CHAPTER VII

PART ONE.--STEEL WELDING

(=83=) The term “steel,” as used in the following pages, unless

otherwise specified, will be the term applied to wrought-iron and

low-carbon steels. High-carbon and alloyed steels are to be considered

only in advanced work and will therefore not be deemed a topic of

interest to the beginner in laying his foundation.

(=84=) The welding of steel is much more difficult than cast iron on

account of the many points which must be observed. In cast iron the

metal is brought to a molten state and may be worked in that condition

for some time without any apparent change in the characteristics of

the metal. A flux is used to break up the oxide or scale and the metal

will flow very easily. The flux is necessary because the oxide has a

higher melting-point than the iron itself. When working on steel, it

will be observed that just the reverse is true, that its oxide has a

lower melting-point than the steel and consequently no flux or cleaning

powder is necessary when working upon it.

(=85=) A large quantity of steel kept in a molten condition by the

flame acting upon it is very easily influenced. The same area is not

kept in a molten condition as with cast iron. The heat does not hold

to the vicinity of the weld nearly so much as in cast iron because of

the greater conductivity of the metal. If the flame is removed, the

molten metal will set almost immediately. This means that the flame

must be in contact with the metal at all times. It must be a strictly

neutral flame or else one of the two gases will be introduced into

the weld and its strength will be materially affected. The size of

this flame must be such that too great an area will not be covered,

yet enough must be covered to keep the metal along the line of the

weld in a molten condition. If a carbonizing flame is used, one which

has an excess of acetylene, such as was shown in Fig. 23, much carbon

will be taken up by the metal, producing a brittle weld. If the flame

is oxidizing, that is, contains an excess of oxygen which is noticed

by the shortening of the flame and an accompanying hissing sound, Fig.

25, the metal will burn and a white foam will appear on the weld like a

milky white glue. This tends to weaken the weld. This same effect will

be in evidence if too large a tip is used. On the other hand if the

tip is too small not enough heat is obtained and the oxides and other

impurities which may be present will not be allowed to float to the

surface but will be trapped in the weld.

(=86=) The filler-rod used on steel should be as near the same grade,

if not better than the metal to be welded and should be very low in

its carbon content. A pure grade of soft iron wire or mild steel will

make a very good filler-rod for ordinary purposes. The size of this

filler-rod is very important, for it should fuse at the same time as

the metal being worked upon, and unless it does this the weld will not

be satisfactory. If the filler-rod is too large it will not be at the

fusion point when the work is, and will not fuse with it. If the rod is

brought to a melting-point the work will have too much heat and will

burn. On the other hand, if the filler-rod is too small, it will burn

up before the work is at the fusion point, or in other words, the work

will still be too cold when the rod is melted.

(=87=) There are many different methods of executing a steel weld, and

it has been noted that very few experienced welders handle their steel

in the same manner. Most of these methods are very difficult to learn

and can be perfected only after years of practice. However, a simple

method which will produce results is thought the most advisable for the

beginner. A careful examination and study of this point has brought

out the following method, which is very easily picked up and which

dispenses with most of the torch movements that are generally advocated

by the old time welders.

[Illustration: FIG. 57.--Preparing and Heating Steel before Welding.]

(=88=) When welding two pieces of steel bars, the cross-section of

which will measure one-half inch by three inches, they are beveled off

and prepared in the manner illustrated in Fig. 57, either by means of

a chisel, file, or by the use of a grinding wheel. About an eighth

of an inch of the original stock is left on the bottom side and the

angle formed from these two places when brought together, should be 90

degrees. When the pieces have been prepared and placed in the position

shown in the illustration, the neutral flame is then brought down at

right angles to the plane of the metal, so that the end of the cone

will just lick the surface. It is moved up and down upon each side of

the part to be welded until each piece is brought to a red heat, for a

distance of at least one inch back. The position of the torch during

this operation can be seen in Fig. 57. From this time on, the operator

should work as rapidly as possible, for the quicker the fusion of

the metal is brought about, the less oxide or scale will appear and a

better weld will result. The description of this process may take some

length but the actual fusion not nearly so long.

[Illustration: FIG. 58.--In Welding Steel, the Beginner Should Fuse His

Pieces together along the Bottom with the Torch Flame, Adding no New

Metal. The Metal on Both Sides of the Torch Flame is Melted together

until a Small Pool of Molten Metal Appears, then the Torch is Twisted

Smartly away, as Shown by the Arrow, and the Metal Allowed to “Set” for

an Instant before Proceeding along the Line of Weld.]

