SCAFFOLDING

A TREATISE ON

THE DESIGN _&_ ERECTION OF SCAFFOLDS,

GANTRIES, AND STAGINGS,

With an Account of the Appliances used in

connection therewith

FOR THE USE OF CONTRACTORS, BUILDERS,

CLERKS OF WORKS, ETC.

With a Chapter on the Legal Aspect of the Question.

By A. G. H. THATCHER,

BUILDING SURVEYOR

SECOND EDITION, REVISED

WITH 146 DIAGRAMS AND 6 FULL-PAGE PLATES.

LONDON:

B. T. BATSFORD, 94 HIGH HOLBORN

1907.

PREFACE

Scaffolding up to quite recent years has been considered by builders

and others concerned, with the exception of the actual workmen, to be a

matter of small importance and consequently unworthy of study. Recent

legislation, however (the Workmen’s Compensation Act, 1897, and the

Factory and Workshop Act, 1901, and preceding dates), has brought it

into greater prominence, with the result that more attention has lately

been given to it. Special study of the subject has, however, remained

very difficult owing to the lack of accessible information.

The author, in the course of considerable experience in the building

trade, has had opportunities of examining a large number of scaffolds

throughout the country, affording him exceptional facilities for

thoroughly studying the subject, and he has been led to prepare this

treatise in the hope that it may prove useful to those engaged both

in the design and erection of scaffolds for building purposes. While

special attention has been given to practical details, the theory has

not been neglected, but has been dealt with by the use of terms well

understood in the building trade. The various formulæ given have been

simplified as far as possible, and it is hoped that in these days of

technical education they will not be beyond the scope of the reader.

The illustrations have generally been drawn to scale, but for the sake

of clearness, details are given to a larger scale where necessary.

The practice of allowing workmen to erect scaffolds without the aid

of expert supervision, as is generally the case, is to be strongly

deprecated. The architect, builder, or clerk of works, should in all

cases be responsible for their erection—the risk of defective or unsafe

work being thereby minimised, and an economy often effected in both

labour and material.

The author desires to acknowledge his indebtedness to Mr. G.

Thatcher, of H.M. Office of Works and Hampton Court Palace, for

valuable information contributed by him, and to Mr. J. Clark, of

the Factory Department of the Home Office, for his very careful

reading of the proofs; while his best thanks are due to the following

manufacturers:—Mr. C. Batchelor, Messrs. Bullivant & Co., Ltd., Messrs.

Butters Bros., Mr. J. Fishburn, Messrs. Frost & Co., and Mr. E. Palmer,

who have furnished him with particulars of their various specialities.

A. G. H. T.

LONDON: _February 1904_.

NOTE TO THE SECOND EDITION

Recent alterations in and additions to the legal enactments affecting

scaffolding and the persons employed in its erection have rendered

necessary a second edition of this work. The author has accordingly

revised the information relating to the law of the subject, and has

embodied the important series of suggestions for the guidance of those

engaged in building operations, published in the Annual Report of the

Chief Inspector of Factories, which, if followed out, will undoubtedly

be the means of reducing the number of fatal and other accidents

occurring at such works.

A. G. H. T.

_October 1907._

CONTENTS

PAGE

PREFACE v

CHAPTER I

_SCAFFOLDING_

Scaffolding—Definition of—Northern system—Derrick

stagings—Working platforms—South country system—Gantries,

commonly called travellers—Travelling gantry—Gantries

which serve as a base for lighter forms of

scaffolding—Stagings—Pole scaffolds—Bricklayers’

