Glen Canyon Dam, like all large Reclamation dams, is being built by
private construction companies that are awarded contracts by competitive
bidding. The prime contract, totaling $107,955,122, was awarded to the
Merritt-Chapman and Scott Corporation of New York City, April 29, 1957.
It provides for construction of the dam and powerhouse and is the
largest single contract the Bureau has ever awarded and probably the
largest for any type of construction project.
By June 1960, the contractor had completed the diversion and spillway
tunnels, lined them with concrete, built the coffer dams (temporary
earth structures diverting the river around the damsite during
construction), and excavated the foundation of the dam. First placement
of concrete in the foundation of the dam and powerhouse was observed by
public ceremonies at the damsite on June 17, 1960. Initial storage of
water behind the dam is scheduled for early 1962.
A $6,392,000 contract for the manufacture of eight 155,500-horsepower,
150-r.p.m., vertical-shaft hydraulic turbines for the powerplant has
been awarded to the Baldwin-Lima Hamilton Corp. Additional contracts for
generators and other adjuncts will be awarded later to equip the dam and
powerplant. Glen Canyon's first hydroelectric generating unit is
scheduled to go on line in 1964.