[Illustration: FIG. 59.--Method of Adding “Filler-rod” in Welding

Steel. Note that the Rod is Worked behind the Flame.]

(=89=) When the red-hot stage is reached, the neutral flame is brought

down to the very lowest part of the “V” at the side nearest the

operator and held there until the metal has melted and is about to

collapse. The flame is then quickly twisted away for just a second to

let the metal set. Perhaps this operation will fuse about one-half

inch or less along the bottom of the “V.” This same operation is

repeated along the line of weld until the whole piece is fused along

the bottom. It will be noted that no filler-rod has as yet been used.

After the last portion has been fused, the flame is brought back

to the starting-point and played not only on the bottom, which has

already been fused, but on the sides of the “V” as well, bringing an

area of about one inch in diameter to a molten condition. The tip

of the welding torch is held in a vertical position all this time

to introduce as much heat into the weld as possible. During this

operation the filler-rod, which should measure three-sixteenths or

one-quarter inch in diameter, is picked up by the operator’s free hand

and its end brought near the heat of the flame so that it may be warmed

and will not chill the metal when introduced into the weld. When the

melted metal is running freely, the tip of the welding torch is slowly

inclined in the direction of the part to be welded and is advanced

along the “V-ed” out portion at this angle as rapidly as the metal can

be made to melt. This position is shown in Fig. 59. It will be noted

that as the flame advances along the line of the weld the molten metal

will mount up behind it of its own accord, providing the metal is in

a molten condition, when the flame passes over it. During this period

the filler-rod is stirred into the molten metal in a circular movement

which should be in back of the torch as much as possible. This means

that the torch comes in contact with the filler-rod but very little

and the rod is melted, not by the flame, but by the molten metal of

the piece being welded. It will be noticed at times, when too much

metal has been welded and the torch is not advancing rapidly enough,

that some of the molten metal will run ahead of the flame, into that

part of the “V” yet to be fused, and to the unwary student this will

be looked upon as a safe place to add his filler-rod. However, when

the piece is broken and the cross-section of the weld examined, it

will be found that in this part of the weld, the metal has only been

laid on and not fused. The beginner should watch this operation and

see to it that this molten metal is not permitted to run ahead of his

torch, an act which he can overcome by the proper manipulation of his

filler-rod, which really governs all the melted metal behind the flame.

If not enough metal has been added to fill in the “V” to the proper

thickness, this operation can be repeated until enough metal has been

added. By practicing this method the student can be taught to execute a

very successful weld and reinforce it all in one operation without any

chance of burning his filler-rod or lapping his metal. More practice

is required to successfully weld steel than most other metals and the

beginner should not be discouraged if it takes him some time to conquer

this metal. It should be forcibly impressed on the student that the

metal must be in a molten condition before the filler-rod is added, or

else it will stick and prevent his working readily and in addition will

produce a very faulty weld. Fusion is the thing to bear in mind for

without it success cannot be expected.

[Illustration: FIG. 60.--This Method of Adding the “Filler-rod” when

Welding is not Recommended for the Beginner.]

(=90=) While outside appearances should not be considered as a prime

requisite, when beginning it is always well to add more metal than is

really necessary in order to reinforce the weld as much as possible. It

cannot be expected, however, that a steel with the same cross-section

as the original will possess the same properties and be as strong,

for a weld is only a casting unless treated otherwise and the steel

or wrought iron used in the specimens is of rolled stock. If too much

metal has been added and dressing down is necessary, the student will

find that by using a slightly oxidizing flame the surplus metal can be

burnt away very rapidly and a very good-looking job can be executed

much more rapidly than if a neutral flame were used. It is well to

remember, however, that this is used only in dressing off pieces and in

places where the strength of the weld is not to be jeopardized.

(=91=) When advancing in steel work, it will be noticed that the same

provision for contraction and expansion is not considered in as great

proportions as on cast iron, and the reason is quite evident. In cast

iron we find the metal is very brittle and will not give without

breaking, whereas on steel it is more ductile and will twist and bend

before breaking. This does not mean, however, that the important points

of expansion and contraction are to be neglected in steel work, for

they are very important, as we shall see later on.

PART TWO.--STEEL WELDING

(=92=) It is still supposed that the beginner knows very little about

the various kinds of metals, or methods of distinguishing between them.