scaffolds—Masons’ scaffolds—Connections 1-29

CHAPTER II

_SCAFFOLDS FOR SPECIAL PURPOSES_

Needle scaffolding—Scaffolds for chimney shafts,

towers and steeples—Domes and arches—Swinging

scaffolds—Painters’ boats—Boatswain’s boat—Ladder

scaffolds—Supported painter’s boat 30-48

CHAPTER III

_SHORING AND UNDERPINNING_

Shoring—Flying shores—Raking shores—Underpinning 49-61

CHAPTER IV

_TIMBER_

Classification and structure—Defects in the living

tree—Felling—Conversion—Seasoning—Description—Selection

—Decay—Preservation—Durability—Use of scaffolding timber 62-75

CHAPTER V

_CORDAGE AND KNOTS_

Cordage—Strength of—Knots 76-89

CHAPTER VI

_SCAFFOLDING ACCESSORIES AND THEIR USE_

Ladders—Trestles—Cripples—Buckets and

skips—Baskets—Barrows—Stone bogies—Hand

barrows—Hods—Timber trucks—Sack trucks—Crates—Ashlar

shears—Stone clips and slings—Stone lewises—Stone

cramps—Wire and chain scaffold lashings—Tightening

screws—Rollers—Levers—Dog irons—Bolts—Straps—Wire

ropes—Chains—Slater’s truss—Duck runs—Mortar

boards—Wedges—Nails—Spikes—Scaffolder’s hatchet 90-114

CHAPTER VII

_THE TRANSPORT OF MATERIAL_

Crane engines—The crane—Pulleys—Differential

pulleys—Winch—Jibs—Shears—Gin—Rails—Sack

trucks—Attachment of material—Ironwork—Timber

—Bricks—Slates—Stone 115-130

CHAPTER VIII

_THE STABILITY OF A SCAFFOLD_

Stability—Wind pressures—Force of weight or gravity—To

find the centre of gravity of a body—Two or more

bodies—Of a dependent scaffold and the effect of loads

upon it—Of a gantry—Of a Scotch derrick 131-142

CHAPTER IX

_THE STRENGTH OF A SCAFFOLD_

Failure of beams—Pillars and struts—Ties and

traces—Dead loads—Live loads—Breaking weight—Safe

load—Constants—Beams subject to a transverse

strain—Posts and struts subject to compression—Braces

and ties subject to a tensional strain 143-153

CHAPTER X

_THE PREVENTION OF ACCIDENTS_

Short ladders—Sagging of ladders—Guard rails—Well

holes—Edge boards—Traps—Runs—Supports to centering—Damp

cordage—Sound material—Competent control—Fan guards—Due

care by workmen 154-160

CHAPTER XI

_LEGAL MATTERS AFFECTING SCAFFOLDING_

Scaffolding bye-laws—Burgh Police (Scotland) Act—Factory

and Workshop Act, 1901—Abstract of same, issued from

the Home Office—Notice of Accident Act—Report on

Building Accidents by a Home Office Inspector—Workmen’s

Compensation Act, 1906—Application of Act and definitions

161-178C

APPENDIX: Weight of Material 179

INDEX 183

LIST OF ILLUSTRATIONS

_PLATES_

I. Derrick staging _Frontispiece_

II. External chimney scaffold _Facing p._ 33

III. Knots 79

IV. Knots 81

V. Knots 85

VI. Knots 87

_ILLUSTRATIONS IN TEXT_

FIG. PAGE

1. Elevation of staging for derrick crane 4

2. Plan of king leg 6

3. Showing shoring to central standard 6

4. Plan of derrick platform partially covered 7

5. Showing method of fixing ladders 8

6. Showing derrick staging mounted on travelling bogie 10

7. Elevation of square derrick staging 11

8 and 8A. Elevation of gantry for traveller 13

9. Footing blocks for struts 15

10. Elevation of travelling gantry 15

11. Gantry or elevated platform over footpaths 17

12. Example of stagings 18

13. Elevation of pole scaffold 20

14. Method of fixing rising standard 21

15. Method of connecting ledgers 22

16. Method of connecting ledgers 22

17. Method of connecting ledgers 23

18. Method of connecting ledgers 23

19. Method of supporting putlogs where windows occur 24

20. Method of supporting putlogs where windows occur 24

21. Shores and ties for dependent scaffolds 25

22. Methods of laying boards 26

23. Methods of laying boards 26

24. Masons’ scaffold: end elevation 27

25. Landing stages 28

26. Needle scaffold 31

27. Internal chimney 33

28. Method of climbing chimneys, steeples, &c. 35

29. Method of climbing chimneys, steeples, &c. 36

30. Brackets for climbing chimneys, steeples, &c. 37

31. Methods of slinging painters’ boats on chimneys, &c. 38

32. Chimney scaffolds for repairs, &c. 39

33. Details of chimney scaffolds for repairs, &c. 39

34. Details of chimney scaffolds for repairs, &c. 40

35. Details of chimney scaffolds for repairs, &c. 40

36. Details of chimney scaffolds for repairs, &c. 41

37. Method of supporting standards within high towers 41

38. Scaffold designed for repairing roofs or arches

where roadway has to be kept open 42

39. Painters’ boats or cradles 43

40. Method of slinging cradle to move horizontally 44

41. Improved painter’s boat 44

42. Boatswain’s boat 45

43. Elevation of ladder scaffolding 46

44. Details of ladder scaffolding 47

45. Details of ladder scaffolding 47

46. Details of ladder scaffolding 47

47. Examples of flying shores 51

48. Examples of single raking shore 52

49. Examples of system of raking shores 53

50. Details of raking shores 54

51. Details of raking shores 55

52. Details of raking shores 56

53. Example of underpinning 59

54. Example of window strutting 60

55. Example of cup shakes in timber 63

56. Example of radial shakes in timber 63

57. Method of cutting stiffest beam from log 66

58. Method of cutting strongest beam from log 66

59. Method of cutting planks from log 67

60. Method of stacking timber for seasoning 68

61. Examples of weather shakes in balks 68

62. Method of strapping ends of boards 74

