SHEWING EXISTING DAMS AND LOCKS BETWEEN LONDON AND OXFORD]

The Thames, moreover, differs entirely from any of the foregoing rivers,

and must be considered on its own merits. The map (Fig. 1) shows that it

is already dammed and provided with locks at thirty-four places between

London and Oxford, the object of these dams being the maintenance of

a uniform level of water for navigation and boating purposes, and to

prevent the river running dry in the dry season and exposing the muddy

foreshores.

But from Teddington Weir to its estuary the Thames is tidal, and there

is no obstruction to the tidal flow except the bridges and the half-tide

weir at Richmond, which merely holds up sufficient water to cover the

foreshores for the advantage of the riparian owners and of boating.

_The Tidal Thames._

To understand clearly the conditions to be dealt with, it is necessary to

consider the daily movements of tide, the affluents, the dock and wharf

business and the traffic of the river.

The maps (Figs. 2 and 3) show the tidal river and estuary from Teddington

to the North Foreland. [Transcriber’s Note: It seems ‘Teddington’ here is

an error for either ‘London’ or ‘Southwark’; that’s what the maps show,

anyway.]

The river proper—that is, from Teddington to Gravesend—is forty-six miles

long, and averages one-third of a mile wide. Its depth at low water

varies from 6 ft. at Teddington to 10 ft. at London Bridge and 40 ft. at

Gravesend, and the rise of tide at London varies from 17 ft. to 21 ft.

and at Gravesend from 15 ft. to 19 ft., the current usually averaging

four knots per hour. At London Bridge the Spring tides flow 5 hours and

ebb 7½ hours; while at Gravesend they flow 6 hours and ebb 6½ hours.

The river winds about considerably. The straight line distance from

Teddington to Gravesend being thirty-three miles, shows that thirteen

miles are added to the river in its bends, some of which—as those at

Grays, Erith, Blackwall and Limehouse—are short and tortuous.

The longitudinal section (Fig. 4) of the river from Teddington to

Gravesend gives graphically all the data necessary for our purpose.

Ordnance Datum (O.D.) is the common datum line of the Government

maps. Trinity High Water (T.H.W.) is the water datum usually

adopted in the river. High and low water, ordinary and Spring tides

(H.W.O.T.—L.W.O.T.—H.W.S.T.—L.W.S.T.) are the levels of the respective

states of tide in the river at various points. The highest and lowest

known tides are also given, as well as the level of the river bottom and

the levels of the principal dock entrance sills and of the crowns of the

Thames tunnels, showing their depths below the river bottom.

_Tidal Wave._

The curved lines (in various forms of dotting) represent the levels of

the surface of water at various states of Spring tides and clearly show

the tidal wave which ascends the river and by its momentum and volume

raises the high-water level at the upper end several feet above that at

Gravesend.

_The Thames Estuary._

From Gravesend to the Nore is an immense triangular area with sandy

bottom, muddy foreshores and several deep channels running in the general

direction of the Essex coast line, that is, N.E. to the North Sea. The

area may be roughly estimated at 120 square miles, and the navigable

depth of the principal channels at from 60 ft. to 26 ft. at low water

Spring tides.

The volume of the estuary at high water Spring tides may be taken at

2600 million cubic yards, and at low water Spring tides at 1500 million

cubic yards, the volumes of the river from Gravesend to Teddington being

respectively 180 million and 80 million cubic yards, so that the volume

of tidal water entering the river each tide is about 100 million cubic

yards.

_Upland Water._

But there is a daily flow over Teddington weir—excluding the water

abstracted by the London water companies—varying during the year on the

average as follows:—

Cubic yards.

Jan. 11,800,000

Feb. 5,300,000

March 4,100,000

April 3,250,000

May 4,720,000

June 2,900,000

July 1,760,000

Aug. 1,590,000

Sept. 1,160,000

Oct. 1,900,000

Nov. 3,530,000

Dec. 8,230,000

Average daily flow, 4,186,000 cubic yards.

Below Teddington, numerous small affluents add to this volume of upland

water as follows:—

Cubic yards

per day.

The River Lea and Essex streams on the north bank 60,000

Streams in the Kent district 500,000

To this must be added a large quantity of spring

water rising in the bed of the river and land

drainage—quantity uncertain 1,000,000

Sewage effluents discharged at Crossness and Barking 1,176,000

Storm water overflow from London sewers 580,000

---------

Total upland fresh water daily average 7,502,000

This gives an average volume of 7½ million cubic yards of fresh water

descending and mingling with the oscillating tidal water of the river and

estuary, which slowly pushes the latter down into the North Sea. Taking

the high-water volume in the river as above at 180 million cubic yards,

the proportion of fresh water from the upland daily flow is 1/24th, and

therefore it will take 24 days to change entirely the water in the tidal

river.

Mr. W. P. Birch has shown that the combination of fresh water and sewage

which enters the river below Teddington remains in the river, oscillating

up and down with the tides for 45 days before it finally gets pushed out

into the North Sea.

[Illustration: THAMES MUD.]

In this way the discharge of effluents at Crossness and Barking passes

up and down in front of London for more than a month, and it becomes

apparent that the tidal action keeps the river continually saturated with

about 45 days’ soilage. It is no wonder, therefore, that the conditions

of colour, smell and turbidity of the river below Teddington are so vile

as compared with the Upper Thames, especially as to the above sources of

filth must be added the tidal current, which is so rapid that it keeps

the mud continually in suspension, washing it up at one time, depositing

it at another, but never permanently leaving it except in the places

unscoured by the upland water, such as docks, backwaters and places out

of the main current. It has been acknowledged by all writers that if

the upland water should be stopped the Thames would become a stagnant

oscillating ditch, because all filth discharged into it would remain in

it permanently.

The docks trap a very large proportion of this mud, and it costs at least

£60,000 per annum to clean it out. The mud enters with the locking water

and with that pumped to make up the basins.

_Effect of Dockisation on the River._

It is proposed to construct across the river at Gravesend a dam or

barrage similar to that across the Nile, containing numerous adjustable

sluices, and in addition a series of very large locks, the dam to hold up

the river to about Trinity high-water level (see section, Fig. 4).

The Great Thames Barrage · 第 6 / 11 题