This is of great importance and should at once be overcome, as he will

not at all times have someone over him to diagnose his case and tell

him the proper procedure. For instance, were he to be given a piece

of cast steel to weld, thinking that it was cast iron, he would use a

cast-iron filler-rod in executing his weld. The results of such a weld

would not be very favorable, and the same would hold true if a steel

filler-rod were used on cast iron. An occasional glance at the table

in paragraph 67 will acquaint him with the various tests to make when

deciding upon the nature of the piece to be worked upon. The tests

should be applied in every doubtful instance. When working on cast

steel, a student may think that he must have a cast-steel filler-rod,

but this is an exception to the general rule and he can use the same

style filler-rod as he would employ on ordinary steel work. It might

be mentioned here that when working on alloyed and high-carbon steels,

the filler-rod generally contains some of the alloy or carbon which

will tend to replace that destroyed by the action of the flame in the

original metal.

(=93=) In welding cast steel the same procedure takes place as

previously described for steel, and it should present no real

difficulties after that process is understood. There may be more sand,

oxide and other impurities present on account of the nature of the

metal, but these can all be worked out if plenty of heat is applied.

At times, when working in steel, it will be found that there may be a

small hole develop in the center of the weld and as the torch is worked

into this hole it is found that it goes down a short distance and

seemingly refuses to be worked out. This is what most welders call a

“crater,” and is caused by the metal at the bottom not being hot enough

for the surrounding melted metal to fuse it. When found they should be

removed before adding any more metal. By playing the torch flame around

and around it, so that the heat may be transmitted to the bottom of the

“crater” and it brought to the melting-point like the surrounding metal

and suddenly jerking the torch away, it will disappear. “Craters”

are generally formed during the first part of the weld, especially if

the “V” is narrow, and they are hard to handle when deep. Under no

circumstances should the filler-rod be melted into them in trying to

make them disappear, as this will only mean covering them over.

(=94=) Some welders find that hard spots develop in their welds which

they have difficulty in overcoming, and it is a very serious handicap

when the weld is to be machined, for ofttimes it will break very

expensive tools and leave a portion of a drill or die broken off in

the metal. It is probably safe to say that the principal cause of hard

spots in steel welds is due to lack of heat. This, if given careful

thought and consideration, will be brought home forcibly to the welder

as he proceeds in his work, for the lapping of metals, trapping of

oxides, “craters,” too rapid cooling, etc., may all be directly

attributed to a lack of sufficient heat. If the metal is in a molten

state, all impurities will be brought to the surface, for they are

bound to be displaced by the weight of the metal, the same as corks in

a barrel will float to the top if water is introduced. The water in

this case has a greater specific gravity than the corks.

[Illustration: FIG. 61.--The Open Ends on long Steel Welds will Overlap

as the Welding Progresses if Improperly Started.]

[Illustration: FIG. 62.--Showing how Open Ends of Steel pieces are

Spread Slightly to Overcome Lapping of Ends in Making Weld.]

(=95=) In welding on sheet iron and steel, many operators will find

that they have more difficulty in executing a successful weld than

on slightly heavier work. This is no doubt due to the thin nature of

the work and the ease with which it may be burned or carbonized if

the operator is not alert. When working on such material a very small

filler-rod is used if thought necessary but this rod must be as free

from impurities as possible. When working on a long seam such as may be

encountered on a steel tank, it will be noticed that in welding from

one end along the seam that the metal ahead of the flame will tend to

overlap as shown in Fig. 61. This may be overcome by tacking (that is,

fusing the metals together), at various points before starting the

weld, or the parts ahead of the torch can be separated as is shown in

Fig. 62 and held this way by using a wedge. This is moved along as the

weld advances and permits the edges to close together. Another method

used by manufacturers who make a specialty of this work is to construct

a jig which clamps the ends rigidly and they are welded while in this

position. This phenomenon in steel welding will appear rather strange

to the welder who has had some experience on thin cast-iron work,

such as oven doors and the like. In these he found that as his weld

advanced, the welded portion before him would separate, and when he had

welded about four inches or so it would be necessary for him to jump

his flame back to the beginning of his weld and heat up that portion,

in order to close up the cracks before him previous to his continuing

the work. This is illustrated in Fig. 63. This may be explained by

the fact that steel is a very ductile metal and when it is fused, the

expansion is taken care of internally by the two edges combining. Then,

in cooling, the metal contracts, an action much more rapid in steel

than in cast iron, and draws the edges of the steel plates past each

other so that they overlap. In cast iron, which is rigid, the edges

are expanded by the fusion of the metal and this space is then filled

up with new metal, holding the edges apart. As the weld progresses the

metal ahead of the torch is pushing out, and that behind is cooling

off, which acts as a lever on each side to open up the unwelded ends.