63. Details of ladder construction 91

64. Details of ladder construction 91

65. Example of painters’ trestles 92

66. Example of cripples 93

67. Example of cripples 93

68. Example of tipping pail 94

69. Details of improved safety baskets 95

70. Details of improved safety baskets 95

71. Details of improved safety baskets 96

72. Details of improved safety baskets 96

73. Details of improved safety baskets 96

74. Example of navvy’s barrow 98

75. Example of stone bogie 98

76. Example of hand barrows 98

77. Example of labourer’s hod 98

78. Example of timber trucks 98

79. Example of sack trucks 98

80. Example of brick crates 99

81. Example of ashlar shears 100

82. Example of ashlar shears 100

83. Example of stone clips 101

84. Method of slinging stone 101

85. Method of slinging stone 101

86. Method of hoisting by means of the lewis 102

87. Method of hoisting by means of the lewis 102

88. Method of hoisting by means of the lewis 102

89. Method of hoisting by means of the lewis 102

90. Example of the stone cramp 103

91. Wire rope lashing 104

92. Chain and bracket lashing 105

93. Coupling links 105

94. Rollers 106

95. Levers 106

96. Dog irons 107

97. Methods of fixing dog irons 107

98. Methods of fixing dog irons 107

99. Methods of fixing dog irons 107

100. Iron bolts 108

101. Iron straps 109

102. Slaters’ truss 112

103. Duck runs 112

104. Scaffolder’s hatchet 113

105. Manual building crane 117

106. Example of pulley wheel 118

107. Example of groove for pulley wheel 119

108. Example of groove for pulley wheel 119

109. Example of groove for pulley wheel 119

110. Example of groove for pulley wheel 119

111. Example of groove for pulley wheel 119

112. Example of sprocket wheel 119

113. Example of single movable pulley 120

114. Example of blocks and tackle 120

115 and 116. Example of differential pulley 122

117. The winch 124

118. The winch in use with a double rope 125

119. Example of a jib 125

120. Example of a jib for fixing purposes 126

121. Example of a mason’s jib 127

122. Example of shear legs 127

123. Example of shear legs to carry jib 128

124. Example of movable shear legs 128

125. Example of a gin 129

126. Method of slinging girders 129

127. Diagram showing method of finding the centre of

gravity of a rectangular body 136

128. Diagram showing method of finding the centre of

gravity between two combined weights 137

129. Diagram showing method of finding the centre of

gravity between three or more combined bodies 138

130. Method of finding the centre of gravity of a

rectangular surface 139

131. Method of finding the centre of gravity of a

triangular surface 141

132. Diagram showing the method of calculating the

breaking weights of beams 147

133. Diagram showing the method of calculating the

breaking weights of beams 147

134. Diagram showing the method of calculating the

breaking weights of beams 148

135. Diagram showing the method of calculating the

breaking weights of beams 148

136. Diagram showing the method of calculating the

breaking weights of beams 148

137. Diagram showing the method of calculating the

breaking weights of beams 148

138. Diagram suggestion for preventing accidents

on short ladders 154

139. Method of staying ladder to prevent sagging 155

140. Method of staying ladder to prevent sagging 155

141. Illustrating dangerously laid boards 156

142. Illustrating the danger of a trap 156

143. Illustrating method of supporting centering 157

144. Illustrating method of supporting centering 158

145. Fan guards 158

146. Illustrating cause of fatal accident 159

SCAFFOLDING

CHAPTER I

_SCAFFOLDING_

Scaffolding is the art of arranging and combining pieces of timber in

order to enable workmen to proceed with their work, and from which, if

required, to lift and carry the material necessary for their purpose.

Many definitions of a scaffold have been given by authorities on

building construction; some of the best known are as follows:—

Mitchell (C. F.): 'Temporary erections constructed to support a number

of platforms at different heights, raised for the convenience of

workmen to enable them to get at their work and to raise the necessary

material for the same.’

Tredgold (Hurst): 'A scaffold as used in building is a temporary

structure supporting a platform by means of which the workmen and their

materials are brought within reach of their work.’

Rivington: 'Scaffolds are temporary erections of timber supporting

platforms close to the work, on which the workmen stand and deposit

their materials.’

Banister F. Fletcher, in 'Carpentry and Joinery’: 'A scaffold is a

temporary structure placed alongside a building to facilitate its

erection by supporting workmen and raising materials during the

construction, or for the repair of buildings.’

Recent cases tried under the Workmen’s Compensation Act have given a

wider meaning to the word, and the following definition is perhaps the

most comprehensive at the present time:

A scaffold, as used in building, is a temporary arrangement of timbers

combined and supported in various ways to enable the workmen to proceed

with their work, and where required, to afford facilities for the

lifting and carrying of the materials.

