EXECUTION OF THE WORK

Appended to that portion of the sundry civil appropriation act approved

March. 2, 1889,[1] in which certain expenses of the United States

Geological Survey are provided for, is the following item:

Repair of the ruin of Casa Grande, Arizona: To enable the Secretary

of the Interior to repair and protect the ruin of Casa Grande,

situate in Pinal County, near Florence, Arizona, two thousand

dollars; and the President is authorized to reserve from settlement

and sale the land on which said ruin is situated and so much of the

public land adjacent thereto as in his judgment may be necessary for

the protection of said ruin and of the ancient city of which it is a

part.

[Footnote 1: 25 Statutes, p. 961.]

On the 12th of April, 1889, there was a conference between the Secretary

of the Interior and the Commissioner of the General Land Office looking

to the execution of the law, and on the 16th of that month the

Commissioner submitted a statement on the subject, calling attention to

the fact that the appropriation would not be available until July 1

following, and suggesting that a special agent should be sent out to

examine the ruin. This suggestion was approved, and on April 27, 1889,

Special Agent Alexander L. Morrison, of the General Land Office, was

instructed to proceed to the ruins for the purpose of investigating and

reporting as to what method should be adopted for their repair and

protection. Mr Morrison was further instructed to report "all the facts

obtainable as regards said ruins of 'Casa Grande,' in order that

appropriate action may be taken by the Department for its preservation."

On May 15,1889, Mr Morrison submitted a report to the Commissioner,

describing his journey, the location of the ruin, the ruin itself, and

other ruins in the vicinity. He stated that danger to the ruin was of

three kinds--(1) by vandalism, (2) by elements, (3) by undermining. He

recommended the construction of a roof and an underpinning of stone for

the walls. Finally, he gave some historical notes, and closed with a

peroration.

Mr Morrison's plans were found impracticable, as their execution would

require an expenditure of many times the sum appropriated, and on

September 23, 1889, all the papers in the case were transmitted by the

Secretary to the Director of the Geological Survey, "for appropriate

action under the clause of the act referred to, as being within the

province of your Bureau." It was ordered that the work be commenced

without the least delay, and November 27, 1889, Mr Victor Mindeleff, of

the Bureau of Ethnology, was detailed by the Director and ordered to

proceed to the ruin and report on the best means of repairing it and

protecting it from further destruction. He was also directed to make

other investigations in the vicinity, which have no relation to the

present case.

On July 1, 1890, Mr Mindeleff submitted a report. He described the ruins

of which Casa Grande is the type, and also Casa Grande itself. He also

made a statement of the condition of the ruin and suggested that the

main destruction "was due to the undermining of the walls, and stated

that much damage had been done by tourists. He recommended (1) that an

area about the ruin be fenced in; (2) that a man be located permanently

on the ground to watch the ruins; (3) that the ruins be cleaned out; (4)

that the walls be underpinned with brick instead of stone, as previously

suggested; (5) that the tops of the walls, after removing several inches

to afford a good bearing surface, be treated with a coping of cement. It

was regarded that this plan, if carried into effect, would afford

sufficient protection against the weather, but a plan for a roof was

submitted should such a structure be deemed desirable and practicable.

Mr Mindeleff also recommended a number of tie-rods and beams, the

replacement of the broken-out lintels, and the filling of the cavities

above.

This plan was approved in its general features, but the means provided

for its execution were found insufficient. A further complication arose

from the fact that a few months later Mr Mindeleff severed his

connection with the Bureau of Ethnology and his knowledge became no

longer available.

November 20, 1890, the writer was ordered to proceed to the ruin and

inaugurate the work of repair, following, so far as practicable, the

plans already approved. He left Washington soon afterward and reached

the ruin late in December. It was found necessary to make a detailed

survey of the ruin and of the group of which it forms a part, and to

make plans and sections showing the probable amount of excavation for

the use of those who were invited to bid on the work. Furthermore, the

amount appropriated was so well known to be inadequate that great

difficulty was experienced in obtaining bids, and it was only through

the efficient cooperation of the Reverend I. T. Whittemore at Florence

and of Mr C. A. Garlick at Phoenix that success was finally achieved.

Two bids were received from the former place and one from the latter;

but this was not accomplished until March 17, 1891, the date when the

last bid was received. In the meantime the writer, having completed his

work at Casa Grande, so far as he could, had entered, in January, on an

archeologic investigation of the valley of the Rio Verde, in compliance

with his orders to that effect.