[Illustration: FIG. 63.--This Illustration Shows how the Open Ends of

Thin Cast-iron Pieces Spread apart as the Weld Progresses. To Close the

Edges together, Jump the Torch Flame from _B_ to _A_; as _A_ heats up,

_B_ Cools and the Lever-like Action Closes the Opening.]

(=96=) To weld a broken automobile frame successfully the body of the

car should be raised if necessary, to keep it from burning and all

pipes, wires and gasoline leads protected with a covering of asbestos

paper. Plenty of room should be allowed, so that the welder may have

easy access to the break, and the frame should be jacked up on both

sides of the break until the frame is in proper alignment. Then

weld the crack from the outside, working across the top, then down

the side and across the bottom, reinforcing a little if necessary on

all sides but the bottom. Then repeat this operation on the inside,

reinforcing at all points. Then take a strip of steel about one-eighth

or one-quarter inch thick and six or eight inches long and as wide as

the bottom of the frame. This piece should be welded securely to the

bottom of the frame with the former break in the middle of the strip. A

cut representing this job is shown in Fig. 64. By this method the frame

can be made stronger than originally.

[Illustration: FIG. 64.--A Good Method of Reinforcing a Weld on an

Automobile Frame is Here Shown. The Patch as Pictured Here is only

“Tacked On.” It Should be Welded Securely to the Bottom of the Frame on

all Four of its Edges.]

PART THREE.--STEEL WELDING

(=97=) Aside from the difficulties already mentioned in steel welding,

there are many others. A few of these will be taken up in order to

let the beginner know how to approach the various problems which

may confront him. But in no wise is this to be considered to be a

treatise on advanced work. Ofttimes the question arises, Can springs

be successfully welded? Now, while springs have been welded, and they

have been tested out thoroughly, yet the practice of spring welding

with the oxy-acetylene flame is not to be recommended. There are

those who will weld leaf springs, such as are found on automobiles,

and will apply rapid blows with the hammer, while their weld is still

in a heated condition and then plunge the spring in water or oil to

harden it and the weld. A close observer will readily see why this

procedure is not correct. Springs of this nature are made up of metal

which takes a uniform hardening, and were it not so they could not be

considered springs. Now, if there is a fracture and a foreign metal,

which under no circumstances can be expected to take the same hardening

as the rest of the spring, is introduced into the weld, it can easily

be seen why a fusion of this kind is not to be relied upon. If it were

possible to diagnose or take an analysis of the metal in the spring

and use a filler-rod which, after being acted upon by the flame,

would come out the same as the metal in the spring, then some success

might be expected, but until that time, welding of springs will not

be encouraged. Unless perchance the break is of such a nature that it

can be reinforced readily and is in such a position that a resilient

quality is not necessary.

[Illustration: FIG. 65.--Building Up Worn Shafts.]

(=98=) Work on crank-shafts often causes perplexity on the part of

the beginner, for he usually hears this matter discussed pro and con.

Crank-shafts of four inches in diameter can be successfully welded

with the oxy-acetylene flame, and even larger, if correct methods are

employed. There are many points which the welder considers before

deciding whether a weld of this nature is advisable. Of course the

usability of the piece after it has been welded is the main issue

when executing any kind of a repair job. Now, a crank-shaft will

generally break in either of two ways; by some external force, such

as a connecting rod breaking loose, or by crystallization, which is

usually due to fatigue. Now, in the latter case, ofttimes the shaft

will break in the cheek of the “offset,” and possibly no part of the

shaft is thrown out of alignment. When such is the case, welding is

usually recommended and the shaft may be brought back to a useful state

in very quick order. However, in the former case, the shaft is apt to

be sprung, and while it could be welded, the machine work necessary to

restore it to normal requires much time, and it has been known, where

after spending a matter of days in trying to get proper alignments,

work was scrapped as useless. So it is entirely up to the welder in

work of this kind to determine whether the job is worth while or not.