The two principal methods of scaffolding are known respectively as the

North and South country systems. The northern, as indicated by the

name, was at one time in use only in Scotland and the north of England,

but its many advantages, more especially for the transport of material,

have now caused it to become general throughout the country.

The second method is essentially the South country system, and is of

greater use when power is not necessary for the construction of the

building.

A combination of both methods is commonly seen, and found useful in

practice.

In scaffolding, the vertical timbers are known as standards or

uprights. The horizontal timbers between the standards are known as

ledgers when of cylindrical section, but as transoms and runners when

of rectangular section. Braces, shores, struts and ties of any section

are pieces used to stiffen the structure. The putlogs, or joists as

they are called when of greater length, carry the boards which form the

working platform.

=The Northern System.=—This scaffolding can be divided into two

parts. First, the derrick staging from which the transporting power

acts; and, second, the platforms, which bring the workmen within reach

of their work.

=Derrick Stagings.=—These stagings, also known as Scotch derricks

and 'Scotchmen,’ are erected to carry the power required, usually a

steam crane.

They consist of three or four timber towers or legs supporting a

platform upon which the crane stands. The number of legs depends upon

the area over which the power is required to act.

When one crane is to be erected, three legs are sufficient to carry the

platform.

If the building is a large one, several such stagings may be

constructed; but in some cases two cranes are required where the size

of the building will not allow of two stagings. In these cases the

platform is square and supported at each angle by a leg. The cranes are

then fixed diametrically opposite each other.

In determining the position of the legs they must be placed where the

effective range of the crane is most required, and also where they will

cause the least possible obstruction to the progress of the building.

The position of the tower that carries the crane, and which is known

as the principal or king leg, is first fixed. The secondary or queen

legs are set out from it in the form of an isosceles triangle. The

distance between the king and queen legs depends upon the length of

the sleepers. These run from below the engine to the lower ends of the

guys, and average from 25 to 30 feet in length.

The legs, especially the king legs, if intended to rise from the earth,

must have a foundation of two thicknesses of 3-inch timbering laid

crosswise. This is unnecessary if there is a concrete or other solid

foundation.

Apart from the necessity for any foundation, the standards should rise

from a framework of balk timbers of about 12 in. by 12 in., laid on the

ground, and halved at their intersection (fig. 1).

[Illustration: FIG. 1.—ELEVATION OF STAGING FOR DERRICK CRANE]

In the case of the queen legs an extra balk is placed under the

framework, as shown in fig. 1.

The legs are from 6 to 10 feet square on plan, the king legs being the

larger. Each leg comprises four standards, either of whole timbers or

battens bolted together. The standards for the king legs should measure

not less than 9 in. by 9 in.; if of battens, then three pieces 9 in. by

3 in. should be used.

For the queen legs, balks 7 in. by 7 in., or three pieces 7 in. by

2-1/2 in., are sufficient sectional area. Where battens are used they

are given a lap equal to one-third of their full length, and are bolted

together by 3/4-inch wrought-iron bolts.

Whole timbers are used when they can be obtained in one piece of

sufficient length.

As the standards rise they are divided into bays by transoms. These are

made out of about 9-in. by 3-in. deals, placed from about 6 to 10 feet

apart.

The bays are triangulated by cross-braces 7 in. by 2-1/2 in.; both of

these are usually placed on the outside of the bay, but one or both

may be placed on the inside. The first method is the better, as the

braces, by butting against the transoms, give an increased resistance

to movement.

The king leg, having to carry the weight of the engine, requires

greater strength. This is gained by running an extra standard up the

centre of the leg. If it is whole timber, balks about 14 in. by 14 in.

are required; if built up, four deals 16 in. by 4 in. are used. It

should stand upon an extra balk laid with the horizontal framing at the

bottom of the leg, and should rest on a solid foundation.

To prevent any tendency to flexure this extra standard should be

strutted from all four of the outer standards behind each transom (see

fig. 2).

Another method is to shore the central standard from the foundation, as

in fig. 3.

The legs in this manner can be made to support a platform up to 120

feet in height.

The required height having been reached, the legs are connected by

trussed beams in the following manner: Two balk timbers of about 12 in.

by 8 in. are laid immediately above each other between the king leg

and each queen leg, resting on the two top transoms, as shown in fig.

1. They are from 6 to 9 feet apart, the top bay being sometimes made

slightly lower than the others.

The lower balks are connected to the centre standard of the king leg by

wrought-iron straps.

[Illustration: FIG. 2.—PLAN OF KING LEG]

[Illustration: A, Central Standard. B, Shorings.

FIG. 3.—SHOWING SHORING TO CENTRAL STANDARD]

The top balks project from 6 to 10 feet beyond the king leg, and

are halved at their point of intersection. The projecting ends are

connected to each other by pieces 8 in. by 6 in., and again to the

return balk by similar pieces (see fig. 4). They are also supported by

struts from the central standard, as shown in fig. 1. The upper and

lower balks are connected by iron bolts about 10 feet apart, and each

bay thus formed is cross-braced in the same manner as the legs.

