a linear scale, in the manner already described for plotting

such points. The reference points to be plotted upon the datum line are

the chain lengths entered in the field-book in the column headed

Distances. These distances are the points at which the levels were

taken, and between them, unless otherwise stated in the field-book, the

ground is supposed to slope uniformly. Moreover, these distances are

assumed to be measured horizontally, and therefore care must be taken to

ascertain whether or not they were so measured in the field; if not,

they must be reduced before plotting, or the section will be too long.

Having plotted the reference points on the datum line, a perpendicular

must be erected from each of them, and a length laid off upon this

perpendicular equal to the vertical height above the datum line

indicated by the entry in the column of the level-book headed Reduced

Levels against the distance to which the perpendicular corresponds. To

render the differences of altitude more apparent, these vertical

distances are plotted to a much larger scale than the horizontal, as

explained in a preceding Section. To erect the perpendiculars, the [T]

and set square furnish the most convenient means. The detail points thus

determined upon the perpendiculars represent the points in the surface

of the ground at which the levels were taken, and by joining these

points we obtain the surface line. An example will clearly show the

method pursued. Let it be required to lay down the section from the

following level-book:--

-------+-------+-----+-----+-------+-------+-------------------------

Back | Fore |Rise.|Fall.|Reduced| Dis- | Remarks.

Sights.|Sights.| | |Levels.|tances.|

-------+-------+-----+-----+-------+-------+-------------------------

feet. | feet. |feet.|feet.| feet. |chains.|

| | | | 100·00| .. |{B.M. north-west corner

| | | | | |{of church tower.

16·41| 9·37| 7·04| .. | 107·04| 230 |

19·36| 10·43| 8·93| .. | 115·97| 465 |

16·42| 19·36| .. | 2·94| 113·03| 640 |

8·36| 14·36| .. | 6·00| 107·03| 794 |

9·37| 12·49| .. | 3·12| 103·91| 1030 |

11·64| 19·76| .. | 8·12| 95·79| 1200 |

19·46| 9·32|10·14| .. | 105·93| 1564 |

17·64| 13·62| 4·02| .. | 109·95| .. |{Centre of road at 123

| | | | | |{links.

18·76| 12·64| 6·12| .. | 116·07| 1823 |

19·84| 16·92| 2·92| .. | 118·99| 1964 |

19·76| 11·64| 8·12| .. | 127·11| 2100 |{Forward station ☉ at

| | | | | |{corner of wood.

17·64| 19·72| .. | 2·08| 125·03| 2250 |

9·73| 18·64| .. | 8·91| 116·12| 2376 |

8·64| 17·64| .. | 9·00| 107·12| 2590 |

18·76| 16·24| 2·52| .. | 109·64| 2700 |

-------+-------+-----+-----+ | |

231·79| 222·15|49·81|40·17| | |

222·15| |40·17| | 100·00| |

-------+ +-----+ +-------+ |

| | | | |{Difference between datum and

9·64| | 9·64| | 9·64|{last reduced level, or height of

| | | | |{B above A.

-------+-------+-----+-----+-------+---------------------------------

[Illustration: FIG. 86.]

Draw the datum line D L, Fig. 86, and set off along it the distances

230, 465, 640, 794, &c., links; these points will be the reference

points for the perpendiculars. Erect a perpendicular from each of these

points, and lay off, to a suitable scale, upon these lines successively

the vertical heights 100, 107·04, 115·97, 113·03, 107·03, &c. The points

thus determined will be the surface detail points, and by joining these

we shall obtain the surface line. Then will A D L B represent a section

of the ground between A and B. A description of objects on the surface

worthy of notice should be written over such objects.

In working sections, where great accuracy is required, larger scales are

employed, and the levels are taken at more frequent intervals. Thus, in

a railway working section, for example, the levels are taken at every

chain’s length, and also over every little undulation in the surface of

the ground. In preparing such sections, vertical lines are drawn in blue

at every chain’s length up to the surface of the ground from the datum

line, and on each vertical is written the reduced height above datum

from the column of reduced levels in the level-book.

Sections, especially working sections, are usually drawn upon ruled, or,

as it is called, “section” paper, the nature of which we have already

described. This method, which was introduced by Mr. Brunel, possesses

many practical advantages, inasmuch as it obviates the necessity of

plotting the “distances” and erecting perpendiculars, the latter already

existing. It also greatly facilitates the computation of the contents of

a given section. Its chief defect lies in the difficulty of making the

horizontal lines coincide when joining the sheets end to end. Of course

scales are not required upon section paper.

_To lay down Gradients._--The method of laying down the gradients of

railways and roads usually adopted in practice consists in applying one

end of an extended silken thread to the section at the point in which

the road commences, and the other end in such a position that the thread

may cut the profile of the earth’s surface so as to leave equal portions

of space above and below the thread, as nearly as can be judged by the

eye. The cuttings from the parts above the thread will then furnish

sufficient materials to form the embankments in the spaces below. This

is called “balancing” the cuttings and embankments. When the first

gradient has been determined in this way, it may be found unfavourable

to the second in respect to the extent of cuttings and embankments; in

such a case it must be modified to suit the requirements of the latter.

In this way the gradients must be modified successively until the

compound result evidently gives a _minimum_ of cuttings and embankments,

due regard, of course, being had to the limits imposed by the nature of

the case, both with respect to the ruling gradient and the proper

heights for bridges.

_To Plot a Section from a Contour Map._--The mode of plotting a section

from a contoured plan was explained when treating of contour lines. The

contour map used for this purpose should give the features of the

surface configuration in sufficient detail without serious error. Having

drawn a line of section on the map and a datum line upon the fair paper

for the vertical section, the points in which the section line

intersects the contours should be measured on the scale of the map from

a zero point in that line, and the measurements plotted upon the datum

line. Perpendiculars should then be drawn through these plotted points,

and on these perpendiculars the reduced altitudes of their respective

contour points should be plotted. A line drawn through these surface

plotted points will be the surface line. When the horizontal scales of

the map and the section are the same, the contour plane lines may be

drawn on the paper for the section parallel to the section line on the

map, and perpendiculars raised to intersect them from the points on the

map in which the section line intersects the contours, in the manner

previously described. The points of intersection with the parallel lines

will be the surface contour points in the vertical section. For

practical purposes, the parallel lines and the perpendiculars are only

temporarily drawn in pencil until the surface trace shall have been

obtained and drawn in ink, with the datum line.

The Draughtsman's Handbook of Plan and Map Drawing Including instructions for the preparation of engineering, architectural, and mechanical drawings. · 第 3 / 7 章