It was found impossible to execute all the work deemed requisite for the

preservation of the ruin within the limits of the appropriation. A

selection of items became necessary, therefore, and those which were of

most importance were chosen. Even in this, however, it was found that a

maximum limit on the amount of work to be done on each item must be set,

and this limit was considerably below the amount of work estimated to be

necessary.

The first thing to be done was, of course, the clearing out of the

rubbish and debris. The item next in importance was the underpinning of

the walls with brick wherever it was needed. The third item was the

restoration of the lintels and the filling of the cavities above them.

The fourth item was the tying in of the south wall, or of the several

parts of it, with braces. This was the only feature of the plan which

would appreciably disfigure the ruin, but some such device was deemed

essential for the preservation of the south wall.

These four items consumed practically all of the amount appropriated,

and the other items of the original plan were therefore omitted. The bid

of T. L. Stouffer and F. E. White, of Florence, Arizona, covering the

four items, was accepted, and a contract was made with them, under date

of May 9, 1891, for the execution of the work for the sum of $1,985.

This contract, together with the specifications, plans, and other

drawings which formed part of it, accompany this report. It was

transmitted to the Director of the Geological Survey, and by him

approved and forwarded to the Secretary of the Interior June 6, 1891. It

was approved by the Acting Secretary June 20, 1891. Finally, on July 20,

1891, it was placed on file, together "with the bids, proposals, and all

the original papers."

A time limit of two months was made in the contract, expiring August 20,

1891, but it was changed to four months from July 1, 1891, expiring

October 31, 1891. Before the time expired, however, Mr H. G. Rizer, then

chief clerk of the Bureau of Ethnology, was ordered to proceed to Casa

Grande ruin to examine the work done and, if in accord with the terms of

the contract and the specifications, to certify the amount due the

contractors. He submitted a report, under date of November 24, 1891,

which is appended hereto. He also obtained six photographic negatives of

the work as it stood a short time before its completion, and two of

these (reproduced in plates CXX and CXXI) have been utilized in the

preparation of this report.

Mr Rizer found that a considerable amount of work had been done by the

contractors in excess of that authorized, and also that not sufficient

work had been done to render the repairs permanently effective. Under

the terms of the contract, no amount in excess of that stated ($1,985)

could be paid, and payment of this amount was made late in 1891. On

January 7, 1892, the contractors filed a claim for extra work on the

ruin amounting to $600.40. The work was actually performed, but the

terms of the contract were clear, and the claim was therefore

disapproved January 28, 1892.

It would have been desirable to have had a supervisor of the work, but

as the contract consumed practically all of the amount appropriated no

provision could be made for one. It is fortunate, therefore, that the

Reverend I. T. Whittemore, who had in the meantime been appointed

honorary custodian of the ruin, generously undertook to look after the

work without compensation, and on its conclusion the small sum remaining

($15) was turned over to him, thus exhausting the appropriation. In the

sundry civil appropriation act for the year ending June 30, 1893,

provision was made for a salaried custodian of the ruin, and Mr

Whittemore was appointed to this position. Similar provision has been

continued from year to year to the present time.

It is to be regretted that the necessities of the case, imposed by the

limited amount appropriated, compelled the fixing of a maximum amount of

work so far below the amount necessary that the repair of the ruin is

incomplete. Had it been possible to carry out the plans, it is believed

that the ruin would have stood unchanged for many decades, if not for a

century. Should further provision be made for the continuation of the

work, it should include an item for the fencing of the area covered by

the ruins or of the reservation, and possibly an item for the

construction of a roof.

It is not clear that a roof is absolutely necessary, but it is certain

that it would be very undesirable. The region where this rain occurs has

probably less rainfall than any other part of the United States, but it

must not be forgotten that while rainstorms are infrequent they are

sometimes violent, and what damage they do may be done in a few hours.

All the items for the repair of the ruin, except that pertaining to a

roof, were so devised that the ruin was not materially disfigured or

changed, and were they fully carried out the ruin would present much the

same general appearance as before. It is important that this appearance

should be preserved as far as possible, but it can not be maintained if

a roof is erected over the walls. As four years have elapsed since the

completion of the work, it should be possible now to determine whether

atmospheric erosion has played a material part in the work of

destruction.[1]

[Footnote 1: See the letter of the Director of the Bureau of

American Ethnology to the Secretary of the Interior regarding the

examination of Casa Grande by Mr W J McGee in the supplement to

the present paper.]

In the original plans and in the specifications which formed part of the

contract (although this section was not operative) a plan for a roof was

included. Such a structure, if erected at all, should be made as

inconspicuous as possible and should be supported entirely from within

the building. The system of framing employed might safely be left to the

contractor if he were made responsible for the strength of the completed

structure.