The iron bolts are covered by pieces of the same scantling as the

braces.

In the single derricks the queen legs can be connected by a trussed

beam similarly formed, or by a single balk carried across and laid on

the top transom.

[Illustration: FIG. 4.—PLAN OF TOP PLATFORM PARTIALLY COVERED]

If the span is considerable, struts can be carried from the queen legs

towards the centre of the underside of the balk to prevent sagging.

On the trussed beams thus formed, joists of 9 in. by 3 in. or ordinary

poles are laid about 3 feet apart.

They are laid parallel to one another, and in a direction at right

angles to the truss or single beam forming the back support of the

platform.

The centre joists are continued to the ends of the balks which project

beyond the king leg.

The advantage of having continued the top balks can now be seen, as it

gives greater area to the platform immediately round the engine.

The boards 9 in. by 1-1/2 in. are laid at right angles to the joists.

Another way of forming the platform is to cover only partially the

surface between the legs. In this case two additional joists, 6 in.

by 6 in., are thrown across the king leg (see fig. 4), the boards not

extending beyond their length.

When this is done, the workmen reach the platform from the

communicating ladder which usually passes up a queen leg, by means of a

run two boards wide. It is better to lay the larger platform, as, apart

from the question of safety to the men, it serves as a storage for coal

for the engine, the weight of which tends to keep the erection steady.

Double boards should be laid under coals or other heavy stores.

To reach the platform, ladders are fixed in different ways. They can

run up inside, or be fixed to the outside of the queen legs. In either

case they are nearly or entirely upright. A better method is shown in

fig. 5, and should be carried out wherever possible.

[Illustration: FIG. 5.—SHOWING METHOD OF FIXING LADDERS]

The derrick sleepers, two in number, are of balk timber, and lie across

the platform from beneath the engine bed to which they are connected,

to the centre of the queen legs.

The guys or stays, also of balk timbers, besides being connected to the

mast, are attached to the sleepers over the queen legs (see fig. 1).

To counteract the overturning force exerted by the jib and the material

lifted, the guys are chained down to the timber balk at the bottom of

the queen legs (fig. 1).

This balk supports a platform which is loaded with bricks or stones

more than equal to double the weight that will be lifted. The chain,

which works loose with the vibration of the scaffold, is tightened by

means of a screw coupler fixed in its length. The arrangement is as

follows:—Two lengths of heavy chain with large links at each end are

required. One length is carried round the sleeper and then taken down

the centre of the leg. The other length is taken round the balk which

is placed underneath the staging, and carried up through the load, when

the tightening screw can be applied and the correct tension brought up.

To prevent lateral motion the legs are cross-braced by poles or deals

between each leg as shown on frontispiece. The poles are tied to the

legs just beneath the platform and connected at their meeting point.

When crossing they should be at right angles to each other.

Deals 9 in. by 3 in. can take the place of the poles if required, bolts

in this case being used instead of tyings.

At the building of the new Post Office, Leeds, 1893, a different method

of raising the platform for the crane was adopted. The legs, instead

of being framed, consisted of a single balk of timber strutted on

each side from the ground level, the sleepers and guys being firmly

attached to the standards themselves.

When erecting long ranges of buildings it may be more convenient to

have the derrick mounted upon a travelling bogie than to dismantle the

structure in order to re-erect at another point.

Fig. 6 illustrates the system, the travelling power being usually

manual. The arrangement is suitable for small derricks, and is employed

where the crane is erected outside the building.

[Illustration: FIG. 6.—SHOWING STAGING MOUNTED ON TRAVELLING

BOGIE]

Another method of using travelling cranes is to erect a platform as

shown in fig. 7.

The standards, which may be of balk timber or built up, as previously

shown, are about 10 feet apart longitudinally and 20 to 30 feet

transversely. They stand upon sills of the same section where the

foundation is not solid. On the head of the standards, the runners are

laid connecting all the standards in the same row.

Head pieces may be fitted between the standards and runners; this

serves to distribute pressure. All the connections are securely made by

dog irons, bolts, and straps. The stability depends entirely upon the

bracing, and this, it is important to note, should be between each bay

longitudinally, and at least every second bay transversely.

[Illustration: Front Elevation

End Elevation

FIG. 7.—ELEVATION OF DERRICK STAGING]

Timbers placed as A in fig. 7 give rigidity to the standards by

preventing flexure, and are necessary when the lengths of the uprights

exceed 30 times their least diameter.

The deals used for braces are bolted to the standards; for poles, tying

is resorted to.

=Working Platforms.=—The working platforms used in conjunction

with overhead or overhand work depend upon the requirements of the

building.

By over head or hand work is meant that the material upon which the

mechanic is to be employed reaches him from over head or hand.

