CONDITION OF THE WORK.

1. _Preparation of foundation._--This consisted in placing a mass of

Portland cement concrete beneath the existing foundation, extending

downwards 131/2 feet; underneath and within the outer edge of the old

foundation 18 feet; and without this edge 23 feet; then, of taking out

the old foundation from beneath the shaft, for a sufficient distance

back to obtain a good bearing upon the new masonry which is built out

upon the slab first mentioned.

This work is so far advanced that it will be entirely completed by the

15th of June.

2. _Preparation for the shaft._--The other operations have consisted in

the erection of the interior frame-work for the staircases and elevator

within the shaft, which frame-work will be used in the construction of

the masonry; the collection of granite and marble for continuing the

shaft; and the preparation of the machinery for raising the stones to

the top of the shaft, and setting them in place on the walls.