There are certain parts of a crank-shaft upon which welding work can be

done with a marked degree of success, such as building up worn bearings

and the like. In doing work of this kind it is recommended that the

welder fuse his metal in a line parallel to the center line of the

bearing, seeing to it that he has a perfect fusion between the surface

of the bearing and the metal he is fusing and adding plenty of metal,

to insure enough being used, so that no low spots will show up when it

is machined. It is considered that by adding the metal as suggested the

welder will hold his heat much better than if he attempted revolving

the shaft continually. Fig. 65 will show the method here outlined in a

very clear way.

[Illustration: FIG. 66.--Shaft Broken at End of Square Shank, its

Weakest Point.]

[Illustration: FIG. 67.--Broken Part of Shaft Removed and New Piece

Added, thereby Moving the Weld away from the Weak Part.]

(=99=) When working on shafts the welder will encounter such articles

as automobile propeller shafts and rear axles, which generally break

adjoining the square ends. He will no doubt wonder whether it is

advisable to weld this square end back on, or whether to try and build

up the shaft the desired length. Undoubtedly the point of fracture is

the weakest portion of the entire shaft, else it would not break there.

The execution of a weld at this point where no additional metal can be

added or any means of reinforcing used is not to be recommended. Fig.

66 will show the problem which confronts the welder, and Fig. 67 the

suggested means of overcoming the difficulty. By removing about four

inches from the broken end of the shaft and adding a new piece, about

ten inches long, of the same diameter, the weld will be removed from

the weak point; a heavier weld can be made, and the end can be machined

off to the desired size. This procedure is recommended on all jobs of

like nature.

(=100=) Occasionally case-hardened ring gears are brought to the welder

to have teeth built up or new ones added, and although the welder must

realize that the hardening is destroyed by the action of the flame,

yet he does not understand why it is necessary to reharden the gear. A

little thought on this subject will make him appreciate the fact that

if he destroys certain properties in metal which have been introduced

for a reason, these must be replaced if he would bring the job back

to normal. It would be like heating up a tempered lathe tool, or

cold chisel for that matter, and trying to use it before it had been

retempered. Therefore if hardening or temper is destroyed by the flame

it must be restored.

[Illustration: FIG. 68.--When Welding a Small Section to a Larger One,

the Flame of the Torch is Directed toward the Heavier of the Two.]

(=101=) If a weld were to break, it would be necessary for the welder

to remove all metal added in the first weld before attempting to

reweld. This is true of his own work as well as that of others which

he may be called upon to do. For no matter how good the surface may

appear, without a solid foundation no weld is of any value, and unless

he clears out all of the old metal he cannot be sure of the work. This

will apply not only to steel work, but to all metals, and it is a point

which should be borne in mind.

(=102=) At times there are jobs come up in which one piece of work is

to be fused to another which is much larger, and will absorb much more

heat during the weld. When handling such work, it will be necessary to

play the torch upon the larger piece most of the time, as shown in Fig.

68, in order to bring both pieces to a fusion point at the same time

and keep them in that condition.

(=103=) Once in a while it will be necessary for a welder to fuse cast

iron to steel or vice versa, and the question will arise as to which

filler-rod he will use. It has been found that a cast-iron filler-rod

can be used with success and of course when using a cast-iron

filler-rod, a cast-iron flux will be necessary. Work of this nature is

not very frequent.

PART FOUR.--STEEL WELDING

(=104=) When steel is in a melted condition, it seems to be in a very

susceptible state. It appears to absorb gases, and with constant

working an oxidation is in evidence which materially effects the

strength of the metal. When working on vanadium and other alloyed

steels, if kept in a molten condition too long, many of their principal

characteristics are destroyed. For this reason it is advisable to

execute steel welds just as rapidly as possible. While this is true

of most work, it is especially to be emphasized on steel. To assist

the welder in executing welds on large steel castings, the pieces

are generally preheated, so that the work will take less time, be

more successful, and save both oxygen and acetylene. When working on

preheated jobs, in order to get the desired angle on the filler-rod so

the welder may use it without discomfort, a light heat is played on the

filler-rod, a matter of six or eight inches from the end being fused

and then bent to an angle of 90 degrees, so that the operator may hold

the rod at some distance from his work and still introduce it in the

manner he desires. Some operators weld their cast-iron filler-rods

together, to get the desired angle as shown in Fig. 69, but this is not

as common as the steel method, probably because cast iron will not bend

and it requires some time to weld the rods together in this manner.

