CAIRO TO JERUSALEM BY RAIL

It was officially announced May 11 that the swing bridge over the Suez

Canal at Kantara was completed, and that on May 15, 1918, there was

direct railway service from Cairo to Jerusalem. When the war broke out

there were no railways between the Suez Canal and the Jaffa-Jerusalem

railway, a distance of some 200 miles, mainly desert.

[Illustration]

At that time a line ran along the western bank of the canal from Suez

to Port Said. It was linked up with the main lines of the Egyptian

State railways by a single track from Ismailia to Zagazig.

A few miles to the north of that track another line from Zagazig

stopped some eighteen miles short of the canal at El Salhia. At the

beginning of the war, to facilitate the transport of troops and

supplies to the canal and beyond, the track from Zagazig to Ismailia

was doubled, and a new line was pushed out from the dead end at El

Salhia to the canal opposite Kantara, a village on the eastern, or

Sinai, side of the canal. Later, when the British troops entered the

Sinai Peninsula, a railway was begun from Kantara eastward, and as the

British troops advanced so did the railway. It followed the northern

track across Sinai, and had been taken within a few miles of Gaza when

that town was captured last November. Meantime the Turks had built a

branch from the Jaffa-Jerusalem line to a point only five miles north

of Gaza, and by February General Allenby had joined the two systems, so

that there was direct railway connection between Kantara and Jerusalem.