When no outside scaffolding is needed, the platforms are laid upon

the floor joints in the interior of the building, being raised upon

trestles as the work proceeds, and until the next floor is reached.

Light forms of scaffolds, as the ordinary masons’ and bricklayers’ pole

scaffolds, are now frequently used as working platforms in connection

with the Scotch system.

=The South Country System.=—This system is divided into two

classes according to the strength required. For the first, square

timbers are used; for the second, poles are employed. The scaffolds

built of square timbers are known as gantries and stagings, and the

pole erections are termed bricklayers’, and masons’ or independent

scaffolds.

=Gantries.=—The term gantry was originally given to erections

constructed with a view to the easy carriage of heavy material, but of

late it has also come to mean a structure arranged to support lighter

forms of scaffolding over footpaths which have to be kept open for

public use.

[Illustration: FIG. 8.—ELEVATION OF GANTRY FOR TRAVELLER]

[Illustration: FIG. 8A.—END ELEVATION OF GANTRY SHOWN IN FIG.

8]

1st. Gantries for transport of material, commonly called travellers.

Figs. 8 and 8a show the general construction.

The distance between the outer rows of standards and the wall depends

upon circumstances. If possible, the space should be allowed for a

cart-way, as the material can thus be brought quite close to the work

before being lifted. If, owing to adjacent footpaths or any other

reason, this cannot be done, the uprights should be placed close to the

wall on either side, the material being lifted at the end of the gantry

or other convenient spot, over which the lifting gear can be brought.

The standards of square timber for the gantry are from 6 in. to 12

in. square, and are erected upon sleepers, or, as they are sometimes

termed, sills laid in the same direction as the run of the scaffold.

One row of standards is placed on each side of the wall. The standards

are placed 8 to 10 feet apart. On the top of the standards runners are

fixed connecting each standard in the same row. Sills, standards, and

runners should be of the same sectional area. The runners are strutted

on their underside, from the standards by pieces of, at least, half the

sectional area of the supported timbers. If the struts are of equal

size to the runners, double the weight can be carried.

The cleats from which the struts rise, are simply spiked to the

standards, but if designed to carry excessive weights they are slightly

housed in. As the space between each row of standards has to be kept

open for the building, no cross bracing can be allowed except at the

ends. Strutting is therefore resorted to in order to give stability.

The struts, one to each standard, are bolted to the upright near the

top, and again to a foot block driven into the ground. Other methods of

fastening down the bottom ends of the struts are shown in fig. 9; the

use of each depends upon the nature of the soil.

Struts are also fixed at the ends to prevent lateral movement. Head

pieces, or corbels, as they are sometimes termed, are occasionally

inserted between the standards and runners, and serve to distribute

pressure.

Straining pieces spiked on the underside of the runners, for the struts

to pitch against, are used when the standards are considerably apart.

[Illustration: FIG. 9.—FOOTING BLOCKS FOR STRUTS]

Rails upon which the travelling engine or traveller can move are laid

on top of the runners, and are turned up at the ends of the platform to

serve as buffers to the engine platform.

[Illustration: End Elevation

Side Elevation

FIG. 10.—ELEVATION OF TRAVELLING GANTRY]

The engine platform consists of two trussed beams of timber about 3

feet apart, connected at their ends with short pieces of the same

scantling, and fitted with grooved wheels to move upon the rails.

Rails are also laid upon each beam and serve for the traversing motion

of the crab. Movement of the traveller is obtained from the crab,

which is worked either by manual or steam power, and acts through a

system of shafting and geared wheels. Movement in three directions is

necessary from the crab: vertically for lifting, and horizontally in

two directions, transversely and longitudinally. Travellers are made up

to 50 feet wide and any required length.

Another method of building travellers is shown in fig. 10.

In this case, the rails upon which the traveller moves in a

longitudinal direction are fixed on sleepers on the ground level,

and the standards and runners of the first example are not required.

In their place is constructed a triangulated system of balk timber

framing. The platform is fixed to the head pieces, and is braced as

shown. Less timber is used in their construction, but owing to the

greater weight a steam winch is required to impart motion.

=Gantries which serve as a base for lighter forms of

scaffolding.=—These erections are in reality elevated platforms,

and allow of a clear way for a footpath where required. They are

constructed of two frames, placed apart according to the width of the

path over which the platform stands (fig. 11).

The method of erection, so far as the side frames are concerned, is

the same as for the first example of travelling gantries. Stability

is, however, gained by cross-bracing as shown in figure, thus making

strutting unnecessary. The platform can be laid by placing short boards

9 in. by 3 in. across the runners when the platform is narrow. It is

more usual, however, to place joists 10 in. by 2 in. across, and on

these to lay the boards longitudinally. The joists average 2 to 3

feet apart, the braces are about 2 in. by 7 in. On the outside of the

scaffold, parallel to the sills, balk timbers are placed forming a

'fender’ to prevent the vehicular traffic from injuring or disturbing

the erection.