[Illustration: FIG. 69.--Kinks for Handling “Filler-rod” on Large Work

to Remove Welder’s Hand away from Heat of Flame.

(_a_) shows how the steel “Filler-rod” is heated by the torch flame

about 6 inches from the end and bent to the angle desired.

(_b_) illustrates how cast “Filler-rods” are handled. Since they will

not bend, they are welded in the T shape shown. First one side is used

in fusing, and then the other.]

(=105=) In some parts of the country boiler flues are acted upon and

eaten away by the impure water used, and when high prices prevail,

retipping is generally resorted to. A simple method in which they can

be satisfactorily and cheaply done is as follows: Cut off the poor end

until solid metal is reached, with a pipe cutter, which will tend to

“V” the work as it cuts and at the same time will squeeze the edge of

the pipe in. After cutting, this end of the flue is placed on the horn

of an anvil and the burr on the inside, which has been made by the

cutter, is flattened out. It is very important that the flue be of the

same size throughout in order to permit its being cleaned. It is then

placed in “V” blocks or a trough, made of angle iron, such as shown in

Fig. 70, and the new end which has been prepared in much the same way

is placed in the position shown in _A_ in the same figure. The piece

is tacked on at two or more spots and then laid aside until the whole

set of flues has been prepared in this manner. Then they are replaced

in the trough and welded, one after another, being turned at one end

by a helper, thus allowing the welder to do continuous work. Care must

be taken at all times that perfect fusion takes place between the flue

proper and the piece being added, yet at no time should the metal be

allowed to run on the inside of the pipe. More metal can be added than

is really necessary and can later be dressed down on a grinding wheel

to the desired size, which must be such that replacement of the flue

can be made. Various-sized pipes can be welded in much the same way

where no reducers are obtainable, the only change being that there must

be a step made in the trough which will permit the various-sized pipes

being lined up correctly. Jigs for the speeding up of manufactured

articles which are to be welded are always being brought out by the

ingenious workman and are to be encouraged whenever possible.

[Illustration: FIG. 70.--Showing a Simple Way to “Line-up” Flues when

Retipping. _B_ Represents the old Flue, and _A_ the New Piece to be

Added.]

[Illustration:

(_Courtesy of the Oxweld Acetylene Co._)

FIG. 71.--Welded Cracks between Staybolts.]

(=106=) In the repair of boilers many a feasible job has been given

up as impossible by the unthinking welder. Cracks have been found in

fire-box sheets around the staybolts which, as soon as they are touched

with the flame, seem to run and keep running. They really discourage

those who are not familiar with this class of work. Many such welds

have been executed and are apparently all right until tested, when

they give way and make the job worse than it was previously. The

trouble is in these instances that the welder has made no provision for

contraction and while the job might appear to be successful, yet the

internal strains exerted will not show themselves at the test. Many

boiler shops have found that the flat patch is not to be relied upon

and when a crack is found between two stay-bolt holes, such as shown in

Fig. 72, a round hole is cut as shown by the dotted line. A circular

plate is then cut slightly larger than this hole and after being

brought to a red heat, it is bellied by the use of a hammer or a set of

dies, so that it assumes the shape of a saucer and is called by many a

“dished” patch. Some idea may be had of such a patch from Fig. 73.

[Illustration: FIG. 72.--A Crack between the Staybolts in a Boiler

should be Cut Out as Shown by the Dotted Line, to Prepare it for a

“Dished” Patch.]

[Illustration: FIG. 73.--A “Dished” Patch.]

(=107=) The patch is placed in the sheet with the concave side toward

the operator and should be securely welded in place, adding as little

metal for reinforcement as possible, but seeing to it that a perfect

fusion is made between the patch and the sheet all the way through. As

soon as the weld is complete the torch is played upon the high part of

the patch, which is protruding, and as the weld cools off, sharp quick

blows can be applied to the center of the patch, which should be kept

in a heated condition until it is nearly flat. This will take care of

any contraction that might set up and is a very good way of handling

patches which do not exceed six or eight inches in diameter.

[Illustration: FIG. 74.--A “Corrugated” Patch.]

