TABLE 25 SUMMARY PART 2

===+========+========+=======+=====+====+=====+==================+=======|

W | | | | UNAVOIDABLE DELAYS |

e | | | AVERAGE TIME | (NOT INCLUDED IN AVERAGE |

i o| | | PER RING. | TIME PER RING). |

g f| | |-------+-----+----+-----+------------------+-------|

h |Average | Time | | | | | | |

t i| No. of |mucking,|Shoving| | | | | |

r| cubic | per | and |Erec-| | | | |

o| yards | cubic |mucking|tion |Lost| | | Time |

n|per ring| yard | [T] | [U] |time|Total|Items |hrs min|

---+--------+--------+-------+-----+----+-----+------------------+-------|

O {| 41 | 0-14 | 9-53 | 5-07| |15-00|First bulkhead |160 00|

r {| 54 | 0-19 | 17-20 | 2-26|0-05|19-51|Second bulkhead |157 45|

d {| 37 | 0-09 | 5-39 | 2-47|0-63| 9-29|Grouting |200 00|

i {| | | | | | | | |

n {| 40 | 0-17 | 12-42 | 3-27|0-38|16-47|Blowout | 69 45|

a {| | | | | | | | |

r {| 24 | 0-05 | 1-58 | 2-29|0-22| 4-49|Waiting-heavy iron| 64 00|

y {|--------+--------+-------+-----+----+-----+------------------+-------|

{| 30 | 0-07 | 3-27 | 2-42|0-18| 6-27|Total |715 30|

{|--------+--------+-------+-----+----+-----+------------------+-------|

{| 36 | 0-11 | 6-40 | 2-52|0-15| 9-47|Per ring | 0 39|

---+--------+--------+-------+-----+----+-----+------------------+-------|

Hvy| 18 | 0-05 | 1-29 | 1-45|0-06| 3-19| | |

---+--------+--------+-------+-----+----+-----+------------------+-------|

All| 29 | 0-09 | 4-36 | 2-25|0-14| 7-15| | |

===+========+========+=======+=====+====+=====+==================+=======|

[R] Excavating ahead of shield.

[S] Shoving shield into silt with ... doors open.

[T] Including time for jacks.

[U] Including bolting time.

TABLE 26.--SHIELD-DRIVEN TUNNEL WORK, WEEHAWKEN SHAFT, RIVER TUNNEL

NORTH. Table showing the size of the gang, the amount of excavation, and

the time per ring taken for the various operations involved in building

tunnel through the several kinds of ground encountered; also the extent

and nature of all the unavoidable delays.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 37 / 55 题