[Illustration: Front Elevation

End Elevation

FIG 11.—GANTRY OR ELEVATED PLATFORM OVER FOOTPATHS]

=Stagings.=—Stagings are erected in a manner similar to travelling

gantries, but are carried more than one storey high (fig. 12). It is a

form of scaffolding rarely seen, more especially since the introduction

of the Scotch derrick system. The timbers are erected to the height of

the first runner in the same manner as the frames in fig. 11. In order

to carry the scaffold higher, horizontal pieces are laid across the

scaffold, over the standards, and are made to project 9 or 10 feet on

each side of the runners.

On these beams, uprights, as in the first tier, are raised, being

connected in like manner, longitudinally by transoms. The rising tiers

of standards are strutted by timbers A A, rising from the

projecting portion of the beam called the footing piece, which serves

in the same manner as a footing block. The footing piece is supported by

struts, B B, rising from the lower standards. The struts B

B are in two pieces, being bolted to the sides of the footing

pieces and uprights. This allows the shores A A to pass

between them.

[Illustration: Front Elevation

Cross Section

FIG. 12.—EXAMPLE OF STAGINGS]

Strutting within the bays formed by the standards is carried out on

each tier with the exception of the top, where braces are fixed, as

shown at C.

On the top runners rails are laid for a traveller.

In constructing the foregoing square timber erection, note should be

taken of the following points:—

That the uprights of the upper tiers should stand immediately over

those of the lower tiers, in order to prevent cross strains on the

runners.

That the timbers should fit as evenly as possible, as thereby the whole

erection is rendered more stable.

That joints between the runners should occur immediately over the

standards.

The several parts of this structure, if for temporary purposes, can

be connected by dog irons; if for a more permanent use, by bolts and

straps.

POLE SCAFFOLDS

=Bricklayers’ Scaffolds.=—A bricklayer’s scaffold consists of a

series of upright poles or standards, to which are lashed horizontal

poles, termed ledgers. The ledgers and the wall of the building carry

the putlogs, on which boards are laid to support the workman, his

material, and tools (fig. 13).

The standards are first erected, and may stand singly or in pairs. In

a repairing job, unless of great height, and where there is no great

weight of material, single poles are sufficient.

Where double poles are required, the first pair are erected of

different lengths.

The short pole is termed a puncheon. The difference of length allows of

a lap in connecting the succeeding poles.

The lap should equal half of the full-length pole. The standards are

placed 6 to 8 feet apart, and from 4 to 6 feet away from the building.

[Illustration: FIG. 13.—ELEVATION OF POLE SCAFFOLD]

The butt-ends are embedded about 2 feet in the ground, which affords

some resistance to overturning. If they cannot be embedded, they

should be placed on end in barrels filled with earth tightly rammed.

As the building rises additional poles are added, being lashed to the

standards already erected.

If the standard is a single pole, the second pole, having a lap of 10

or 15 feet, stands upon a putlog placed close to the first pole for

that purpose (fig. 14).

The inner end of the putlog is securely fastened down to the scaffold

or inserted into the building.

If the standard is double, the rising pole is placed upon the top end

of the puncheon, and afterwards others are placed on end upon the

lowest free end of the standards already fixed.

[Illustration: FIG. 14.—METHOD OF FIXING RISING STANDARD]

As the standards rise, they are spliced or 'married’ together with band

ties.

At a height of 5 feet, this distance being the greatest at which a man

can work with ease, a ledger is tied across the standards to form a

support for the working platform.

Where a single pole is insufficient in length to form a continuous

ledger, two are joined in one of three ways.

[Illustration: FIG. 15]

In the first they are lapped over each other as fig. 15. This method

gives a strong connection, but prevents the putlogs being laid evenly.

[Illustration: FIG. 16]

The second way provides that the ledgers shall lap horizontally side by

side. This allows of evenness of line for the putlogs, but is not so

strong (fig. 16).

In both of these methods the lap should cover two standards, and not as

shown in fig. 17.

The third manner of connection (fig. 18) is the best. The ledgers butt

end to end. Underneath, a short pole is placed crossing two standards.

The tying at the standard embraces the double ledger. A band tie is run

round the supporting pole and the ends of the ledgers where they butt.

Great strength is obtained in this way and the putlogs can be evenly

laid.

Additional ledgers are fixed as the work proceeds.

[Illustration: FIG. 17]

On the ledgers, and at right angles to them, putlogs are laid, resting

outwardly on the ledgers and inwardly on the wall, where header bricks

have been left out for their reception.

[Illustration: FIG. 18]

The putlogs, which are placed about 3 or 4 feet apart, should be tied

to the ledgers and fastened by wedges into the wall. This is not often

done, but at least one putlog to every tying between standard and

ledger should be so treated.