(=108=) A “corrugated” patch has been brought out more recently than

the “dished” patch, and as its name would indicate, it has corrugations

around at least three of its sides. While a “dished” patch is limited

in its scope and cannot be applied to square holes unless the square

holes be cut round, the “corrugated” patch knows absolutely no limits

as to size or shape. While its preparation is probably more difficult,

yet its purpose is the same, that is, to take care of the contraction

which takes place in sheets of metal where heat has been introduced.

To prepare a “corrugated” patch, a piece of metal which is somewhat

larger than the hole is taken and the corrugation is made by placing

two rods on one side and somewhat separated and between them on the

other side another rod. With this section of the patch heated to a red

heat, a drop hammer is played upon it and a corrugation effected.

Or an easier method is by the use of specially prepared dies, which

will turn out a patch in quick order. It must be remembered that

while the patch shown in Fig. 74 is only for a very simple job, which

is rectangular in shape, yet “L” shaped patches can be prepared and

handled in the same manner. When the corrugation has been introduced

into the patch, the latter is cut so that it will fit the hole, and it

is tacked in position with the bellied sides out. The method used in

applying a patch of this kind is to weld the uncorrugated side, then

start up the corrugated side and weld for two or three inches, then

play the torch upon the corrugation, adjoining the part welded, and

slightly hammer to assist in the expansion of the same; then return

to the weld, continuing it until the corrugation can again be played

upon. By doing this, when finished the patch will be flat and no signs

of the corrugations will be shown. While many patches of this nature

are in use giving the very best service, the welder who looks upon the

finished job cannot tell how it has been accomplished.

(=109=) While the methods here given seem only to apply to boiler

work, they are not so restricted and can be applied to tanks and

various vessels with success. However, when welding on tanks which

have contained inflammable gases or gasoline the welder is cautioned

to take every measure to safeguard himself, and while it is known that

much work is being done on such jobs, it is not recommended and in fact

quite the contrary. It is true that there are such methods as filling

the containers with water; cleansing with live steam, and so forth, but

the cautious man will refrain from working on these vessels even though

such measures have been taken. Gasoline has a faculty of penetrating

the pores of metallic surfaces, and although these vessels have been

emptied and have remained so a matter of a year, the gasoline is still

present to some extent, as is evidenced by the fact that as soon as

heat is applied and the molecules of the metal are expanded, the gas

is released in sufficient quantities to cause an explosion. This is

not in one instance only, but in many, so it has been thought best to

discourage any welding work on vessels which have contained gasoline at

any time.

[Illustration: FIG. 75.--Working a Vertical Weld on Steel, from the Top

Down.]

(=110=) While it is possible to weld cast iron on the vertical, by

the use of carbon blocks and so forth, the same kind of work can be

accomplished on steel with much ease, without the use of any blocks,

or materials other than the filler-rod and the welding torch. There

are two methods of handling vertical welds; welding from the top

down, or starting from the bottom and working up. The former seems

to be condemned by those who have never tried it, on account of the

carelessness which is apt to be used on work of this kind. However, for

the beginner, it is thought advisable to teach this method, as there

are many places where it can be used advantageously. The metal at the

top of the seam, such as a broken automobile frame, or the like, is

brought to a molten state and held there, not only by the velocity of

the flame, but also by the filler-rod, as is shown in Fig. 75. With

the choosing of a tip of the correct size, the melted metal can be

held under control with much ease, after a little practice, and it is

allowed to descend as soon as the metal below it is in the proper shape

for fusion. The filler-rod is added continually, for it is never lifted

out of the molten metal, merely stirred a little from side to side as

it descends. None of the melted metal is allowed to precede the flame,

and at all times the operator can see whether the edges to be fused are

at the right heat. As soon as the bottom is reached, the weld can again

be gone over if it is not thought strong enough, and reinforced as much

as desired. As soon as the operator is familiar with this method, he

will find that much more speed can be developed, less filler-rod lost

and less lapping done than by building up from the bottom.

(=111=) In welding over head there is a tendency on the part of

most welders to avoid the use of enough heat to bring their metal

to a molten state, for fear that it will drop upon them. It must be

remembered that lack of heat means poor welds and that the metal must

be in a molten condition whenever the weld is to be made. As soon as

a little practice is given to this kind of work, the welder will see

that the melted metal can assume some proportions without dropping off,

despite its weight. It has probably been noticed that on “sweating”

water tanks drops of water accumulate on the bottom of the tank and

do not fall off. It is the same sort of problem in the case of melted

steel. The adhesion of the molecules and the surface tension are the

forces that keep the metal from dropping.