TABLE 17.--COST OF CONDUIT WORK.

=========================================+==========+==========+=======

|Manhattan.|Weehawken.| Total.

-----------------------------------------+----------+----------+-------

Duct feet | 115,962 | 35,155 |151,117

-----------------------------------------+----------+----------+-------

Average Cost per Duct Foot.

-----------------------------------------+----------+----------+-------

Labor | $0.035 | $0.032 | $0.034

Material | 0.043 | 0.052 | 0.045

-----------------------------------------+----------+----------+-------

Total field charges | 0.078 | 0.084 | 0.079

-----------------------------------------+----------+----------+-------

Chief office and plant depreciation | 0.005 | 0.008 | 0.006

-----------------------------------------+----------+----------+-------

Total average cost | $0.083 | $0.092 | $0.085

=========================================+==========+==========+=======

When the haulage was up grade, 6 by 6-in. Lidgerwood hoisting engines,

with 10-in. single friction drums, and driven by compressed air from the

high-pressure lines, were used. Down grade, cars were moved and

controlled by hand.

The muck which came through the shaft at Manhattan was dumped into

hopper bins on the surface and thence loaded into trucks at convenience.

At the open cut, the muck was dumped into trucks direct. The trucking

was sublet by the contractor to a sub-contractor, who provided trucks,

teams, and trimmers at the pier. At Weehawken, arrangements were made

with the Erie Railroad which undertook to take muck which was needed as

fill. The tunnel cars, therefore, were dumped directly on flat cars

which were brought up to a roughly made platform near the shaft.

The hoisting at Manhattan was by derrick at Tenth Avenue and the open

cut, and by the elevator at the Manhattan Shaft. At Weehawken, all

hoisting was done by the elevator in the shaft.

The sand and stone were received at the wharves by scows. At Manhattan,

these materials were unloaded on trucks by an overhead traveler, and

teamed to the shaft, where they were unloaded by derricks into the bins.

At Weehawken, they were unloaded by an orange-peel grab bucket, loaded

into cars on the overhead trestle, transported in these to the top of

the shaft, and discharged into the bins.

The cement at Manhattan was trucked from the Company's warehouse, at

Eleventh Avenue and 38th Street, to the shaft, where it was put into a

supplementary storage shed at the top of the shaft, whence it was

removed to the mixer by the elevator when needed. At Weehawken, it was

taken on flat cars directly from the warehouse to the mixer.

Lighting.

Temporarily and for a short time at the start, kerosene flares were used

for light until replaced by electric lights, the current for which was

furnished by the contractor's generators, which have been described

under the head of "Power Plant."

The lamps used along the track were of 16 c.p., and were protected by

wire screens; these were single, but, wherever work was going on, groups

of four or five, provided with reflectors, were used.

Pumping.

Two pumps were installed at the Manhattan Shaft. They had to handle the

water, not only from the rock tunnels, but also from those under the

river. One was a Deane compound duplex pump, having a capacity of 500

gal. per min., the other, a Blake pump, of 150 gal. per min. They were

first driven by steam direct from the power-house, but compressed

air was used later. When the power-house was shut down, an

electrically-driven centrifugal pump was used. This was driven by a

General Electric shunt-wound motor, Type C-07½, with a speed of 1,250

rev. per min. at 250 volts and 37.5 amperes (10 h.p.) when open, and

22.9 amperes (6 h.p.) when closed, and had a capacity of 450 gal. per

min. To send the water to the shaft sump during the construction, small

compressed-air Cameron pumps, of about 140 gal. per min., were used.

At the Weehawken shaft two pumps were used; these dealt with the water

from the Bergen Hill Tunnels as well as that from the Weehawken Tunnels.

At first a Worthington duplex pump having a capacity of about 500 gal.

per min. was used. Later, this was replaced by a General Electric

shunt-wound motor, Type O-15, with a speed of 925 rev. per min. at 230

volts and 74 amperes (20 h.p.) when open, and 38.5 amperes (10 h.p.)

when closed. Its capacity was 240 gal. per min. During the progress of

the construction, the water was pumped from the working face to the

shaft by small Cameron pumps similar to those used at Manhattan. When

the work was finished, a subgrade reversed-grade drain carried the

water to the shaft sump by gravity.

The work in the Manhattan Land Tunnels was practically finished by May

1st, 1908, though the ventilating arrangements and overhead platform in

the intercepting arch were not put in until after the River Tunnel

concrete was completed, so that the work was not finished until

September, 1909.

The Weehawken Land Tunnels work was finished in July, 1907, but the

benches and ventilating arrangements in the Weehawken Shaft were not put

in until after the completion of the Bergen Hill Tunnels, and so were

not finished until August, 1909.

The reinforced concrete wall around the Weehawken Shaft, together with

the stairs from the bench level of the shaft to the surface, was let as

a separate contract; the work was started on September 15th, 1909, and

finished by the end of December, 1909.

Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The North River Tunnels. Paper No. 1155 · 第 20 / 55 题