Where the putlogs cannot be carried by the wall owing to an aperture in

the building, such as a window, they are supported by bearers fixed as

shown in figs. 19 and 20.

[Illustration: FIG. 19]

[Illustration: FIG. 20]

By wedging the inner end of the putlog into the wall, some stability

is given to the scaffold, but the connection cannot be considered

satisfactory, as the putlog would draw under very little strain.

Greater stability can be gained if the outer frame of the scaffold is

supported by one of the three methods given as follows.

[Illustration: FIG. 21.—SHORES AND TIES FOR DEPENDENT

SCAFFOLDS]

A shore or tie can be fixed between the erection and the ground as

shown in fig. 21, or, if there are openings in the wall, supports can

be fixed as ties shown in the same diagram.

The ties or struts should be placed to every third or fourth standard

at about 25 feet from the ground, and their fastenings made good.

Additional ties should be carried within the building at a greater

height where possible. The stability of the scaffold under loads and

cross wind pressure, depends greatly upon the ties or shores, and their

fastenings should be well made and kept in good order. The historical

instance of the mechanic who, to escape a shower of rain, stood upon

the inner board of the platform, and by leaning against the building

pushed the scaffold over, should have no opportunity of recurrence.

[Illustration: FIG. 22]

To stiffen the scaffold longitudinally braces are tied on the outside

of the scaffold in the form of a St. Andrew’s cross (see fig. 13).

They start from the lower end of one standard and rise obliquely across

the scaffold to near the top, or some distance up a standard in the

same run. Tied at their crossing-point, connections are made to all the

main timbers of the scaffold with which they come in contact. Braces

are fixed in all exposed situations, and generally where the scaffold

is more than one pole (30 feet) in height.

[Illustration: FIG. 23]

The only exception to effective bracing being carried out is where the

building, being of irregular form, creates many breaks and returns in

the scaffolding. It is obvious that where a scaffold butts against or

breaks with a return wall, the tendency to lateral motion is lessened.

The boards, which are placed longitudinally across the putlogs, can be

laid to lap or butt at their ends. When lapping, one putlog only is

required to carry the ends of two series of boards (fig. 22).

When butting, two putlogs are required placed about 4 inches apart

(fig. 23).

The second method is the better, as the boards are not so likely to

lose their place or to trip the workmen. If heavy work is in progress

the boards are laid double. As the building rises, the boards are

carried up to each successive platform, but each tied putlog is left in

its place.

[Illustration: FIG. 24.—MASONS’ SCAFFOLDS: END ELEVATION]

=Masons’ Scaffolds.=—Masons’, or independent scaffolds differ from

the bricklayers’ in that they have to be self-contained. Owing to the

different material of which the building is erected, the putlogs cannot

rest upon the wall. If openings were left for them, as in brickwork,

the wall would be permanently disfigured, more especially when ashlar

fronted.

In order to gain the necessary support two parallel frames of standards

and ledgers are erected along the line of wall to be built (fig. 24).

They are from 4 to 5 feet apart, the inner frame being as close to

the wall as possible. As a heavier material has to be dealt with, the

standards are placed closer together, say from 4 to 5 feet.

[Illustration: FIG. 25.—LANDING STAGES]

The ledgers and braces are placed as before, the putlogs now resting on

ledgers at each end, and not on the wall at the innermost end, as in

the bricklayer’s scaffold.

To prevent cross movement of the scaffold, an additional method of

bracing is available in this system. An inner and outer standard are

connected by short braces across each bay, as shown in fig. 24.

This method of cross-bracing can be continued to the top of the

scaffold, and the braces should be put in longitudinally, about 20 feet

apart.

The platforms laid on all pole-scaffolds are from 4 to 5 feet wide. It

is usually necessary, on anything but the smallest jobs, to keep this

width free for the workman and his material.

In order, therefore, to provide a platform on which the material can be

landed, it is convenient to erect, on the outside of the scaffold, an

additional platform from 5 to 10 feet square (fig. 25).

It is constructed of standards, ledgers, and braces, in like manner as

the scaffold to which it is attached.

The face-boards, as shown in this figure, should be fixed wherever

material is being hoisted, to prevent any projection of the load

catching under a ledger and upsetting.

=Connections.=—The members of pole scaffolds are connected by

cordage. The names of the various knots are given in Chapter V.

The arranging of the various timbers used in erecting scaffolds is a

dangerous occupation, and one requiring skill and considerable nerve on

the part of the workmen. In the majority of cases, the timbers on the

ground level are placed in position by manual labour only, shear legs

being used to facilitate matters. When the scaffold rises, advantage is

taken of any rigid member on which pulley wheels can be hung, and by

this means the succeeding poles, &c. are raised, manual dexterity and

strength being responsible for their final position.